131 works across 1 implementing agency, recommended by 4 members of parliament. No allocation figure is published per district — every rupee below is summed from the works themselves.
The people a district authority actually supervises. Vendor concentration is counted from the payment records: an agency paying almost everything to one vendor is worth a question, not an accusation.
| # | Agency | Works | Completed | Sanctioned | To verify | Avg score | Top vendor |
|---|---|---|---|---|---|---|---|
| 1 | YADGIR(Deputy Commsioner Yadgir_ida) | 131 | 96 | ₹7.21 Cr | 2 | 13.2 | N S Sajjan LLP 31% of spend · 25 vendors |
Whose funds paid for this district’s works.
| Member | Works | Sanctioned | To verify |
|---|---|---|---|
| Raja Amareshwara Naik RAICHUR | 83 | ₹4.07 Cr | 1 |
| Umesh G. Jadhav GULBARGA | 35 | ₹1.68 Cr | 0 |
| Jairam Ramesh Sitting Rajya Sabha | 12 | ₹96.00 L | 0 |
| Nirmala Sitharaman Sitting Rajya Sabha | 1 | ₹50.00 L | 1 |
Sector read from each work’s description.
| Sector | Works | Sanctioned | To verify |
|---|---|---|---|
| Street Lighting | 58 | ₹2.84 Cr | 1 |
| Roads & Paving | 29 | ₹1.39 Cr | 0 |
| Religious & Cultural | 17 | ₹82.94 L | 0 |
| Water | 14 | ₹1.06 Cr | 0 |
| Community Buildings | 8 | ₹84.90 L | 1 |
| Education | 2 | ₹10.00 L | 0 |
| Drainage & Sanitation | 2 | ₹8.84 L | 0 |
| Health | 1 | ₹4.86 L | 0 |
Patterns across an agency’s whole book of work. None of these move any individual work’s score.
The whole population fails the textbook test — the median agency scores 6.2 where Nigrini calls 1.5 nonconformant — because MPLADS amounts are capped, rounded and repeated by design. This ranks agencies against each other, not against the law. It is the weakest signal here and is never evidence on its own.
Ranked by score. Cost is judged against comparable works in this district and sector, so a high cost score means unlike its neighbours — not overpriced.
| Work | Agency | Status | Sanctioned | Delay | Cost vs peers | Score | Band |
|---|---|---|---|---|---|---|---|
| Setting up of Farmers Training Center and Common Facility Ce ₹5,000,000 against a ₹1,000,000 median for Community Buildings works in YADGIR (400% above, 25 peer works) | YADGIR(Deputy Commsioner Yadgir_ida) | Completed | ₹50.00 L | — | +400% | 48.0 | MEDIUM |
| 14) Installation of Highmask light near Valmiki circle of Ma Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range | YADGIR(Deputy Commsioner Yadgir_ida) | Recommended | ₹5.00 L | 758 d | +3% | 40.1 | MEDIUM |
| Formation of road from Govt LPS Allipur Vari Tanda to Namdev Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range | YADGIR(Deputy Commsioner Yadgir_ida) | Recommended | ₹5.00 L | 690 d | +1% | 38.0 | LOW |
| Road Formation, CC and Drainage from Saidapur Station KEB co 666 days beyond expected completion | YADGIR(Deputy Commsioner Yadgir_ida) | Recommended | ₹4.50 L | 666 d | -9% | 37.3 | LOW |
| CC Road from Bikasing house to Rakesh house at Saidapur Stat 666 days beyond expected completion | YADGIR(Deputy Commsioner Yadgir_ida) | Recommended | ₹4.00 L | 666 d | -19% | 36.9 | LOW |
| CC Road from Bhimabai House to Hanamanth House at Lingera Ta 646 days beyond expected completion | YADGIR(Deputy Commsioner Yadgir_ida) | Recommended | ₹5.00 L | 646 d | +1% | 36.8 | LOW |
| CC Road from Yadgir Harkera Main Road to Reddy Ramu Pawar Ho 646 days beyond expected completion | YADGIR(Deputy Commsioner Yadgir_ida) | Recommended | ₹4.99 L | 646 d | +1% | 36.8 | LOW |
| Construction of Samskrutik bhavan at Sri Vaggarayanna mutya 546 days beyond expected completion | YADGIR(Deputy Commsioner Yadgir_ida) | Recommended | ₹5.00 L | 546 d | -50% | 36.5 | LOW |
| Construction of 01 school room at Sri Swayambhu vara siddivi 629 days beyond expected completion | YADGIR(Deputy Commsioner Yadgir_ida) | Recommended | ₹5.00 L | 629 d | 0% | 36.5 | LOW |
| 2) Construction of Samskrutik Bhavan near Sri Hingulambika D 629 days beyond expected completion | YADGIR(Deputy Commsioner Yadgir_ida) | Recommended | ₹5.00 L | 629 d | -50% | 36.5 | LOW |
| 2) Construction of Samskrutik Bhavan near Golden Cave Buddha 629 days beyond expected completion | YADGIR(Deputy Commsioner Yadgir_ida) | Recommended | ₹5.00 L | 629 d | -50% | 36.5 | LOW |
| Formation of Road from Basavanpur Road to Kasanhari Devastan 623 days beyond expected completion | YADGIR(Deputy Commsioner Yadgir_ida) | Recommended | ₹5.00 L | 623 d | +1% | 36.3 | LOW |
| Construction of Sanskrit Bhawan near Sri Sevalal Temple at M 623 days beyond expected completion | YADGIR(Deputy Commsioner Yadgir_ida) | Recommended | ₹5.00 L | 623 d | -50% | 36.3 | LOW |
| CC Road from Ranganna House to Dasar House at Kudluru Villag 552 days beyond expected completion | YADGIR(Deputy Commsioner Yadgir_ida) | Recommended | ₹5.00 L | 552 d | +1% | 36.3 | LOW |
| Installation of Highmast Lamp at Shree Nija Sharana Ambigar 552 days beyond expected completion | YADGIR(Deputy Commsioner Yadgir_ida) | Recommended | ₹5.00 L | 552 d | +3% | 36.3 | LOW |