51 works across 1 implementing agency, recommended by 2 members of parliament. No allocation figure is published per district — every rupee below is summed from the works themselves.
The people a district authority actually supervises. Vendor concentration is counted from the payment records: an agency paying almost everything to one vendor is worth a question, not an accusation.
| # | Agency | Works | Completed | Sanctioned | To verify | Avg score | Top vendor |
|---|---|---|---|---|---|---|---|
| 1 | VELLORE(DISTRICT COLLECTOR VELLORE_IDA) | 51 | 11 | ₹7.01 Cr | 0 | 24.2 | VINAYAGAM ENTERPRISES 18% of spend · 13 vendors |
Whose funds paid for this district’s works.
| Member | Works | Sanctioned | To verify |
|---|---|---|---|
| D M Kathir Anand VELLORE | 50 | ₹6.01 Cr | 0 |
| Dr. S Jagathratchakan ARAKKONAM | 1 | ₹1.00 Cr | 0 |
Sector read from each work’s description.
| Sector | Works | Sanctioned | To verify |
|---|---|---|---|
| Community Buildings | 32 | ₹3.60 Cr | 0 |
| Roads & Paving | 7 | ₹1.36 Cr | 0 |
| Drainage & Sanitation | 3 | ₹33.98 L | 0 |
| Education | 3 | ₹1.22 Cr | 0 |
| Water | 3 | ₹15.64 L | 0 |
| Health | 2 | ₹22.00 L | 0 |
| Religious & Cultural | 1 | ₹11.00 L | 0 |
Patterns across an agency’s whole book of work. None of these move any individual work’s score.
Round figures are normal and similar works legitimately cost the same. One figure covering nearly every work is what this looks for, and it means the costing is worth seeing, not that it is wrong.
Ranked by score. Cost is judged against comparable works in this district and sector, so a high cost score means unlike its neighbours — not overpriced.
| Work | Agency | Status | Sanctioned | Delay | Cost vs peers | Score | Band |
|---|---|---|---|---|---|---|---|
| Construction of bus shelter at Perumugai North Side (Towards Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range | VELLORE(DISTRICT COLLECTOR VELLORE_IDA) | Recommended | ₹15.00 L | 114 d | +36% | 32.7 | LOW |
| Construction of bus shelter at Near Pillayar Kuppam south si Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range | VELLORE(DISTRICT COLLECTOR VELLORE_IDA) | Recommended | ₹15.00 L | 114 d | +36% | 32.7 | LOW |
| Construction of Bus Shelter at Machampattu Panchyat Pernambu 117 days beyond expected completion | VELLORE(DISTRICT COLLECTOR VELLORE_IDA) | Recommended | ₹11.00 L | 117 d | 0% | 31.7 | LOW |
| Construction of Bus Shelter at Masigam Panchyat Pernambut Un 117 days beyond expected completion | VELLORE(DISTRICT COLLECTOR VELLORE_IDA) | Recommended | ₹11.00 L | 117 d | 0% | 31.7 | LOW |
| Construction of Bus Shelter at Ward No 4 Near Puthukovil Pe 117 days beyond expected completion | VELLORE(DISTRICT COLLECTOR VELLORE_IDA) | Recommended | ₹11.00 L | 117 d | 0% | 31.7 | LOW |
| Construction of Bus Shelter at Ward No 9 V.Kotta road Pernam 117 days beyond expected completion | VELLORE(DISTRICT COLLECTOR VELLORE_IDA) | Recommended | ₹11.00 L | 117 d | 0% | 31.7 | LOW |
| Construction of Bus Shelter at Erikuthi Panchyat Pernambut U 117 days beyond expected completion | VELLORE(DISTRICT COLLECTOR VELLORE_IDA) | Recommended | ₹11.00 L | 117 d | 0% | 31.7 | LOW |
| Construction of Bus Shelter at Ward No 18 Salapet Bus Stop i 117 days beyond expected completion | VELLORE(DISTRICT COLLECTOR VELLORE_IDA) | Recommended | ₹11.00 L | 117 d | 0% | 31.7 | LOW |
| Construction of Bus Shelter at Morasapalli Panchyat Pernambu 117 days beyond expected completion | VELLORE(DISTRICT COLLECTOR VELLORE_IDA) | Recommended | ₹11.00 L | 117 d | 0% | 31.7 | LOW |
| Construction of Bus Shelter at Valathur Panchyat Gudiyatham 117 days beyond expected completion | VELLORE(DISTRICT COLLECTOR VELLORE_IDA) | Recommended | ₹11.00 L | 117 d | 0% | 31.7 | LOW |
| Construction of Bus Shelter at Chempedukutroad Ulli Panchyat 117 days beyond expected completion | VELLORE(DISTRICT COLLECTOR VELLORE_IDA) | Recommended | ₹11.00 L | 117 d | 0% | 31.7 | LOW |
| Construction of Bus shelter at Koothampakkam Panchyat Gudiya 117 days beyond expected completion | VELLORE(DISTRICT COLLECTOR VELLORE_IDA) | Recommended | ₹11.00 L | 117 d | 0% | 31.7 | LOW |
| Construction of Bus shelter at Near Floram shoes gollamangal 117 days beyond expected completion | VELLORE(DISTRICT COLLECTOR VELLORE_IDA) | Recommended | ₹11.00 L | 117 d | 0% | 31.7 | LOW |
| Construction of Bus shelter Near Melmoil Govt Elementary Sch 117 days beyond expected completion | VELLORE(DISTRICT COLLECTOR VELLORE_IDA) | Recommended | ₹11.00 L | 117 d | 0% | 31.7 | LOW |
| Construction of Bus Shelter at Sethuvandai Village K.V.Kuppa 117 days beyond expected completion | VELLORE(DISTRICT COLLECTOR VELLORE_IDA) | Recommended | ₹11.00 L | 117 d | 0% | 31.7 | LOW |