Open this link on a larger screen to see the verification queue.
51 works across 1 implementing agency, recommended by 2 members of parliament. No allocation figure is published per district — every rupee below is summed from the works themselves.
The people a district authority actually supervises. Vendor concentration is counted from the payment records: an agency paying almost everything to one vendor is worth a question, not an accusation.
| # | Agency | Works | Completed | Sanctioned | To verify | Avg score | Top vendor |
|---|---|---|---|---|---|---|---|
| 1 | Nirmal(DISTRICT COLLECTOR NIRMAL_3) | 51 | 27 | ₹1.71 Cr | 12 | 24.5 | KRSIHNA DAS 22% of spend · 19 vendors |
Whose funds paid for this district’s works.
| Member | Works | Sanctioned | To verify |
|---|---|---|---|
| Soyam Bapu Rao ADILABAD | 47 | ₹1.51 Cr | 12 |
| Damodar Rao Divakonda Sitting Rajya Sabha | 4 | ₹20.00 L | 0 |
Sector read from each work’s description.
| Sector | Works | Sanctioned | To verify |
|---|---|---|---|
| Roads & Paving | 22 | ₹56.26 L | 6 |
| Community Buildings | 11 | ₹47.48 L | 2 |
| Religious & Cultural | 7 | ₹28.56 L | 1 |
| Education | 5 | ₹25.00 L | 0 |
| Drainage & Sanitation | 3 | ₹4.00 L | 3 |
| Sports | 1 | ₹5.00 L | 0 |
| Street Lighting | 1 | ₹1.00 L | 0 |
| Water | 1 | ₹3.99 L | 0 |
Ranked by score. Cost is judged against comparable works in this district and sector, so a high cost score means unlike its neighbours — not overpriced.
| Work | Agency | Status | Sanctioned | Delay | Cost vs peers | Score | Band |
|---|---|---|---|---|---|---|---|
| Construction of CC road from main road Govt. School via Ravi ₹400,000 against a ₹200,000 median for Roads & Paving works in NIRMAL (100% above, 42 peer works) | Nirmal(DISTRICT COLLECTOR NIRMAL_3) | Recommended | ₹4.00 L | 562 d | +100% | 54.0 | MEDIUM |
| Construction of CC Road from Basa Kishna (H) to Hanuman Tem ₹500,000 against a ₹200,000 median for Roads & Paving works in NIRMAL (150% above, 42 peer works) | Nirmal(DISTRICT COLLECTOR NIRMAL_3) | Recommended | ₹5.00 L | 749 d | +150% | 54.0 | MEDIUM |
| Construction of CC Road From Gp Building To Shravan Reddy Ho ₹400,000 against a ₹200,000 median for Roads & Paving works in NIRMAL (100% above, 42 peer works) | Nirmal(DISTRICT COLLECTOR NIRMAL_3) | Recommended | ₹4.00 L | 791 d | +100% | 54.0 | MEDIUM |
| Construction of side drain from Gajanan (H) to Godsha at Bha Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range | Nirmal(DISTRICT COLLECTOR NIRMAL_3) | Recommended | ₹1.00 L | 919 d | 0% | 44.6 | MEDIUM |
| Construction side drain from Lingam (H) to Bheemamandir at B Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range | Nirmal(DISTRICT COLLECTOR NIRMAL_3) | Recommended | ₹1.50 L | 919 d | 0% | 44.3 | MEDIUM |
| Construction of CC road from Basa Lingeshwar (H) to Shenkar ₹300,000 against a ₹200,000 median for Roads & Paving works in NIRMAL (50% above, 42 peer works) | Nirmal(DISTRICT COLLECTOR NIRMAL_3) | Recommended | ₹3.00 L | 919 d | +50% | 43.6 | MEDIUM |
| Construction of Reading Room at Sevalal Thanda Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range | Nirmal(DISTRICT COLLECTOR NIRMAL_3) | Recommended | ₹1.50 L | 791 d | -70% | 42.2 | MEDIUM |
| Construction of Compound wall Near Sevala mandir Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range | Nirmal(DISTRICT COLLECTOR NIRMAL_3) | Recommended | ₹1.50 L | 791 d | -69% | 42.2 | MEDIUM |
| Formation of Gravel road from Baddam Linga Reddy House To Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range | Nirmal(DISTRICT COLLECTOR NIRMAL_3) | Recommended | ₹1.50 L | 791 d | -25% | 42.2 | MEDIUM |
| Construction of Drain from akula Santhosh House to Linga red Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range | Nirmal(DISTRICT COLLECTOR NIRMAL_3) | Recommended | ₹1.50 L | 791 d | 0% | 42.2 | MEDIUM |
| Formation of Gravel road from Parapelly to Godavari at Par Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range | Nirmal(DISTRICT COLLECTOR NIRMAL_3) | Recommended | ₹2.00 L | 791 d | 0% | 41.7 | MEDIUM |
| Construction of Shed Near Bustand at Jam (Peddur). Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range | Nirmal(DISTRICT COLLECTOR NIRMAL_3) | Recommended | ₹3.00 L | 791 d | -40% | 41.3 | MEDIUM |
| Erection of LED lights near temple at jam 561 days beyond expected completion | Nirmal(DISTRICT COLLECTOR NIRMAL_3) | Recommended | ₹1.00 L | 561 d | 0% | 37.6 | LOW |
| Construction of reading room near Repelli Satya House at Nav 561 days beyond expected completion | Nirmal(DISTRICT COLLECTOR NIRMAL_3) | Recommended | ₹5.00 L | 561 d | 0% | 37.2 | LOW |
| Construction of Dining hall at Ayyappa Temple at Khanapur ma 562 days beyond expected completion | Nirmal(DISTRICT COLLECTOR NIRMAL_3) | Recommended | ₹5.00 L | 562 d | 0% | 37.1 | LOW |