284 works across 1 implementing agency, recommended by 5 members of parliament. No allocation figure is published per district — every rupee below is summed from the works themselves.
The people a district authority actually supervises. Vendor concentration is counted from the payment records: an agency paying almost everything to one vendor is worth a question, not an accusation.
| # | Agency | Works | Completed | Sanctioned | To verify | Avg score | Top vendor |
|---|---|---|---|---|---|---|---|
| 1 | Baleshwar(DISTRICT COLLECTOR BALESHWAR_IDA) 1 high risk | 284 | 21 | ₹10.46 Cr | 27 | 20.1 | VE Commercial Vehicles Ltd 18% of spend · 25 vendors |
Whose funds paid for this district’s works.
| Member | Works | Sanctioned | To verify |
|---|---|---|---|
| Avimanyu Sethi BHADRAK | 148 | ₹2.76 Cr | 4 |
| Pratap Chandra Sarangi BALASORE | 99 | ₹2.89 Cr | 0 |
| Sulata Deo Sitting Rajya Sabha | 20 | ₹58.00 L | 17 |
| Sasmit Patra Sitting Rajya Sabha | 13 | ₹34.30 L | 2 |
| Ashwini Vaishnaw Sitting Rajya Sabha | 4 | ₹3.89 Cr | 4 |
Sector read from each work’s description.
| Sector | Works | Sanctioned | To verify |
|---|---|---|---|
| Street Lighting | 109 | ₹70.41 L | 1 |
| Roads & Paving | 60 | ₹1.64 Cr | 5 |
| Community Buildings | 39 | ₹1.94 Cr | 7 |
| Education | 37 | ₹1.70 Cr | 4 |
| Religious & Cultural | 19 | ₹68.10 L | 4 |
| Sports | 6 | ₹13.00 L | 0 |
| Boundary & Protection | 4 | ₹11.00 L | 1 |
| Health | 4 | ₹3.41 Cr | 4 |
| Water | 3 | ₹7.00 L | 0 |
| Drainage & Sanitation | 2 | ₹5.50 L | 1 |
Ranked by score. Cost is judged against comparable works in this district and sector, so a high cost score means unlike its neighbours — not overpriced.
| Work | Agency | Status | Sanctioned | Delay | Cost vs peers | Score | Band |
|---|---|---|---|---|---|---|---|
| Construction of Yatri Niwas and Tourism Facilities. ₹5,000,000 against a ₹300,000 median for Community Buildings works in BALESHWAR (1567% above, 101 peer works) | Baleshwar(DISTRICT COLLECTOR BALESHWAR_IDA) | Recommended | ₹50.00 L | 387 d | +1567% | 75.8 | HIGH |
| Bus for Sanjeevani Express (Treatment of Dialysis patients) Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range | Baleshwar(DISTRICT COLLECTOR BALESHWAR_IDA) | Recommended | ₹29.00 L | 133 d | -66% | 60.3 | MEDIUM |
| Completion of Basanti Community Centre at Buanl GP Buanl Blo ₹500,000 against a ₹300,000 median for Community Buildings works in BALESHWAR (67% above, 101 peer works) | Baleshwar(DISTRICT COLLECTOR BALESHWAR_IDA) | Recommended | ₹5.00 L | 105 d | +67% | 57.1 | MEDIUM |
| Completion of Boundary wall with drain at Dolagobinda High S ₹300,000 against a ₹200,000 median for Drainage & Sanitation works in BALESHWAR (50% above, 11 peer works) | Baleshwar(DISTRICT COLLECTOR BALESHWAR_IDA) | Recommended | ₹3.00 L | 106 d | +50% | 53.1 | MEDIUM |
| Construction of Biju community centre at Madhusudhanpur GP S ₹450,000 against a ₹300,000 median for Community Buildings works in BALESHWAR (50% above, 101 peer works) | Baleshwar(DISTRICT COLLECTOR BALESHWAR_IDA) | Recommended | ₹4.50 L | 105 d | +50% | 52.9 | MEDIUM |
| Upgradation and Construction work at District Head Quarter H ₹17,000,000 against a ₹8,450,000 median for Health works in BALESHWAR (101% above, 8 peer works) | Baleshwar(DISTRICT COLLECTOR BALESHWAR_IDA) | Recommended | ₹1.70 Cr | — | +101% | 50.8 | MEDIUM |
| Construction of class room at Aurobindo Poornanga Shiksha Ga ₹1,000,000 against a ₹500,000 median for Education works in BALESHWAR (100% above, 95 peer works) | Baleshwar(DISTRICT COLLECTOR BALESHWAR_IDA) | Recommended | ₹10.00 L | — | +100% | 50.8 | MEDIUM |
| Installation of Solar light (15 watt) at Jharanaghati Hudisa ₹490,000 against a ₹125,000 median for Street Lighting works in BALESHWAR (292% above, 431 peer works) | Baleshwar(DISTRICT COLLECTOR BALESHWAR_IDA) | Completed | ₹4.90 L | — | +292% | 50.8 | MEDIUM |
| Construction of Biju Community Center near Maheswar Chhaka U 105 days beyond expected completion | Baleshwar(DISTRICT COLLECTOR BALESHWAR_IDA) | Recommended | ₹4.00 L | 105 d | +33% | 48.8 | MEDIUM |
| Construction of Biju Community Centre at Kuradhia GP Kurandh 105 days beyond expected completion | Baleshwar(DISTRICT COLLECTOR BALESHWAR_IDA) | Recommended | ₹4.00 L | 105 d | +33% | 48.8 | MEDIUM |
| Construction of CC Road from Hatasahi Tube well Chhaka to Na ₹380,000 against a ₹200,000 median for Roads & Paving works in BALESHWAR (90% above, 100 peer works) | Baleshwar(DISTRICT COLLECTOR BALESHWAR_IDA) | Recommended | ₹3.80 L | — | +90% | 48.3 | MEDIUM |
| Construction of Building,Saraswati Shishu Vidya Mandir, Bana ₹500,000 against a ₹295,733 median for Religious & Cultural works in BALESHWAR (69% above, 39 peer works) | Baleshwar(DISTRICT COLLECTOR BALESHWAR_IDA) | Recommended | ₹5.00 L | 180 d | +69% | 48.1 | MEDIUM |
| Construction of Building of Saraswati Shishu Mandir, Anantap ₹500,000 against a ₹295,733 median for Religious & Cultural works in BALESHWAR (69% above, 39 peer works) | Baleshwar(DISTRICT COLLECTOR BALESHWAR_IDA) | Recommended | ₹5.00 L | 180 d | +69% | 48.1 | MEDIUM |
| Consruction of Community Centre at Jhinkiria near Panchayat ₹500,000 against a ₹300,000 median for Community Buildings works in BALESHWAR (67% above, 101 peer works) | Baleshwar(DISTRICT COLLECTOR BALESHWAR_IDA) | Recommended | ₹5.00 L | 180 d | +67% | 47.5 | MEDIUM |
| Upgradation work at Sub-Divisional Hospital (SDH), Nilagiri ₹14,000,000 against a ₹8,450,000 median for Health works in BALESHWAR (66% above, 8 peer works) | Baleshwar(DISTRICT COLLECTOR BALESHWAR_IDA) | Recommended | ₹1.40 Cr | — | +66% | 47.3 | MEDIUM |