Open this link on a larger screen to see the verification queue.
243 works across 1 implementing agency, recommended by 3 members of parliament. No allocation figure is published per district — every rupee below is summed from the works themselves.
The people a district authority actually supervises. Vendor concentration is counted from the payment records: an agency paying almost everything to one vendor is worth a question, not an accusation.
| # | Agency | Works | Completed | Sanctioned | To verify | Avg score | Top vendor |
|---|---|---|---|---|---|---|---|
| 1 | BIRBHUM(DISTRICT MAGISTRATE BIRBHUM_IDA) | 243 | 173 | ₹27.53 Cr | 8 | 14.8 | BIDYUT BHANDARI 18% of spend · 109 vendors |
Whose funds paid for this district’s works.
| Member | Works | Sanctioned | To verify |
|---|---|---|---|
| Asit Kumar Mal BOLPUR | 146 | ₹20.07 Cr | 4 |
| Satabdi Roy BIRBHUM | 95 | ₹7.20 Cr | 4 |
| Samik Bhattacharya Sitting Rajya Sabha | 2 | ₹25.48 L | 0 |
Sector read from each work’s description.
| Sector | Works | Sanctioned | To verify |
|---|---|---|---|
| Street Lighting | 85 | ₹8.69 Cr | 2 |
| Roads & Paving | 59 | ₹5.64 Cr | 1 |
| Education | 24 | ₹3.88 Cr | 0 |
| Community Buildings | 19 | ₹2.23 Cr | 2 |
| Water | 17 | ₹63.67 L | 0 |
| Religious & Cultural | 10 | ₹31.80 L | 0 |
| Drainage & Sanitation | 9 | ₹99.09 L | 0 |
| Equipment & Vehicles | 5 | ₹1.84 Cr | 0 |
| Sports | 5 | ₹2.13 Cr | 2 |
| Other | 4 | ₹43.60 L | 0 |
Patterns across an agency’s whole book of work. None of these move any individual work’s score.
An agency whose sanctions all arrive in the last quarter looks identical. This is a spending pattern, not a finding.
Ranked by score. Cost is judged against comparable works in this district and sector, so a high cost score means unlike its neighbours — not overpriced.
| Work | Agency | Status | Sanctioned | Delay | Cost vs peers | Score | Band |
|---|---|---|---|---|---|---|---|
| Construction Gallery shed at SDSA STADIUM under jurisdictio ₹3,454,681 against a ₹951,102 median for Community Buildings works in BIRBHUM (263% above, 27 peer works) | BIRBHUM(DISTRICT MAGISTRATE BIRBHUM_IDA) | Recommended | ₹34.55 L | 184 d | +263% | 51.1 | MEDIUM |
| construction of common work shed common covered siting Area, ₹2,000,000 against a ₹951,102 median for Community Buildings works in BIRBHUM (110% above, 27 peer works) | BIRBHUM(DISTRICT MAGISTRATE BIRBHUM_IDA) | Recommended | ₹20.00 L | 263 d | +110% | 51.1 | MEDIUM |
| Construction of P.C.C Road , Executive Agency - E.O Zella Pa ₹3,215,000 against a ₹500,000 median for Roads & Paving works in BIRBHUM (543% above, 91 peer works) | BIRBHUM(DISTRICT MAGISTRATE BIRBHUM_IDA) | Recommended | ₹32.15 L | 263 d | +543% | 51.1 | MEDIUM |
| Instalation of Solar Light, Executive Agency - Prodhan Budhi 167 days beyond expected completion | BIRBHUM(DISTRICT MAGISTRATE BIRBHUM_IDA) | Recommended | ₹2.50 L | 167 d | -36% | 50.2 | MEDIUM |
| Instalation of solar light, Executive Agency - Prodhan Budhi 167 days beyond expected completion | BIRBHUM(DISTRICT MAGISTRATE BIRBHUM_IDA) | Recommended | ₹2.50 L | 167 d | -36% | 50.2 | MEDIUM |
| Construction of Boundary Wall at Sukhbazar Eco PARK UNDER ,I ₹4,124,451 against a ₹2,342,930 median for Sports works in BIRBHUM (76% above, 8 peer works) | BIRBHUM(DISTRICT MAGISTRATE BIRBHUM_IDA) | Recommended | ₹41.24 L | 349 d | +76% | 45.7 | MEDIUM |
| Development of Adayasakti park at Bolpur Municipality ward n Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range | BIRBHUM(DISTRICT MAGISTRATE BIRBHUM_IDA) | Recommended | ₹30.60 L | 181 d | +31% | 42.6 | MEDIUM |
| Construction of boundary wall with main gate at LOKPARA MAHA Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range | BIRBHUM(DISTRICT MAGISTRATE BIRBHUM_IDA) | Recommended | ₹15.00 L | 349 d | 0% | 40.1 | MEDIUM |
| CONSTRUCTION OF FOOT PATH AND PARTITION WALL 0F DIGHIPUKUR A Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range | BIRBHUM(DISTRICT MAGISTRATE BIRBHUM_IDA) | Recommended | ₹15.00 L | 323 d | 0% | 39.8 | LOW |
| Construction of skill development centre at ILLAMBAZAR BLOCK Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range | BIRBHUM(DISTRICT MAGISTRATE BIRBHUM_IDA) | Recommended | ₹11.19 L | 190 d | +18% | 36.3 | LOW |
| Construction of main gate at PURNIDEVI COWDHURY GIRLS COLLEG 190 days beyond expected completion | BIRBHUM(DISTRICT MAGISTRATE BIRBHUM_IDA) | Recommended | ₹8.79 L | 190 d | -26% | 35.5 | LOW |
| Construction of BOUNDARY WALL at NOAPARA HEALTH CENTER. Exec 349 days beyond expected completion | BIRBHUM(DISTRICT MAGISTRATE BIRBHUM_IDA) | Recommended | ₹5.00 L | 349 d | 0% | 34.9 | LOW |
| Construction of extention building AT CHOTOTURIGRAM MADRASHA 349 days beyond expected completion | BIRBHUM(DISTRICT MAGISTRATE BIRBHUM_IDA) | Recommended | ₹5.00 L | 349 d | -58% | 34.9 | LOW |
| Construction of boundary wall and gate at mayureswar girls 349 days beyond expected completion | BIRBHUM(DISTRICT MAGISTRATE BIRBHUM_IDA) | Recommended | ₹5.00 L | 349 d | -58% | 34.9 | LOW |
| Installation of Chilled Drinking water Mechine, Gosainpur Hi 345 days beyond expected completion | BIRBHUM(DISTRICT MAGISTRATE BIRBHUM_IDA) | Recommended | ₹2.50 L | 345 d | -29% | 34.6 | LOW |