88 works across 1 implementing agency, recommended by 3 members of parliament. No allocation figure is published per district — every rupee below is summed from the works themselves.
The people a district authority actually supervises. Vendor concentration is counted from the payment records: an agency paying almost everything to one vendor is worth a question, not an accusation.
| # | Agency | Works | Completed | Sanctioned | To verify | Avg score | Top vendor |
|---|---|---|---|---|---|---|---|
| 1 | CHIKKABALLAPURA(DEPUTY COMMISSIONER CHICKKABALLAPUR_IDA) 4 high risk | 88 | 54 | ₹4.24 Cr | 34 | 32.1 | Project Manager 33% of spend · 8 vendors |
Whose funds paid for this district’s works.
| Member | Works | Sanctioned | To verify |
|---|---|---|---|
| S. Muniswamy KOLAR | 54 | ₹2.04 Cr | 14 |
| Bache Gowda B.N. CHIKBALLAPUR | 33 | ₹2.05 Cr | 20 |
| Dharmasthala Veerendra Heggade Nominated Rajya Sabha | 1 | ₹15.00 L | 0 |
Sector read from each work’s description.
| Sector | Works | Sanctioned | To verify |
|---|---|---|---|
| Community Buildings | 35 | ₹1.90 Cr | 16 |
| Street Lighting | 27 | ₹67.69 L | 6 |
| Roads & Paving | 22 | ₹1.38 Cr | 12 |
| Religious & Cultural | 2 | ₹7.99 L | 0 |
| Drainage & Sanitation | 1 | ₹5.00 L | 0 |
| Education | 1 | ₹15.00 L | 0 |
Patterns across an agency’s whole book of work. None of these move any individual work’s score.
An agency whose sanctions all arrive in the last quarter looks identical. This is a spending pattern, not a finding.
The whole population fails the textbook test — the median agency scores 6.2 where Nigrini calls 1.5 nonconformant — because MPLADS amounts are capped, rounded and repeated by design. This ranks agencies against each other, not against the law. It is the weakest signal here and is never evidence on its own.
Ranked by score. Cost is judged against comparable works in this district and sector, so a high cost score means unlike its neighbours — not overpriced.
| Work | Agency | Status | Sanctioned | Delay | Cost vs peers | Score | Band |
|---|---|---|---|---|---|---|---|
| Construction of Community hall ₹1,000,000 against a ₹499,000 median for Community Buildings works in CHIKKABALLAPURA (100% above, 56 peer works) | CHIKKABALLAPURA(DEPUTY COMMISSIONER CHICKKABALLAPUR_IDA) | Recommended | ₹10.00 L | 600 d | +100% | 76.3 | HIGH |
| Road Development ₹1,000,000 against a ₹500,000 median for Roads & Paving works in CHIKKABALLAPURA (100% above, 36 peer works) | CHIKKABALLAPURA(DEPUTY COMMISSIONER CHICKKABALLAPUR_IDA) | Recommended | ₹10.00 L | 610 d | +100% | 76.3 | HIGH |
| Road Development ₹1,200,000 against a ₹500,000 median for Roads & Paving works in CHIKKABALLAPURA (140% above, 36 peer works) | CHIKKABALLAPURA(DEPUTY COMMISSIONER CHICKKABALLAPUR_IDA) | Recommended | ₹12.00 L | 610 d | +140% | 76.3 | HIGH |
| Road Development ₹900,000 against a ₹500,000 median for Roads & Paving works in CHIKKABALLAPURA (80% above, 36 peer works) | CHIKKABALLAPURA(DEPUTY COMMISSIONER CHICKKABALLAPUR_IDA) | Recommended | ₹9.00 L | 610 d | +80% | 71.3 | HIGH |
| Construction of Bus Stand 633 days beyond expected completion | CHIKKABALLAPURA(DEPUTY COMMISSIONER CHICKKABALLAPUR_IDA) | Recommended | ₹5.00 L | 633 d | +0% | 60.0 | MEDIUM |
| CC Road 633 days beyond expected completion | CHIKKABALLAPURA(DEPUTY COMMISSIONER CHICKKABALLAPUR_IDA) | Recommended | ₹5.00 L | 633 d | 0% | 60.0 | MEDIUM |
| CC Road 633 days beyond expected completion | CHIKKABALLAPURA(DEPUTY COMMISSIONER CHICKKABALLAPUR_IDA) | Recommended | ₹5.00 L | 633 d | 0% | 60.0 | MEDIUM |
| CC Road 633 days beyond expected completion | CHIKKABALLAPURA(DEPUTY COMMISSIONER CHICKKABALLAPUR_IDA) | Recommended | ₹5.00 L | 633 d | 0% | 60.0 | MEDIUM |
| Road Development 610 days beyond expected completion | CHIKKABALLAPURA(DEPUTY COMMISSIONER CHICKKABALLAPUR_IDA) | Recommended | ₹5.00 L | 610 d | 0% | 59.3 | MEDIUM |
| Road Development 610 days beyond expected completion | CHIKKABALLAPURA(DEPUTY COMMISSIONER CHICKKABALLAPUR_IDA) | Recommended | ₹5.00 L | 610 d | 0% | 59.3 | MEDIUM |
| Road Development 610 days beyond expected completion | CHIKKABALLAPURA(DEPUTY COMMISSIONER CHICKKABALLAPUR_IDA) | Recommended | ₹5.00 L | 610 d | 0% | 59.3 | MEDIUM |
| Construction of Community Hall 610 days beyond expected completion | CHIKKABALLAPURA(DEPUTY COMMISSIONER CHICKKABALLAPUR_IDA) | Recommended | ₹5.00 L | 610 d | +0% | 59.3 | MEDIUM |
| Road Development 610 days beyond expected completion | CHIKKABALLAPURA(DEPUTY COMMISSIONER CHICKKABALLAPUR_IDA) | Recommended | ₹5.00 L | 610 d | 0% | 59.3 | MEDIUM |
| Construction of Road and Drain ₹1,000,000 against a ₹500,000 median for Roads & Paving works in CHIKKABALLAPURA (100% above, 36 peer works) | CHIKKABALLAPURA(DEPUTY COMMISSIONER CHICKKABALLAPUR_IDA) | Recommended | ₹10.00 L | 610 d | +100% | 56.3 | MEDIUM |
| Construction of first floor for media association ₹1,000,000 against a ₹499,000 median for Community Buildings works in CHIKKABALLAPURA (100% above, 56 peer works) | CHIKKABALLAPURA(DEPUTY COMMISSIONER CHICKKABALLAPUR_IDA) | Recommended | ₹10.00 L | 633 d | +100% | 56.3 | MEDIUM |