27 works across 1 implementing agency, recommended by 2 members of parliament. No allocation figure is published per district — every rupee below is summed from the works themselves.
The people a district authority actually supervises. Vendor concentration is counted from the payment records: an agency paying almost everything to one vendor is worth a question, not an accusation.
| # | Agency | Works | Completed | Sanctioned | To verify | Avg score | Top vendor |
|---|---|---|---|---|---|---|---|
| 1 | VELLORE(DISTRICT COLLECTOR VELLORE_IDA) | 27 | 22 | ₹3.90 Cr | 5 | 22.1 | ROYAL AGENCIES 11% of spend · 19 vendors |
Whose funds paid for this district’s works.
| Member | Works | Sanctioned | To verify |
|---|---|---|---|
| D M Kathir Anand VELLORE | 25 | ₹2.97 Cr | 4 |
| Dr. S Jagathratchakan ARAKKONAM | 2 | ₹92.97 L | 1 |
Sector read from each work’s description.
| Sector | Works | Sanctioned | To verify |
|---|---|---|---|
| Community Buildings | 20 | ₹3.05 Cr | 5 |
| Education | 2 | ₹27.97 L | 0 |
| Street Lighting | 2 | ₹30.00 L | 0 |
| Religious & Cultural | 1 | ₹11.00 L | 0 |
| Roads & Paving | 1 | ₹12.97 L | 0 |
| Water | 1 | ₹2.94 L | 0 |
Ranked by score. Cost is judged against comparable works in this district and sector, so a high cost score means unlike its neighbours — not overpriced.
| Work | Agency | Status | Sanctioned | Delay | Cost vs peers | Score | Band |
|---|---|---|---|---|---|---|---|
| Construction of Community Hall at Thirowpathiyamman Koil Thi ₹8,000,000 against a ₹1,100,000 median for Community Buildings works in VELLORE (627% above, 52 peer works) | VELLORE(DISTRICT COLLECTOR VELLORE_IDA) | Recommended | ₹80.00 L | 562 d | +627% | 56.5 | MEDIUM |
| Construction of passenger shelter in front of Vellore New Bu ₹2,500,000 against a ₹1,100,000 median for Community Buildings works in VELLORE (127% above, 52 peer works) | VELLORE(DISTRICT COLLECTOR VELLORE_IDA) | Recommended | ₹25.00 L | 724 d | +127% | 56.5 | MEDIUM |
| Construction of passenger shelter at KV Kuppam Block Vanjoor Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range | VELLORE(DISTRICT COLLECTOR VELLORE_IDA) | Recommended | ₹11.00 L | 729 d | 0% | 46.8 | MEDIUM |
| Construction of passenger shelter at Mathur Bus Stand, Chinn Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range | VELLORE(DISTRICT COLLECTOR VELLORE_IDA) | Recommended | ₹11.00 L | 724 d | 0% | 46.7 | MEDIUM |
| Construction of passenger shelter at Melpatti Panchayat Melp Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range | VELLORE(DISTRICT COLLECTOR VELLORE_IDA) | Recommended | ₹11.00 L | 724 d | 0% | 46.7 | MEDIUM |
| Construction of Govt School Compound Wall in Satkar Panchyat Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range | VELLORE(DISTRICT COLLECTOR VELLORE_IDA) | Completed | ₹19.99 L | — | 0% | 20.4 | LOW |
| Construction of passenger shelter at Duraimulai Bus Stand, K Completed work has no photographic documentation on record | VELLORE(DISTRICT COLLECTOR VELLORE_IDA) | Completed | ₹11.00 L | — | 0% | 18.5 | LOW |
| Construction of passenger shelter at Veppur Panchayat Veppur Completed work has no photographic documentation on record | VELLORE(DISTRICT COLLECTOR VELLORE_IDA) | Completed | ₹10.99 L | — | -0% | 18.5 | LOW |
| Construction of passenger shelter at Karthikeyapuram Bus Sta Completed work has no photographic documentation on record | VELLORE(DISTRICT COLLECTOR VELLORE_IDA) | Completed | ₹10.99 L | — | -0% | 18.5 | LOW |
| Construction of passenger shelter at Gudiyatham block Erthan Completed work has no photographic documentation on record | VELLORE(DISTRICT COLLECTOR VELLORE_IDA) | Completed | ₹10.99 L | — | -0% | 18.5 | LOW |
| Construction of passenger shelter at Ambur Block anaicut Uni Completed work has no photographic documentation on record | VELLORE(DISTRICT COLLECTOR VELLORE_IDA) | Completed | ₹10.99 L | — | -0% | 18.5 | LOW |
| Construction of Bus Shelter at Vanjur Kalani in Vanjur Panch Completed work has no photographic documentation on record | VELLORE(DISTRICT COLLECTOR VELLORE_IDA) | Completed | ₹10.94 L | — | -1% | 18.4 | LOW |
| Construction of passenger shelter at the bus station in Vell Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range | VELLORE(DISTRICT COLLECTOR VELLORE_IDA) | Completed | ₹14.56 L | — | +32% | 17.0 | LOW |
| Installation of Street lights in the center of the road from Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range | VELLORE(DISTRICT COLLECTOR VELLORE_IDA) | Completed | ₹15.00 L | — | 0% | 16.9 | LOW |
| Installation of Street lights in the center of the road from Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range | VELLORE(DISTRICT COLLECTOR VELLORE_IDA) | Completed | ₹15.00 L | — | 0% | 16.9 | LOW |