CC Road
Roads & Paving
Karnataka / CHIKKABALLAPURA — CHIKKABALLAPURA(DEPUTY COMMISSIONER CHICKKABALLAPUR_IDA) · Bache Gowda B.N. (CHIKBALLAPUR)
Overall risk score
60/100
Blended from the five components below, each weighted as shown.
Risk components
Cost35
Delay100
Duplication100
Agency42
Compliance0
Sanctioned
₹5.00 L
Delay
633d
Cost deviation
0%
Work status
Recommended
AI powered · gemini-flash-liteWhy was this flagged?
- 633 days beyond expected completionPublished dates
- 100% similarity with another nearby workAI · Sentence-BERT embeddings (all-MiniLM-L6-v2)
- Implementing agency has a 42% delay rate across its projectsStated compliance rule
Decision trail
Nobody has recorded a decision on this work yet.
Reads as a near-duplicate of work #28510 (sentence-embedding similarity 1.00, measured by all-MiniLM-L6-v2 on meaning rather than shared words; two works can legitimately share a description, so this is a prompt to check, not a finding)