294 works across 1 implementing agency, recommended by 4 members of parliament. No allocation figure is published per district — every rupee below is summed from the works themselves.
The people a district authority actually supervises. Vendor concentration is counted from the payment records: an agency paying almost everything to one vendor is worth a question, not an accusation.
| # | Agency | Works | Completed | Sanctioned | To verify | Avg score | Top vendor |
|---|---|---|---|---|---|---|---|
| 1 | RAYAGADA(DISTRICT COLLECTOR RAYAGADA_IDA) | 294 | 67 | ₹9.69 Cr | 6 | 10.6 | RAMESWAR NAIK 43% of spend · 20 vendors |
Whose funds paid for this district’s works.
| Member | Works | Sanctioned | To verify |
|---|---|---|---|
| Saptagiri Sankar Ulaka KORAPUT | 290 | ₹9.47 Cr | 3 |
| Sasmit Patra Sitting Rajya Sabha | 2 | ₹10.00 L | 2 |
| Sujeet Kumar Sitting Rajya Sabha | 1 | ₹7.00 L | 0 |
| Manas Ranjan Mangaraj Sitting Rajya Sabha | 1 | ₹5.00 L | 1 |
Sector read from each work’s description.
| Sector | Works | Sanctioned | To verify |
|---|---|---|---|
| Roads & Paving | 207 | ₹5.96 Cr | 4 |
| Community Buildings | 28 | ₹1.37 Cr | 1 |
| Education | 20 | ₹1.18 Cr | 0 |
| Boundary & Protection | 13 | ₹30.00 L | 0 |
| Water | 9 | ₹28.50 L | 0 |
| Religious & Cultural | 8 | ₹26.00 L | 0 |
| Drainage & Sanitation | 7 | ₹19.00 L | 0 |
| Sports | 2 | ₹15.00 L | 1 |
Ranked by score. Cost is judged against comparable works in this district and sector, so a high cost score means unlike its neighbours — not overpriced.
| Work | Agency | Status | Sanctioned | Delay | Cost vs peers | Score | Band |
|---|---|---|---|---|---|---|---|
| Construction of additional rooms of Netaji Social, Cultural 398 days beyond expected completion | RAYAGADA(DISTRICT COLLECTOR RAYAGADA_IDA) | Recommended | ₹5.00 L | 398 d | 0% | 57.0 | MEDIUM |
| Completion of incomplete building of Netaji Social, Cultural 233 days beyond expected completion | RAYAGADA(DISTRICT COLLECTOR RAYAGADA_IDA) | Recommended | ₹5.00 L | 233 d | 0% | 55.8 | MEDIUM |
| To establish the library infrastructure and procure books, d ₹500,000 against a ₹250,000 median for Roads & Paving works in RAYAGADA (100% above, 237 peer works) | RAYAGADA(DISTRICT COLLECTOR RAYAGADA_IDA) | Recommended | ₹5.00 L | 36 d | +100% | 53.3 | MEDIUM |
| Construction of CC Road from Baising Village to Mashani, GP ₹500,000 against a ₹250,000 median for Roads & Paving works in RAYAGADA (100% above, 237 peer works) | RAYAGADA(DISTRICT COLLECTOR RAYAGADA_IDA) | Recommended | ₹5.00 L | 196 d | +100% | 53.3 | MEDIUM |
| Construction of Bridge near Mashani Road of Village, GP Bada ₹1,000,000 against a ₹250,000 median for Roads & Paving works in RAYAGADA (300% above, 237 peer works) | RAYAGADA(DISTRICT COLLECTOR RAYAGADA_IDA) | Recommended | ₹10.00 L | 196 d | +300% | 53.3 | MEDIUM |
| Construction of Paver Block road at Saltu Krishna Street Bis ₹500,000 against a ₹250,000 median for Roads & Paving works in RAYAGADA (100% above, 237 peer works) | RAYAGADA(DISTRICT COLLECTOR RAYAGADA_IDA) | Recommended | ₹5.00 L | 293 d | +100% | 53.3 | MEDIUM |
| Construction of Community Hall at Mundabandha Mendri Sahi of 293 days beyond expected completion | RAYAGADA(DISTRICT COLLECTOR RAYAGADA_IDA) | Recommended | ₹5.00 L | 293 d | 0% | 36.4 | LOW |
| Construction of Additional Hostel Building at Loknathpur Hig 293 days beyond expected completion | RAYAGADA(DISTRICT COLLECTOR RAYAGADA_IDA) | Recommended | ₹5.00 L | 293 d | -17% | 36.4 | LOW |
| Construction of CC Road at G. Budubali of Budubali GP under 293 days beyond expected completion | RAYAGADA(DISTRICT COLLECTOR RAYAGADA_IDA) | Recommended | ₹3.00 L | 293 d | +20% | 36.2 | LOW |
| Construction of Community Hall at Upper Chelianala Village o 293 days beyond expected completion | RAYAGADA(DISTRICT COLLECTOR RAYAGADA_IDA) | Recommended | ₹3.00 L | 293 d | -40% | 36.2 | LOW |
| Construction of Community Hall at Dorabariguda Village of Pa 293 days beyond expected completion | RAYAGADA(DISTRICT COLLECTOR RAYAGADA_IDA) | Recommended | ₹3.00 L | 293 d | -40% | 36.2 | LOW |
| Construction of Additional Room of Community Hall at Kotalgu 196 days beyond expected completion | RAYAGADA(DISTRICT COLLECTOR RAYAGADA_IDA) | Recommended | ₹5.00 L | 196 d | 0% | 35.3 | LOW |
| Construction of drain at Mala Street of Village, GP Jimidipe 196 days beyond expected completion | RAYAGADA(DISTRICT COLLECTOR RAYAGADA_IDA) | Recommended | ₹5.00 L | 196 d | 0% | 35.3 | LOW |
| Construction of CC Road at Village,GP Pipalguda, Block Rayag 196 days beyond expected completion | RAYAGADA(DISTRICT COLLECTOR RAYAGADA_IDA) | Recommended | ₹3.00 L | 196 d | +20% | 35.0 | LOW |
| Construction of CC Road at Bada Kutuli village of Kutuli GP, 196 days beyond expected completion | RAYAGADA(DISTRICT COLLECTOR RAYAGADA_IDA) | Recommended | ₹3.00 L | 196 d | +20% | 35.0 | LOW |