135 works across 1 implementing agency, recommended by 4 members of parliament. No allocation figure is published per district — every rupee below is summed from the works themselves.
The people a district authority actually supervises. Vendor concentration is counted from the payment records: an agency paying almost everything to one vendor is worth a question, not an accusation.
| # | Agency | Works | Completed | Sanctioned | To verify | Avg score | Top vendor |
|---|---|---|---|---|---|---|---|
| 1 | VIKARABAD(DISTRICT COLLECTOR VIKARABAD_2) 5 high risk | 135 | 108 | ₹6.44 Cr | 67 | 39.0 | UPPARI SHEKHAR 32% of spend · 28 vendors |
Whose funds paid for this district’s works.
| Member | Works | Sanctioned | To verify |
|---|---|---|---|
| Gaddam Ranjith Reddy CHELVELLA | 132 | ₹6.29 Cr | 64 |
| Anil Kumar Yadav Mandadi Sitting Rajya Sabha | 1 | ₹9.96 L | 1 |
| Srinivas Reddy Manne MAHABUBNAGAR | 1 | ₹5.00 L | 1 |
| Bheemrao Baswanthrao Patil ZAHIRABAD | 1 | ₹1.00 L | 1 |
Sector read from each work’s description.
| Sector | Works | Sanctioned | To verify |
|---|---|---|---|
| Roads & Paving | 52 | ₹2.58 Cr | 45 |
| Street Lighting | 37 | ₹1.62 Cr | 12 |
| Education | 19 | ₹93.48 L | 0 |
| Drainage & Sanitation | 11 | ₹54.59 L | 2 |
| Religious & Cultural | 6 | ₹26.91 L | 6 |
| Community Buildings | 6 | ₹23.85 L | 1 |
| Water | 1 | ₹5.00 L | 1 |
| Health | 1 | ₹5.00 L | 0 |
| Other | 1 | ₹10.00 L | 0 |
| Boundary & Protection | 1 | ₹5.00 L | 0 |
Ranked by score. Cost is judged against comparable works in this district and sector, so a high cost score means unlike its neighbours — not overpriced.
| Work | Agency | Status | Sanctioned | Delay | Cost vs peers | Score | Band |
|---|---|---|---|---|---|---|---|
| Laying of CC Road ₹500,000 against a ₹125,000 median for Roads & Paving works in VIKARABAD (300% above, 298 peer works) | VIKARABAD(DISTRICT COLLECTOR VIKARABAD_2) | Recommended | ₹5.00 L | 548 d | +300% | 73.1 | HIGH |
| Laying of CC Road ₹720,000 against a ₹125,000 median for Roads & Paving works in VIKARABAD (476% above, 298 peer works) | VIKARABAD(DISTRICT COLLECTOR VIKARABAD_2) | Recommended | ₹7.20 L | 548 d | +476% | 73.1 | HIGH |
| Laying of CC Road ₹500,000 against a ₹125,000 median for Roads & Paving works in VIKARABAD (300% above, 298 peer works) | VIKARABAD(DISTRICT COLLECTOR VIKARABAD_2) | Recommended | ₹5.00 L | 552 d | +300% | 73.1 | HIGH |
| Laying of CC Road ₹500,000 against a ₹125,000 median for Roads & Paving works in VIKARABAD (300% above, 298 peer works) | VIKARABAD(DISTRICT COLLECTOR VIKARABAD_2) | Recommended | ₹5.00 L | 552 d | +300% | 73.1 | HIGH |
| Laying of CC Road ₹1,000,000 against a ₹125,000 median for Roads & Paving works in VIKARABAD (700% above, 298 peer works) | VIKARABAD(DISTRICT COLLECTOR VIKARABAD_2) | Recommended | ₹10.00 L | 552 d | +700% | 73.1 | HIGH |
| Laying of CC Road From GP Building to KavaliBabu (H) at Ebba ₹500,000 against a ₹125,000 median for Roads & Paving works in VIKARABAD (300% above, 298 peer works) | VIKARABAD(DISTRICT COLLECTOR VIKARABAD_2) | Recommended | ₹5.00 L | 552 d | +300% | 66.4 | MEDIUM |
| Laying of CC road from GP building to Kavalibabu (H) at Ebba ₹1,000,000 against a ₹125,000 median for Roads & Paving works in VIKARABAD (700% above, 298 peer works) | VIKARABAD(DISTRICT COLLECTOR VIKARABAD_2) | Recommended | ₹10.00 L | 570 d | +700% | 66.4 | MEDIUM |
| Laying of CC Road ₹200,000 against a ₹125,000 median for Roads & Paving works in VIKARABAD (60% above, 298 peer works) | VIKARABAD(DISTRICT COLLECTOR VIKARABAD_2) | Recommended | ₹2.00 L | 548 d | +60% | 63.1 | MEDIUM |
| Providing of LED based Hi-Mast lights with Material 547 days beyond expected completion | VIKARABAD(DISTRICT COLLECTOR VIKARABAD_2) | Recommended | ₹3.40 L | 547 d | +36% | 57.1 | MEDIUM |
| Construction of Community Hall 548 days beyond expected completion | VIKARABAD(DISTRICT COLLECTOR VIKARABAD_2) | Recommended | ₹5.00 L | 548 d | 0% | 56.5 | MEDIUM |
| Providing of LED based Hi-mast lights with material 547 days beyond expected completion | VIKARABAD(DISTRICT COLLECTOR VIKARABAD_2) | Recommended | ₹1.70 L | 547 d | -32% | 56.1 | MEDIUM |
| Providing Hi-Mast Lights 548 days beyond expected completion | VIKARABAD(DISTRICT COLLECTOR VIKARABAD_2) | Recommended | ₹3.00 L | 548 d | +20% | 55.9 | MEDIUM |
| Construction of C C Road from Majid to P Balappa (H) at Chow ₹500,000 against a ₹125,000 median for Roads & Paving works in VIKARABAD (300% above, 298 peer works) | VIKARABAD(DISTRICT COLLECTOR VIKARABAD_2) | Recommended | ₹5.00 L | 577 d | +300% | 53.1 | MEDIUM |
| CONSTRUCTION OF CULTURAL CENTER ATB WATER TANK, KAREEMPUR VI ₹500,000 against a ₹200,000 median for Water works in VIKARABAD (150% above, 69 peer works) | VIKARABAD(DISTRICT COLLECTOR VIKARABAD_2) | Recommended | ₹5.00 L | 990 d | +150% | 53.1 | MEDIUM |
| Construction of Cultural Centre at Balajinagar Colony Parig ₹1,000,000 against a ₹500,000 median for Religious & Cultural works in VIKARABAD (100% above, 8 peer works) | VIKARABAD(DISTRICT COLLECTOR VIKARABAD_2) | Recommended | ₹10.00 L | 1,270 d | +100% | 53.1 | MEDIUM |