Open this link on a larger screen to see the verification queue.
125 works across 1 implementing agency, recommended by 4 members of parliament. No allocation figure is published per district — every rupee below is summed from the works themselves.
The people a district authority actually supervises. Vendor concentration is counted from the payment records: an agency paying almost everything to one vendor is worth a question, not an accusation.
| # | Agency | Works | Completed | Sanctioned | To verify | Avg score | Top vendor |
|---|---|---|---|---|---|---|---|
| 1 | Cooch Behar(DISTRICT MAGISTRATE COOCHBEHAR_IDA) 5 high risk | 125 | 2 | ₹22.99 Cr | 72 | 40.5 | SAJAL KUMAR KAR 29% of spend · 11 vendors |
Whose funds paid for this district’s works.
| Member | Works | Sanctioned | To verify |
|---|---|---|---|
| Jagadish Chandra Barma Basunia COOCHBEHAR | 94 | ₹10.95 Cr | 54 |
| Nagendra Ray Sitting Rajya Sabha | 20 | ₹10.87 Cr | 11 |
| Manoj Tigga ALIPURDUARS | 10 | ₹1.03 Cr | 6 |
| Samik Bhattacharya Sitting Rajya Sabha | 1 | ₹15.00 L | 1 |
Sector read from each work’s description.
| Sector | Works | Sanctioned | To verify |
|---|---|---|---|
| Street Lighting | 79 | ₹5.18 Cr | 43 |
| Roads & Paving | 25 | ₹8.57 Cr | 14 |
| Education | 8 | ₹6.80 Cr | 7 |
| Community Buildings | 3 | ₹74.97 L | 2 |
| Water | 3 | ₹39.88 L | 1 |
| Boundary & Protection | 2 | ₹50.00 L | 2 |
| Equipment & Vehicles | 2 | ₹25.00 L | 1 |
| Sports | 2 | ₹39.01 L | 2 |
| Health | 1 | ₹15.00 L | 0 |
Patterns across an agency’s whole book of work. None of these move any individual work’s score.
Round figures are normal and similar works legitimately cost the same. One figure covering nearly every work is what this looks for, and it means the costing is worth seeing, not that it is wrong.
Ranked by score. Cost is judged against comparable works in this district and sector, so a high cost score means unlike its neighbours — not overpriced.
| Work | Agency | Status | Sanctioned | Delay | Cost vs peers | Score | Band |
|---|---|---|---|---|---|---|---|
| Construction of Paver Block road with GSB subgrade from Tors ₹8,245,381 against a ₹2,302,669 median for Roads & Paving works in COOCH BEHAR (258% above, 32 peer works) | Cooch Behar(DISTRICT MAGISTRATE COOCHBEHAR_IDA) | Recommended | ₹82.45 L | 188 d | +258% | 77.2 | HIGH |
| Construction of Paver Block road with GSB subgrade from A ₹6,496,211 against a ₹2,302,669 median for Roads & Paving works in COOCH BEHAR (182% above, 32 peer works) | Cooch Behar(DISTRICT MAGISTRATE COOCHBEHAR_IDA) | Recommended | ₹64.96 L | 311 d | +182% | 77.2 | HIGH |
| Construction of Paver Block road with GSB subgrade from Nat ₹8,617,886 against a ₹2,302,669 median for Roads & Paving works in COOCH BEHAR (274% above, 32 peer works) | Cooch Behar(DISTRICT MAGISTRATE COOCHBEHAR_IDA) | Recommended | ₹86.18 L | 311 d | +274% | 77.2 | HIGH |
