58 works across 1 implementing agency, recommended by 4 members of parliament. No allocation figure is published per district — every rupee below is summed from the works themselves.
The people a district authority actually supervises. Vendor concentration is counted from the payment records: an agency paying almost everything to one vendor is worth a question, not an accusation.
| # | Agency | Works | Completed | Sanctioned | To verify | Avg score | Top vendor |
|---|---|---|---|---|---|---|---|
| 1 | YADGIR(Deputy Commsioner Yadgir_ida) | 58 | 3 | ₹5.32 Cr | 4 | 22.3 | NIRMITHI KENDRA YADGIR 48% of spend · 4 vendors |
Whose funds paid for this district’s works.
| Member | Works | Sanctioned | To verify |
|---|---|---|---|
| G Kumar Naik RAICHUR | 42 | ₹3.66 Cr | 3 |
| Jairam Ramesh Sitting Rajya Sabha | 12 | ₹96.00 L | 0 |
| Radhakrishna GULBARGA | 3 | ₹20.00 L | 0 |
| Nirmala Sitharaman Sitting Rajya Sabha | 1 | ₹50.00 L | 1 |
Sector read from each work’s description.
| Sector | Works | Sanctioned | To verify |
|---|---|---|---|
| Community Buildings | 17 | ₹2.50 Cr | 2 |
| Roads & Paving | 12 | ₹87.00 L | 0 |
| Water | 12 | ₹96.00 L | 0 |
| Education | 8 | ₹50.80 L | 2 |
| Street Lighting | 6 | ₹30.00 L | 0 |
| Equipment & Vehicles | 1 | ₹6.00 L | 0 |
| Drainage & Sanitation | 1 | ₹2.00 L | 0 |
| Boundary & Protection | 1 | ₹10.00 L | 0 |
Ranked by score. Cost is judged against comparable works in this district and sector, so a high cost score means unlike its neighbours — not overpriced.
| Work | Agency | Status | Sanctioned | Delay | Cost vs peers | Score | Band |
|---|---|---|---|---|---|---|---|
| Construction of Shikshara bhavana at Shahapur town ₹1,000,000 against a ₹500,000 median for Education works in YADGIR (100% above, 10 peer works) | YADGIR(Deputy Commsioner Yadgir_ida) | Recommended | ₹10.00 L | 195 d | +100% | 53.0 | MEDIUM |
| construction samudhay bhavan near Durgamma temple at bhach ₹2,000,000 against a ₹1,000,000 median for Community Buildings works in YADGIR (100% above, 25 peer works) | YADGIR(Deputy Commsioner Yadgir_ida) | Recommended | ₹20.00 L | 163 d | +100% | 50.7 | MEDIUM |
| construction samudhaya bhavan near govt,higher primary scho ₹1,000,000 against a ₹500,000 median for Education works in YADGIR (100% above, 10 peer works) | YADGIR(Deputy Commsioner Yadgir_ida) | Recommended | ₹10.00 L | 163 d | +100% | 50.7 | MEDIUM |
| Setting up of Farmers Training Center and Common Facility Ce ₹5,000,000 against a ₹1,000,000 median for Community Buildings works in YADGIR (400% above, 25 peer works) | YADGIR(Deputy Commsioner Yadgir_ida) | Completed | ₹50.00 L | — | +400% | 48.0 | MEDIUM |
| construction samudhaya bhavan behind Police station at gogip ₹1,500,000 against a ₹1,000,000 median for Community Buildings works in YADGIR (50% above, 25 peer works) | YADGIR(Deputy Commsioner Yadgir_ida) | Recommended | ₹15.00 L | 163 d | +50% | 38.2 | LOW |
| Construction of Samuday bhavan at Gogi K village 195 days beyond expected completion | YADGIR(Deputy Commsioner Yadgir_ida) | Recommended | ₹10.00 L | 195 d | 0% | 37.4 | LOW |
| Construction of Compound wall to Buddha vihar at Madriki vil 195 days beyond expected completion | YADGIR(Deputy Commsioner Yadgir_ida) | Recommended | ₹10.00 L | 195 d | 0% | 37.4 | LOW |
| Road improvement work from Wadigere Taluk shivapur village r 179 days beyond expected completion | YADGIR(Deputy Commsioner Yadgir_ida) | Recommended | ₹50,000 | 179 d | -90% | 36.7 | LOW |
| Road improvement work in Shivapur village near Govt,primary 179 days beyond expected completion | YADGIR(Deputy Commsioner Yadgir_ida) | Recommended | ₹50,000 | 179 d | -90% | 36.7 | LOW |
| Construction compand wall to Govt,high School in Shivapur vi 179 days beyond expected completion | YADGIR(Deputy Commsioner Yadgir_ida) | Recommended | ₹1.00 L | 179 d | -80% | 35.7 | LOW |
| CC Road improvement work in Shivapur village inforant of Du 179 days beyond expected completion | YADGIR(Deputy Commsioner Yadgir_ida) | Recommended | ₹1.00 L | 179 d | -80% | 35.7 | LOW |
| construction samudhaya bhavan near mailarlinga temple at dev 163 days beyond expected completion | YADGIR(Deputy Commsioner Yadgir_ida) | Recommended | ₹10.00 L | 163 d | 0% | 34.7 | LOW |
| continuation work of Construction of samudhaya bhavan at g 163 days beyond expected completion | YADGIR(Deputy Commsioner Yadgir_ida) | Recommended | ₹10.00 L | 163 d | 0% | 34.7 | LOW |
| Constucation work at Toilet Room in Govt,high school in Shiv 179 days beyond expected completion | YADGIR(Deputy Commsioner Yadgir_ida) | Recommended | ₹2.00 L | 179 d | 0% | 34.0 | LOW |
| construction samskruthik bhavan near shree bramar guhadevi m 163 days beyond expected completion | YADGIR(Deputy Commsioner Yadgir_ida) | Recommended | ₹5.00 L | 163 d | -50% | 31.9 | LOW |