Open this link on a larger screen to see the verification queue.
193 works across 1 implementing agency, recommended by 3 members of parliament. No allocation figure is published per district — every rupee below is summed from the works themselves.
The people a district authority actually supervises. Vendor concentration is counted from the payment records: an agency paying almost everything to one vendor is worth a question, not an accusation.
| # | Agency | Works | Completed | Sanctioned | To verify | Avg score | Top vendor |
|---|---|---|---|---|---|---|---|
| 1 | YADADRI BHUVANAGIRI(DISTRICT COLLECTOR YADADRI BHUVANAGIRI_IDA) | 193 | 171 | ₹3.10 Cr | 4 | 13.9 | NARSIMHULU AKULA 24% of spend · 18 vendors |
Whose funds paid for this district’s works.
| Member | Works | Sanctioned | To verify |
|---|---|---|---|
| Chamala Kiran Kumar Reddy BHONGIR | 174 | ₹2.26 Cr | 0 |
| Ravi Chandra Vaddiraju Sitting Rajya Sabha | 18 | ₹78.79 L | 3 |
| Abhishek Manu Singhvi Sitting Rajya Sabha | 1 | ₹5.00 L | 1 |
Sector read from each work’s description.
| Sector | Works | Sanctioned | To verify |
|---|---|---|---|
| Street Lighting | 155 | ₹1.25 Cr | 2 |
| Community Buildings | 14 | ₹72.96 L | 0 |
| Roads & Paving | 9 | ₹44.88 L | 0 |
| Drainage & Sanitation | 8 | ₹35.96 L | 2 |
| Water | 2 | ₹6.63 L | 0 |
| Religious & Cultural | 2 | ₹8.98 L | 0 |
| Sports | 1 | ₹4.99 L | 0 |
| Health | 1 | ₹5.00 L | 0 |
| Education | 1 | ₹5.00 L | 0 |
Ranked by score. Cost is judged against comparable works in this district and sector, so a high cost score means unlike its neighbours — not overpriced.
| Work | Agency | Status | Sanctioned | Delay | Cost vs peers | Score | Band |
|---|---|---|---|---|---|---|---|
| Providing LED Street Lights 45 watts at Redlarepaka(V), Vali Completed work has no photographic documentation on record | YADADRI BHUVANAGIRI(DISTRICT COLLECTOR YADADRI BHUVANAGIRI_IDA) | Completed | ₹2.00 L | — | +167% | 49.9 | MEDIUM |
| Providing high mast lights at Laxmapuram Village, Ramannapet ₹500,000 against a ₹74,713 median for Street Lighting works in YADADRI BHUVANAGIRI (569% above, 287 peer works) | YADADRI BHUVANAGIRI(DISTRICT COLLECTOR YADADRI BHUVANAGIRI_IDA) | Recommended | ₹5.00 L | — | +569% | 45.4 | MEDIUM |
| Construction of RCC Drain at Anantharam(V)Bhognir(M), Yadadr Completed work has no photographic documentation on record | YADADRI BHUVANAGIRI(DISTRICT COLLECTOR YADADRI BHUVANAGIRI_IDA) | Completed | ₹9.00 L | — | +80% | 44.9 | MEDIUM |
| Construction of Side Drain from Kathula Kamalamma(H) to Kath 109 days beyond expected completion | YADADRI BHUVANAGIRI(DISTRICT COLLECTOR YADADRI BHUVANAGIRI_IDA) | Recommended | ₹4.99 L | 109 d | 0% | 40.8 | MEDIUM |
| Drilling of Borewell and Installation of Submersible Pumpset 93 days beyond expected completion | YADADRI BHUVANAGIRI(DISTRICT COLLECTOR YADADRI BHUVANAGIRI_IDA) | Recommended | ₹4.99 L | 93 d | 0% | 39.1 | LOW |
| Construction of Side Drain from Kotamarthy Bustand to Jitte 93 days beyond expected completion | YADADRI BHUVANAGIRI(DISTRICT COLLECTOR YADADRI BHUVANAGIRI_IDA) | Recommended | ₹4.99 L | 93 d | 0% | 39.1 | LOW |
| Construction of Side Drain from ZP High School Backside to N 93 days beyond expected completion | YADADRI BHUVANAGIRI(DISTRICT COLLECTOR YADADRI BHUVANAGIRI_IDA) | Recommended | ₹2.00 L | 93 d | -60% | 38.4 | LOW |
| PROVIDING OF STREET LIGHTS IN SIRIVENIKUNTA VILLAGE Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range | YADADRI BHUVANAGIRI(DISTRICT COLLECTOR YADADRI BHUVANAGIRI_IDA) | Recommended | ₹30,000 | 301 d | -60% | 35.9 | LOW |
| PROVIDING OF STREET LIGHTS IN GOLLAGUDEM VILLAGE Completed work has no photographic documentation on record | YADADRI BHUVANAGIRI(DISTRICT COLLECTOR YADADRI BHUVANAGIRI_IDA) | Completed | ₹1.00 L | — | +34% | 33.3 | LOW |
| PROVIDING OF STREET LIGHTS IN RAGHAVAPURAM VILLAGE Completed work has no photographic documentation on record | YADADRI BHUVANAGIRI(DISTRICT COLLECTOR YADADRI BHUVANAGIRI_IDA) | Completed | ₹99,855 | — | +34% | 33.3 | LOW |
| PROVIDING OF STREET LIGHTS IN GOLLAGUDEM VILLAGE Completed work has no photographic documentation on record | YADADRI BHUVANAGIRI(DISTRICT COLLECTOR YADADRI BHUVANAGIRI_IDA) | Completed | ₹35,000 | — | -53% | 30.6 | LOW |
| PROVIDING OF STREET LIGHTS IN RAGHAVAPURAM VILLAGE Completed work has no photographic documentation on record | YADADRI BHUVANAGIRI(DISTRICT COLLECTOR YADADRI BHUVANAGIRI_IDA) | Completed | ₹24,596 | — | -67% | 30.4 | LOW |
| Providing of LED Street Lights in Narayanapur village Completed work has no photographic documentation on record | YADADRI BHUVANAGIRI(DISTRICT COLLECTOR YADADRI BHUVANAGIRI_IDA) | Completed | ₹2.00 L | — | +167% | 29.9 | LOW |
| Providing of LED high mast Lights 2Nos in Telangana Resident Completed work has no photographic documentation on record | YADADRI BHUVANAGIRI(DISTRICT COLLECTOR YADADRI BHUVANAGIRI_IDA) | Completed | ₹3.00 L | — | +301% | 29.9 | LOW |
| PROVIDING OF STREET LIGHTS IN BIBINAGAR TOWN Completed work has no photographic documentation on record | YADADRI BHUVANAGIRI(DISTRICT COLLECTOR YADADRI BHUVANAGIRI_IDA) | Completed | ₹1.50 L | — | +101% | 29.9 | LOW |