86 works across 1 implementing agency, recommended by 1 member of parliament. No allocation figure is published per district — every rupee below is summed from the works themselves.
The people a district authority actually supervises. Vendor concentration is counted from the payment records: an agency paying almost everything to one vendor is worth a question, not an accusation.
| # | Agency | Works | Completed | Sanctioned | To verify | Avg score | Top vendor |
|---|---|---|---|---|---|---|---|
| 1 | LATEHAR(Deputy Commissioner latehar_IDA) | 86 | 22 | ₹2.14 Cr | 0 | 11.2 | NARESH MANDAL JE ZILA PARISHAD LATEHAR 50% of spend · 5 vendors |
Whose funds paid for this district’s works.
| Member | Works | Sanctioned | To verify |
|---|---|---|---|
| Kali Charan Singh CHATRA | 86 | ₹2.14 Cr | 0 |
Sector read from each work’s description.
| Sector | Works | Sanctioned | To verify |
|---|---|---|---|
| Roads & Paving | 50 | ₹1.24 Cr | 0 |
| Community Buildings | 29 | ₹67.96 L | 0 |
| Water | 3 | ₹8.99 L | 0 |
| Education | 2 | ₹7.50 L | 0 |
| Religious & Cultural | 2 | ₹5.50 L | 0 |
Patterns across an agency’s whole book of work. None of these move any individual work’s score.
Round figures are normal and similar works legitimately cost the same. One figure covering nearly every work is what this looks for, and it means the costing is worth seeing, not that it is wrong.
Ranked by score. Cost is judged against comparable works in this district and sector, so a high cost score means unlike its neighbours — not overpriced.
| Work | Agency | Status | Sanctioned | Delay | Cost vs peers | Score | Band |
|---|---|---|---|---|---|---|---|
| Repair of Bhalukera Ahar 113 days beyond expected completion | LATEHAR(Deputy Commissioner latehar_IDA) | Recommended | ₹3.00 L | 113 d | 0% | 29.1 | LOW |
| Construction of Sanskriti Bhawan in Sant. Sri Nageshwar Swam 108 days beyond expected completion | LATEHAR(Deputy Commissioner latehar_IDA) | Recommended | ₹5.00 L | 108 d | 0% | 28.3 | LOW |
| Construction of PCC road on bhid of dumaria ahar (Block-Bari 88 days beyond expected completion | LATEHAR(Deputy Commissioner latehar_IDA) | Recommended | ₹2.50 L | 88 d | 0% | 25.4 | LOW |
| Construction of Gate in high school (Block-Bariyatu, Panchay 88 days beyond expected completion | LATEHAR(Deputy Commissioner latehar_IDA) | Recommended | ₹2.50 L | 88 d | 0% | 25.4 | LOW |
| Construction of Ashamshan shed in Haram (Block-Balumath, Pan 50% of this agency's ₹9,465,816 spend went to one vendor (NARESH MANDAL JE ZILA PARISHAD LATEHAR), across 5 vendors and 39 transactions | LATEHAR(Deputy Commissioner latehar_IDA) | Recommended | ₹2.00 L | 23 d | -20% | 22.7 | LOW |
| Construction of Ashamshan shed (Block-Balumath, Panchayat-Ma 50% of this agency's ₹9,465,816 spend went to one vendor (NARESH MANDAL JE ZILA PARISHAD LATEHAR), across 5 vendors and 39 transactions | LATEHAR(Deputy Commissioner latehar_IDA) | Recommended | ₹2.00 L | 23 d | -20% | 22.7 | LOW |
| Construction of Ashamshan Shed in Rajwar Nadi (Block-Balumat 50% of this agency's ₹9,465,816 spend went to one vendor (NARESH MANDAL JE ZILA PARISHAD LATEHAR), across 5 vendors and 39 transactions | LATEHAR(Deputy Commissioner latehar_IDA) | Recommended | ₹2.00 L | 23 d | -20% | 16.1 | LOW |
| Construction of PCC Road from house of biru saw to shiv mand 50% of this agency's ₹9,465,816 spend went to one vendor (NARESH MANDAL JE ZILA PARISHAD LATEHAR), across 5 vendors and 39 transactions | LATEHAR(Deputy Commissioner latehar_IDA) | Recommended | ₹2.00 L | 23 d | -20% | 16.1 | LOW |
| Construction of shed in Ashamsan Ghat (Block-Balumath, Panch 50% of this agency's ₹9,465,816 spend went to one vendor (NARESH MANDAL JE ZILA PARISHAD LATEHAR), across 5 vendors and 39 transactions | LATEHAR(Deputy Commissioner latehar_IDA) | Recommended | ₹2.00 L | 23 d | -20% | 16.1 | LOW |
| Construction of shed in Ashashman Ghat in Chatti Tola (Block 50% of this agency's ₹9,465,816 spend went to one vendor (NARESH MANDAL JE ZILA PARISHAD LATEHAR), across 5 vendors and 39 transactions | LATEHAR(Deputy Commissioner latehar_IDA) | Recommended | ₹2.00 L | 23 d | -20% | 16.1 | LOW |
| Construction of steps near pahadi mandir (Block-Balumath, Pa 50% of this agency's ₹9,465,816 spend went to one vendor (NARESH MANDAL JE ZILA PARISHAD LATEHAR), across 5 vendors and 39 transactions | LATEHAR(Deputy Commissioner latehar_IDA) | Recommended | ₹3.00 L | 23 d | 0% | 15.7 | LOW |
| construction of Smshan Shed in village-Rampur, Panchait-Mahu Completed work has no photographic documentation on record | LATEHAR(Deputy Commissioner latehar_IDA) | Completed | ₹1.50 L | — | -40% | 14.5 | LOW |
| construction of Viwah Mandap vill-Sidra, Panchait-Champa, Bl Completed work has no photographic documentation on record | LATEHAR(Deputy Commissioner latehar_IDA) | Completed | ₹1.50 L | — | -40% | 14.5 | LOW |
| Repair of Belargodi Ahar Completed work has no photographic documentation on record | LATEHAR(Deputy Commissioner latehar_IDA) | Completed | ₹2.99 L | — | -0% | 14.0 | LOW |
| construction of P.C.C. Road from House of Mantu Krishna to H Completed work has no photographic documentation on record | LATEHAR(Deputy Commissioner latehar_IDA) | Completed | ₹2.49 L | — | -0% | 13.7 | LOW |