| 1 Installation of Solar Street Light 57 Nos at road site of ₹2,843,160 against a ₹586,716 median for Street Lighting works in COOCH BEHAR (385% above, 155 peer works) | Cooch Behar(DISTRICT MAGISTRATE COOCHBEHAR_IDA) | Recommended | ₹28.43 L | 345 d | +385% | 77.2 | HIGH |
| Installation of 9 no Mini High Mast Solar Street Light Syste ₹5,280,444 against a ₹586,716 median for Street Lighting works in COOCH BEHAR (800% above, 155 peer works) | Cooch Behar(DISTRICT MAGISTRATE COOCHBEHAR_IDA) | Recommended | ₹52.80 L | 345 d | +800% | 77.2 | HIGH |
| seating furniture (Low and High Bench set) for Siddheswari K ₹19,950,000 against a ₹9,975,000 median for Education works in COOCH BEHAR (100% above, 14 peer works) | Cooch Behar(DISTRICT MAGISTRATE COOCHBEHAR_IDA) | Recommended | ₹2.00 Cr | 96 d | +100% | 65.5 | MEDIUM |
| Purchase of Books for Student of 7 number of Schools and 2 ₹19,596,140 against a ₹9,975,000 median for Education works in COOCH BEHAR (96% above, 14 peer works) | Cooch Behar(DISTRICT MAGISTRATE COOCHBEHAR_IDA) | Recommended | ₹1.96 Cr | 96 d | +96% | 64.7 | MEDIUM |
| Installation for the single unit Mini High Mast Solar Lighte 206 days beyond expected completion | Cooch Behar(DISTRICT MAGISTRATE COOCHBEHAR_IDA) | Recommended | ₹5.87 L | 206 d | 0% | 57.8 | MEDIUM |
| Installation for the single unit Mini High Mast Solar Lighte 206 days beyond expected completion | Cooch Behar(DISTRICT MAGISTRATE COOCHBEHAR_IDA) | Recommended | ₹5.87 L | 206 d | 0% | 57.8 | MEDIUM |
| Installation for the single unit Mini High Mast Solar Lighte 206 days beyond expected completion | Cooch Behar(DISTRICT MAGISTRATE COOCHBEHAR_IDA) | Recommended | ₹5.87 L | 206 d | 0% | 57.6 | MEDIUM |
| Installation for the single unit Mini High Mast Solar Lighte 206 days beyond expected completion | Cooch Behar(DISTRICT MAGISTRATE COOCHBEHAR_IDA) | Recommended | ₹5.87 L | 206 d | 0% | 57.6 | MEDIUM |
| ESTIMATE FOR CONSTRUCTION OF BLACKTOP ROAD FROM NH-31 NEAR H ₹5,925,309 against a ₹2,302,669 median for Roads & Paving works in COOCH BEHAR (157% above, 32 peer works) | Cooch Behar(DISTRICT MAGISTRATE COOCHBEHAR_IDA) | Recommended | ₹59.25 L | 188 d | +157% | 57.2 | MEDIUM |
| ESTIMATE FOR CONSTRUCTION OF BLACKTOP ROAD FROM BABUMIAH TO ₹5,697,372 against a ₹2,302,669 median for Roads & Paving works in COOCH BEHAR (147% above, 32 peer works) | Cooch Behar(DISTRICT MAGISTRATE COOCHBEHAR_IDA) | Recommended | ₹56.97 L | 188 d | +147% | 57.2 | MEDIUM |
| ESTIMATE FOR CONSTRUCTION OF BLACKTOP ROAD FROM HOUSE OF KHA ₹4,883,588 against a ₹2,302,669 median for Roads & Paving works in COOCH BEHAR (112% above, 32 peer works) | Cooch Behar(DISTRICT MAGISTRATE COOCHBEHAR_IDA) | Recommended | ₹48.84 L | 188 d | +112% | 57.2 | MEDIUM |
| CONSTRUCTION OF GUARD WALL AT GOLKUNDA POND OF OKRABARI HIGH ₹1,988,324 against a ₹960,000 median for Water works in COOCH BEHAR (107% above, 11 peer works) | Cooch Behar(DISTRICT MAGISTRATE COOCHBEHAR_IDA) | Recommended | ₹19.88 L | 188 d | +107% | 57.2 | MEDIUM |