117 works across 1 implementing agency, recommended by 2 members of parliament. No allocation figure is published per district — every rupee below is summed from the works themselves.
The people a district authority actually supervises. Vendor concentration is counted from the payment records: an agency paying almost everything to one vendor is worth a question, not an accusation.
| # | Agency | Works | Completed | Sanctioned | To verify | Avg score | Top vendor |
|---|---|---|---|---|---|---|---|
| 1 | Nirmal(DISTRICT COLLECTOR NIRMAL_3) | 117 | 28 | ₹3.59 Cr | 0 | 13.5 | Mategama Vinod Reddy 22% of spend · 23 vendors |
Whose funds paid for this district’s works.
| Member | Works | Sanctioned | To verify |
|---|---|---|---|
| Godam Nagesh ADILABAD | 113 | ₹3.39 Cr | 0 |
| Damodar Rao Divakonda Sitting Rajya Sabha | 4 | ₹20.00 L | 0 |
Sector read from each work’s description.
| Sector | Works | Sanctioned | To verify |
|---|---|---|---|
| Community Buildings | 57 | ₹2.28 Cr | 0 |
| Water | 30 | ₹42.13 L | 0 |
| Roads & Paving | 20 | ₹45.71 L | 0 |
| Religious & Cultural | 4 | ₹13.50 L | 0 |
| Education | 2 | ₹15.00 L | 0 |
| Health | 1 | ₹5.00 L | 0 |
| Drainage & Sanitation | 1 | ₹53,978 | 0 |
| Boundary & Protection | 1 | ₹5.00 L | 0 |
| Street Lighting | 1 | ₹4.00 L | 0 |
Ranked by score. Cost is judged against comparable works in this district and sector, so a high cost score means unlike its neighbours — not overpriced.
| Work | Agency | Status | Sanctioned | Delay | Cost vs peers | Score | Band |
|---|---|---|---|---|---|---|---|
| Construction of additional rooms to Community Hall at BC Col 157 days beyond expected completion | Nirmal(DISTRICT COLLECTOR NIRMAL_3) | Recommended | ₹5.00 L | 157 d | 0% | 33.2 | LOW |
| Construction of additional rooms and halls to Community Hal 157 days beyond expected completion | Nirmal(DISTRICT COLLECTOR NIRMAL_3) | Recommended | ₹5.00 L | 157 d | 0% | 33.2 | LOW |
| Construction of Reading room at Kotalgaon Village 157 days beyond expected completion | Nirmal(DISTRICT COLLECTOR NIRMAL_3) | Recommended | ₹1.00 L | 157 d | -80% | 33.1 | LOW |
| Construction of compound wall to Community Hall at SC Colony 157 days beyond expected completion | Nirmal(DISTRICT COLLECTOR NIRMAL_3) | Recommended | ₹1.00 L | 157 d | -80% | 33.1 | LOW |
| Construction of Road from Madhav Rao (H) to Mogli Road at K 157 days beyond expected completion | Nirmal(DISTRICT COLLECTOR NIRMAL_3) | Recommended | ₹1.00 L | 157 d | -50% | 33.1 | LOW |
| Construction of Road from Bridge to School Building at Dhar 157 days beyond expected completion | Nirmal(DISTRICT COLLECTOR NIRMAL_3) | Recommended | ₹1.50 L | 157 d | -25% | 32.1 | LOW |
| Construction of Road from R and B road to Bridge at Dhar Ku 157 days beyond expected completion | Nirmal(DISTRICT COLLECTOR NIRMAL_3) | Recommended | ₹2.50 L | 157 d | +25% | 32.1 | LOW |
| Construction of Shed at Naikpod Colony Dyangapur village 156 days beyond expected completion | Nirmal(DISTRICT COLLECTOR NIRMAL_3) | Recommended | ₹1.50 L | 156 d | -70% | 32.0 | LOW |
| Construction of Community Hall at Boyawada Colony Mamada vil 156 days beyond expected completion | Nirmal(DISTRICT COLLECTOR NIRMAL_3) | Recommended | ₹4.00 L | 156 d | -20% | 31.7 | LOW |
| Construction of Road from X Road to Shivalayam Temple at Sir 157 days beyond expected completion | Nirmal(DISTRICT COLLECTOR NIRMAL_3) | Recommended | ₹1.75 L | 157 d | -13% | 31.7 | LOW |
| Construction of Common work sheds for artisans (Vishwa Brahm 157 days beyond expected completion | Nirmal(DISTRICT COLLECTOR NIRMAL_3) | Recommended | ₹5.00 L | 157 d | 0% | 31.7 | LOW |
| Construction of Community Hall at Mudhiraj Colony Chandrapur 156 days beyond expected completion | Nirmal(DISTRICT COLLECTOR NIRMAL_3) | Recommended | ₹5.00 L | 156 d | 0% | 31.5 | LOW |
| Construction of Community Hall at SC Colony Laxmanchanda vil 156 days beyond expected completion | Nirmal(DISTRICT COLLECTOR NIRMAL_3) | Recommended | ₹5.00 L | 156 d | 0% | 31.5 | LOW |
| Construction of Common Community Hall at Potia village 156 days beyond expected completion | Nirmal(DISTRICT COLLECTOR NIRMAL_3) | Recommended | ₹5.00 L | 156 d | 0% | 31.5 | LOW |
| Construction of Community Hall at Naikpod Colony Gundampalle 156 days beyond expected completion | Nirmal(DISTRICT COLLECTOR NIRMAL_3) | Recommended | ₹5.00 L | 156 d | 0% | 31.5 | LOW |