66 works across 1 implementing agency, recommended by 1 member of parliament. No allocation figure is published per district — every rupee below is summed from the works themselves.
The people a district authority actually supervises. Vendor concentration is counted from the payment records: an agency paying almost everything to one vendor is worth a question, not an accusation.
| # | Agency | Works | Completed | Sanctioned | To verify | Avg score | Top vendor |
|---|---|---|---|---|---|---|---|
| 1 | KUMURAM BHEEM ASIFABAD(District Collector KB Asifabad_IDA) | 66 | 32 | ₹1.73 Cr | 7 | 24.2 | JAGADEESHWAR HANUMANDLA 47% of spend · 5 vendors |
Whose funds paid for this district’s works.
| Member | Works | Sanctioned | To verify |
|---|---|---|---|
| Godam Nagesh ADILABAD | 66 | ₹1.73 Cr | 7 |
Sector read from each work’s description.
| Sector | Works | Sanctioned | To verify |
|---|---|---|---|
| Water | 33 | ₹33.23 L | 0 |
| Street Lighting | 20 | ₹40.00 L | 6 |
| Community Buildings | 6 | ₹30.00 L | 0 |
| Roads & Paving | 6 | ₹19.99 L | 1 |
| Education | 1 | ₹50.00 L | 0 |
Ranked by score. Cost is judged against comparable works in this district and sector, so a high cost score means unlike its neighbours — not overpriced.
| Work | Agency | Status | Sanctioned | Delay | Cost vs peers | Score | Band |
|---|---|---|---|---|---|---|---|
| High mast lights at Heerapur village of Asifabad GP of Asifa 157 days beyond expected completion | KUMURAM BHEEM ASIFABAD(District Collector KB Asifabad_IDA) | Recommended | ₹2.00 L | 157 d | 0% | 49.0 | MEDIUM |
| High mast lights at Dasnapur village of Asifabad GP of Asifa 157 days beyond expected completion | KUMURAM BHEEM ASIFABAD(District Collector KB Asifabad_IDA) | Recommended | ₹2.00 L | 157 d | 0% | 49.0 | MEDIUM |
| High mast lights at Godavelli village of Asifabad GP of Asif 157 days beyond expected completion | KUMURAM BHEEM ASIFABAD(District Collector KB Asifabad_IDA) | Recommended | ₹2.00 L | 157 d | 0% | 43.5 | MEDIUM |
| High mast lights at Besthawada village of Asifabad GP of Asi 157 days beyond expected completion | KUMURAM BHEEM ASIFABAD(District Collector KB Asifabad_IDA) | Recommended | ₹2.00 L | 157 d | 0% | 42.1 | MEDIUM |
| High mast lights at Kasbawada village of Asifabad GP of Asif 157 days beyond expected completion | KUMURAM BHEEM ASIFABAD(District Collector KB Asifabad_IDA) | Recommended | ₹2.00 L | 157 d | 0% | 41.8 | MEDIUM |
| High mast lights at NTR Nagar village of Asifabad GP of Asif 157 days beyond expected completion | KUMURAM BHEEM ASIFABAD(District Collector KB Asifabad_IDA) | Recommended | ₹2.00 L | 157 d | 0% | 41.2 | MEDIUM |
| Gravelling Road From Maddiguda to Kuntala manepally ₹500,000 against a ₹250,000 median for Roads & Paving works in KUMURAM BHEEM ASIFABAD (100% above, 27 peer works) | KUMURAM BHEEM ASIFABAD(District Collector KB Asifabad_IDA) | Recommended | ₹5.00 L | 55 d | +100% | 40.9 | MEDIUM |
| High mast lights at Rajura village of Mothuguda GP of Asifab 157 days beyond expected completion | KUMURAM BHEEM ASIFABAD(District Collector KB Asifabad_IDA) | Recommended | ₹2.00 L | 157 d | 0% | 39.8 | LOW |
| High mast lights at Banar Boguda village of Asifabad GP of A 157 days beyond expected completion | KUMURAM BHEEM ASIFABAD(District Collector KB Asifabad_IDA) | Recommended | ₹2.00 L | 157 d | 0% | 37.8 | LOW |
| Providing of Drinking water source at ZPSS Vempally 157 days beyond expected completion | KUMURAM BHEEM ASIFABAD(District Collector KB Asifabad_IDA) | Recommended | ₹1.00 L | 157 d | +1% | 37.4 | LOW |
| Providing of Drinking water source near Trinethra Shivalayam 157 days beyond expected completion | KUMURAM BHEEM ASIFABAD(District Collector KB Asifabad_IDA) | Recommended | ₹1.00 L | 157 d | +1% | 37.4 | LOW |
| Providing of drinking water source near Hanuman Temple at Ge 157 days beyond expected completion | KUMURAM BHEEM ASIFABAD(District Collector KB Asifabad_IDA) | Recommended | ₹1.00 L | 157 d | +1% | 37.4 | LOW |
| Construction of Addl. room at Press club at Dhaegaon 157 days beyond expected completion | KUMURAM BHEEM ASIFABAD(District Collector KB Asifabad_IDA) | Recommended | ₹5.00 L | 157 d | 0% | 35.9 | LOW |
| Construction of Community hall at Rudrapur 157 days beyond expected completion | KUMURAM BHEEM ASIFABAD(District Collector KB Asifabad_IDA) | Recommended | ₹5.00 L | 157 d | 0% | 35.9 | LOW |
| Construction of Reading room near Brahmana Sangham Ward No 1 157 days beyond expected completion | KUMURAM BHEEM ASIFABAD(District Collector KB Asifabad_IDA) | Recommended | ₹5.00 L | 157 d | 0% | 35.9 | LOW |