Construction of cement road at Daregaon Ta.Jalna (S.C.)
Roads & Paving
Maharashtra / JALNA — JALNA(DISTRICT COLLECTOR JALNA_IDA) · Raosaheb Dadarao Danve (JALNA)
Overall risk score
64/100
Blended from the five components below, each weighted as shown.
Risk components
Cost39
Delay100
Duplication80
Agency87
Compliance0
Sanctioned
₹5.95 L
Delay
582d
Cost deviation
-41%
Work status
Recommended
AI powered · gemini-flash-liteWhy was this flagged?
- 582 days beyond expected completionPublished dates
- 99% similarity with another nearby workAI · Sentence-BERT embeddings (all-MiniLM-L6-v2)
- Implementing agency has a 87% delay rate across its projectsStated compliance rule
Decision trail
Nobody has recorded a decision on this work yet.
Reads as a near-duplicate of work #31209 (sentence-embedding similarity 0.99, measured by all-MiniLM-L6-v2 on meaning rather than shared words; two works can legitimately share a description, so this is a prompt to check, not a finding)