94 works across 1 implementing agency, recommended by 3 members of parliament. No allocation figure is published per district — every rupee below is summed from the works themselves.
The people a district authority actually supervises. Vendor concentration is counted from the payment records: an agency paying almost everything to one vendor is worth a question, not an accusation.
| # | Agency | Works | Completed | Sanctioned | To verify | Avg score | Top vendor |
|---|---|---|---|---|---|---|---|
| 1 | JALNA(DISTRICT COLLECTOR JALNA_IDA) 3 high risk | 94 | 5 | ₹7.88 Cr | 89 | 52.0 | Yamuna Majur Sahakari Sanstha Ltd Sonak Pimpalgaon 6% of spend · 49 vendors |
Whose funds paid for this district’s works.
| Member | Works | Sanctioned | To verify |
|---|---|---|---|
| Raosaheb Dadarao Danve JALNA | 58 | ₹4.99 Cr | 58 |
| Sanjay Haribhau Jadhav PARBHANI | 23 | ₹1.59 Cr | 18 |
| Imran Pratapgarhi Sitting Rajya Sabha | 13 | ₹1.30 Cr | 13 |
Sector read from each work’s description.
| Sector | Works | Sanctioned | To verify |
|---|---|---|---|
| Roads & Paving | 53 | ₹4.22 Cr | 50 |
| Community Buildings | 30 | ₹2.82 Cr | 28 |
| Religious & Cultural | 7 | ₹50.94 L | 7 |
| Education | 3 | ₹29.97 L | 3 |
| Boundary & Protection | 1 | ₹2.49 L | 1 |
Patterns across an agency’s whole book of work. None of these move any individual work’s score.
An agency whose sanctions all arrive in the last quarter looks identical. This is a spending pattern, not a finding.
Ranked by score. Cost is judged against comparable works in this district and sector, so a high cost score means unlike its neighbours — not overpriced.
| Work | Agency | Status | Sanctioned | Delay | Cost vs peers | Score | Band |
|---|---|---|---|---|---|---|---|
| Construction of cement concrete road from Main Road To Ansar Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range | JALNA(DISTRICT COLLECTOR JALNA_IDA) | Recommended | ₹10.00 L | 342 d | 0% | 70.0 | HIGH |
| Construction of cement concrete road internal Shamshan Bhumi Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range | JALNA(DISTRICT COLLECTOR JALNA_IDA) | Recommended | ₹10.00 L | 342 d | 0% | 70.0 | HIGH |
| Construction of cement concrete road internal Idgah Qabrista Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range | JALNA(DISTRICT COLLECTOR JALNA_IDA) | Recommended | ₹10.00 L | 342 d | 0% | 70.0 | HIGH |
| Construction of cement road from Javed Pathan House to Rahim Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range | JALNA(DISTRICT COLLECTOR JALNA_IDA) | Recommended | ₹10.00 L | 356 d | 0% | 70.0 | MEDIUM |
| Construction of cement road from Feroz House to Manjur Bagwa Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range | JALNA(DISTRICT COLLECTOR JALNA_IDA) | Recommended | ₹10.00 L | 356 d | 0% | 70.0 | MEDIUM |
| Construction of cement road from Moosa Shah House to Gaffar Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range | JALNA(DISTRICT COLLECTOR JALNA_IDA) | Recommended | ₹10.00 L | 356 d | 0% | 70.0 | MEDIUM |
| Construction of cement road from Amitabh Nhonsale House to V Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range | JALNA(DISTRICT COLLECTOR JALNA_IDA) | Recommended | ₹10.00 L | 356 d | 0% | 70.0 | MEDIUM |
| Construction of cement road from main road to Patel (Momin) Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range | JALNA(DISTRICT COLLECTOR JALNA_IDA) | Recommended | ₹10.00 L | 356 d | 0% | 70.0 | MEDIUM |
| Paving and Strengthening of road from Gori Jankshan to Laksh Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range | JALNA(DISTRICT COLLECTOR JALNA_IDA) | Recommended | ₹10.00 L | 356 d | 0% | 70.0 | MEDIUM |
| Construction of cement road from hadi bhai house to rafiq bh Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range | JALNA(DISTRICT COLLECTOR JALNA_IDA) | Recommended | ₹10.00 L | 356 d | 0% | 70.0 | MEDIUM |
| Construction of compound wall and cement road at Muslim Kabr Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range | JALNA(DISTRICT COLLECTOR JALNA_IDA) | Recommended | ₹10.00 L | 356 d | 0% | 70.0 | MEDIUM |
| Construction of compound wall and cement road at Bagwan kabr Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range | JALNA(DISTRICT COLLECTOR JALNA_IDA) | Recommended | ₹10.00 L | 356 d | 0% | 70.0 | MEDIUM |
| Construction of compound wall and cement road at Pathan Kabr Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range | JALNA(DISTRICT COLLECTOR JALNA_IDA) | Recommended | ₹10.00 L | 356 d | 0% | 70.0 | MEDIUM |
| Construction of cement road at Daregaon Ta.Dist. Jalna Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range | JALNA(DISTRICT COLLECTOR JALNA_IDA) | Recommended | ₹7.00 L | 660 d | -30% | 65.7 | MEDIUM |
| Construction of cement road at Daregaon Ta.Jalna (S.C.) 582 days beyond expected completion | JALNA(DISTRICT COLLECTOR JALNA_IDA) | Recommended | ₹5.95 L | 582 d | -41% | 63.8 | MEDIUM |