85 works across 1 implementing agency, recommended by 5 members of parliament. No allocation figure is published per district — every rupee below is summed from the works themselves.
The people a district authority actually supervises. Vendor concentration is counted from the payment records: an agency paying almost everything to one vendor is worth a question, not an accusation.
| # | Agency | Works | Completed | Sanctioned | To verify | Avg score | Top vendor |
|---|---|---|---|---|---|---|---|
| 1 | WANAPARTHY(DISTRICT COLLECTOR WANAPARTHY_IDA) | 85 | 34 | ₹4.66 Cr | 15 | 24.1 | PRAGATHI CONSTRUCITONS 37% of spend · 18 vendors |
Whose funds paid for this district’s works.
| Member | Works | Sanctioned | To verify |
|---|---|---|---|
| Mallu Ravi NAGARKURNOOL | 31 | ₹2.13 Cr | 1 |
| D K Aruna MAHABUBNAGAR | 20 | ₹76.24 L | 0 |
| Damodar Rao Divakonda Sitting Rajya Sabha | 19 | ₹94.63 L | 11 |
| Ravi Chandra Vaddiraju Sitting Rajya Sabha | 12 | ₹51.47 L | 2 |
| Abhishek Manu Singhvi Sitting Rajya Sabha | 3 | ₹30.00 L | 1 |
Sector read from each work’s description.
| Sector | Works | Sanctioned | To verify |
|---|---|---|---|
| Street Lighting | 33 | ₹95.41 L | 5 |
| Roads & Paving | 17 | ₹80.74 L | 2 |
| Community Buildings | 14 | ₹77.65 L | 6 |
| Drainage & Sanitation | 7 | ₹43.99 L | 1 |
| Education | 3 | ₹1.09 Cr | 1 |
| Boundary & Protection | 3 | ₹15.00 L | 0 |
| Health | 2 | ₹9.99 L | 0 |
| Religious & Cultural | 2 | ₹9.00 L | 0 |
| Sports | 2 | ₹13.50 L | 0 |
| Equipment & Vehicles | 1 | ₹1.19 L | 0 |
Ranked by score. Cost is judged against comparable works in this district and sector, so a high cost score means unlike its neighbours — not overpriced.
| Work | Agency | Status | Sanctioned | Delay | Cost vs peers | Score | Band |
|---|---|---|---|---|---|---|---|
| Providing of High Mast Light (2.Nos) Near Sevalal Temple an ₹400,000 against a ₹250,000 median for Street Lighting works in WANAPARTHY (60% above, 59 peer works) | WANAPARTHY(DISTRICT COLLECTOR WANAPARTHY_IDA) | Recommended | ₹4.00 L | 303 d | +60% | 63.7 | MEDIUM |
| Providing of High Mast Light (2.Nos) Near Sevalal Temple an ₹400,000 against a ₹250,000 median for Street Lighting works in WANAPARTHY (60% above, 59 peer works) | WANAPARTHY(DISTRICT COLLECTOR WANAPARTHY_IDA) | Recommended | ₹4.00 L | 303 d | +60% | 63.7 | MEDIUM |
| Providing of High Mast Light (2.Nos) Near Tarya House and S ₹400,000 against a ₹250,000 median for Street Lighting works in WANAPARTHY (60% above, 59 peer works) | WANAPARTHY(DISTRICT COLLECTOR WANAPARTHY_IDA) | Recommended | ₹4.00 L | 303 d | +60% | 63.7 | MEDIUM |
| Construction of ST Common Hall at BakkaThandain Mamidimada 303 days beyond expected completion | WANAPARTHY(DISTRICT COLLECTOR WANAPARTHY_IDA) | Recommended | ₹5.00 L | 303 d | 0% | 56.9 | MEDIUM |
| Construction of ST Common Hall at Doonthikunta Thanda in Ma 303 days beyond expected completion | WANAPARTHY(DISTRICT COLLECTOR WANAPARTHY_IDA) | Recommended | ₹5.00 L | 303 d | 0% | 56.9 | MEDIUM |
| Construction of ST Common Hall at Kothapally Thanda in Man 303 days beyond expected completion | WANAPARTHY(DISTRICT COLLECTOR WANAPARTHY_IDA) | Recommended | ₹5.00 L | 303 d | 0% | 56.9 | MEDIUM |
| Construction of ST Common Hall at Road imeedi Thanda in T 303 days beyond expected completion | WANAPARTHY(DISTRICT COLLECTOR WANAPARTHY_IDA) | Recommended | ₹5.00 L | 303 d | +0% | 56.9 | MEDIUM |
| Providing of High Mast Light (1.Nos) Near Bichya House, Mee 303 days beyond expected completion | WANAPARTHY(DISTRICT COLLECTOR WANAPARTHY_IDA) | Recommended | ₹2.00 L | 303 d | -20% | 56.6 | MEDIUM |
| Providing of High Mast Light (1.Nos) Near Devya House, Bakk 303 days beyond expected completion | WANAPARTHY(DISTRICT COLLECTOR WANAPARTHY_IDA) | Recommended | ₹2.00 L | 303 d | -20% | 56.6 | MEDIUM |
| Construction of Common Hall in Mazeed Road 227 days beyond expected completion | WANAPARTHY(DISTRICT COLLECTOR WANAPARTHY_IDA) | Recommended | ₹4.99 L | 227 d | -0% | 56.0 | MEDIUM |
| Construction of Night Shelters for Homeless at Karne Thanda Completed work has no photographic documentation on record | WANAPARTHY(DISTRICT COLLECTOR WANAPARTHY_IDA) | Completed | ₹10.00 L | — | +100% | 53.2 | MEDIUM |
| Cons of toilet flooring, electrical work, and painting work ₹2,000,000 against a ₹400,000 median for Drainage & Sanitation works in WANAPARTHY (400% above, 10 peer works) | WANAPARTHY(DISTRICT COLLECTOR WANAPARTHY_IDA) | Recommended | ₹20.00 L | — | +400% | 48.7 | MEDIUM |
| Construction of Old Age Home at Karne Thanda in Shapur Gram ₹995,166 against a ₹500,000 median for Community Buildings works in WANAPARTHY (99% above, 27 peer works) | WANAPARTHY(DISTRICT COLLECTOR WANAPARTHY_IDA) | Completed | ₹9.95 L | — | +99% | 48.5 | MEDIUM |
| Construction of Community Hall at Ekalavya Colony Rangapur, 114 days beyond expected completion | WANAPARTHY(DISTRICT COLLECTOR WANAPARTHY_IDA) | Recommended | ₹5.00 L | 114 d | 0% | 45.0 | MEDIUM |
| Construction of Social Welfare Girls College Hostel A in Wan Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range | WANAPARTHY(DISTRICT COLLECTOR WANAPARTHY_IDA) | Recommended | ₹1.00 Cr | 129 d | 0% | 43.0 | MEDIUM |