535 works across 1 implementing agency, recommended by 5 members of parliament. No allocation figure is published per district — every rupee below is summed from the works themselves.
The people a district authority actually supervises. Vendor concentration is counted from the payment records: an agency paying almost everything to one vendor is worth a question, not an accusation.
| # | Agency | Works | Completed | Sanctioned | To verify | Avg score | Top vendor |
|---|---|---|---|---|---|---|---|
| 1 | Baleshwar(DISTRICT COLLECTOR BALESHWAR_IDA) 1 high risk | 535 | 256 | ₹14.47 Cr | 127 | 29.2 | Ms Durga Traders 31% of spend · 62 vendors |
Whose funds paid for this district’s works.
| Member | Works | Sanctioned | To verify |
|---|---|---|---|
| Pratap Chandra Sarangi BALASORE | 454 | ₹8.77 Cr | 101 |
| Manjulata Mandal BHADRAK | 44 | ₹89.50 L | 3 |
| Sulata Deo Sitting Rajya Sabha | 20 | ₹58.00 L | 17 |
| Sasmit Patra Sitting Rajya Sabha | 13 | ₹34.30 L | 2 |
| Ashwini Vaishnaw Sitting Rajya Sabha | 4 | ₹3.89 Cr | 4 |
Sector read from each work’s description.
| Sector | Works | Sanctioned | To verify |
|---|---|---|---|
| Street Lighting | 322 | ₹3.71 Cr | 72 |
| Community Buildings | 62 | ₹2.57 Cr | 15 |
| Education | 58 | ₹2.35 Cr | 7 |
| Roads & Paving | 40 | ₹1.00 Cr | 14 |
| Religious & Cultural | 20 | ₹63.06 L | 6 |
| Drainage & Sanitation | 9 | ₹20.26 L | 4 |
| Boundary & Protection | 7 | ₹12.00 L | 1 |
| Sports | 6 | ₹19.00 L | 2 |
| Health | 4 | ₹3.41 Cr | 4 |
| Water | 3 | ₹7.00 L | 0 |
Patterns across an agency’s whole book of work. None of these move any individual work’s score.
An agency whose sanctions all arrive in the last quarter looks identical. This is a spending pattern, not a finding.
Round figures are normal and similar works legitimately cost the same. One figure covering nearly every work is what this looks for, and it means the costing is worth seeing, not that it is wrong.
Ranked by score. Cost is judged against comparable works in this district and sector, so a high cost score means unlike its neighbours — not overpriced.
| Work | Agency | Status | Sanctioned | Delay | Cost vs peers | Score | Band |
|---|---|---|---|---|---|---|---|
| Construction of Yatri Niwas and Tourism Facilities. ₹5,000,000 against a ₹300,000 median for Community Buildings works in BALESHWAR (1567% above, 101 peer works) | Baleshwar(DISTRICT COLLECTOR BALESHWAR_IDA) | Recommended | ₹50.00 L | 387 d | +1567% | 75.8 | HIGH |
| INSTALLATION OF 5 NOS 70WATT LED STREET LIGHT WITH FITTING I 584 days beyond expected completion | Baleshwar(DISTRICT COLLECTOR BALESHWAR_IDA) | Recommended | ₹26,000 | 584 d | -79% | 60.4 | MEDIUM |
| INSTALLATION OF 5 NOS 70WATT LED STREET LIGHT WITH FITTING I 584 days beyond expected completion | Baleshwar(DISTRICT COLLECTOR BALESHWAR_IDA) | Recommended | ₹26,000 | 584 d | -79% | 60.4 | MEDIUM |
| INSTALLATION OF 5 NOS 70WATT LED STREET LIGHT WITH FITTING I 584 days beyond expected completion | Baleshwar(DISTRICT COLLECTOR BALESHWAR_IDA) | Recommended | ₹26,000 | 584 d | -79% | 60.3 | MEDIUM |
| INSTALLATION OF 5 NOS 70WATT LED STREET LIGHT WITH FITTING I 584 days beyond expected completion | Baleshwar(DISTRICT COLLECTOR BALESHWAR_IDA) | Recommended | ₹26,000 | 584 d | -79% | 60.3 | MEDIUM |
| INSTALLATION OF 5 NOS 70WATT LED STREET LIGHT WITH FITTING I 584 days beyond expected completion | Baleshwar(DISTRICT COLLECTOR BALESHWAR_IDA) | Recommended | ₹26,000 | 584 d | -79% | 60.3 | MEDIUM |
| INSTALLATION OF 5 NOS 70WATT LED STREET LIGHT WITH FITTING I 584 days beyond expected completion | Baleshwar(DISTRICT COLLECTOR BALESHWAR_IDA) | Recommended | ₹26,000 | 584 d | -79% | 60.3 | MEDIUM |
| INSTALLATION OF 5 NOS 70WATT LED STREET LIGHT WITH FITTING I 584 days beyond expected completion | Baleshwar(DISTRICT COLLECTOR BALESHWAR_IDA) | Recommended | ₹26,000 | 584 d | -79% | 60.3 | MEDIUM |
| INSTALLATION OF 5 NOS 70WATT LED STREET LIGHT WITH FITTING I 584 days beyond expected completion | Baleshwar(DISTRICT COLLECTOR BALESHWAR_IDA) | Recommended | ₹26,000 | 584 d | -79% | 60.3 | MEDIUM |
| Bus for Sanjeevani Express (Treatment of Dialysis patients) Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range | Baleshwar(DISTRICT COLLECTOR BALESHWAR_IDA) | Recommended | ₹29.00 L | 133 d | -66% | 60.3 | MEDIUM |
| INSTALLATION OF 5 NOS 70WATT LED STREET LIGHT WITH FITTING I 584 days beyond expected completion | Baleshwar(DISTRICT COLLECTOR BALESHWAR_IDA) | Recommended | ₹26,000 | 584 d | -79% | 60.2 | MEDIUM |
| INSTALLATION OF 5 NOS 70WATT LED STREET LIGHT WITH FITTING I 584 days beyond expected completion | Baleshwar(DISTRICT COLLECTOR BALESHWAR_IDA) | Recommended | ₹26,000 | 584 d | -79% | 60.2 | MEDIUM |
| INSTALLATION OF 5 NOS 70WATT LED STREET LIGHT WITH FITTING I 584 days beyond expected completion | Baleshwar(DISTRICT COLLECTOR BALESHWAR_IDA) | Recommended | ₹26,000 | 584 d | -79% | 60.2 | MEDIUM |
| INSTALLATION OF 5 NOS 70WATT LED STREET LIGHT WITH FITTING I 584 days beyond expected completion | Baleshwar(DISTRICT COLLECTOR BALESHWAR_IDA) | Recommended | ₹26,000 | 584 d | -79% | 60.2 | MEDIUM |
| INSTALLATION OF 5 NOS 70WATT LED STREET LIGHT WITH FITTING I 584 days beyond expected completion | Baleshwar(DISTRICT COLLECTOR BALESHWAR_IDA) | Recommended | ₹26,000 | 584 d | -79% | 60.2 | MEDIUM |