Kasauti can only be opened on a desktop or laptop.

Open this link on a larger screen to see the verification queue.

← Back to works

Construction of CC Road at G. Budubali of Budubali GP under

Roads & Paving

Odisha / RAYAGADA — RAYAGADA(DISTRICT COLLECTOR RAYAGADA_IDA) · Saptagiri Sankar Ulaka (KORAPUT)

Construction of CC Road at G. Budubali of Budubali GP under Chandrapur Block

Overall risk score
36/100
Blended from the five components below, each weighted as shown.
LOW

Risk components

Cost31
Delay100
Duplication0
Agency22
Compliance0
Sanctioned
₹3.00 L
Delay
293d
Cost deviation
20%
Work status
Recommended

AI powered · gemini-flash-liteWhy was this flagged?

  • 293 days beyond expected completionPublished dates

Decision trail

Nobody has recorded a decision on this work yet.