23 works across 1 implementing agency, recommended by 1 member of parliament. No allocation figure is published per district — every rupee below is summed from the works themselves.
The people a district authority actually supervises. Vendor concentration is counted from the payment records: an agency paying almost everything to one vendor is worth a question, not an accusation.
| # | Agency | Works | Completed | Sanctioned | To verify | Avg score | Top vendor |
|---|---|---|---|---|---|---|---|
| 1 | LATEHAR(Deputy Commissioner latehar_IDA) | 23 | 11 | ₹69.95 L | 1 | 23.0 | NIRANJAN PRASAD MEHTA JE NREP LATEHAR 47% of spend · 4 vendors |
Whose funds paid for this district’s works.
| Member | Works | Sanctioned | To verify |
|---|---|---|---|
| Sunil Kumar Singh CHATRA | 23 | ₹69.95 L | 1 |
Sector read from each work’s description.
| Sector | Works | Sanctioned | To verify |
|---|---|---|---|
| Roads & Paving | 13 | ₹39.96 L | 1 |
| Water | 6 | ₹17.99 L | 0 |
| Community Buildings | 2 | ₹6.00 L | 0 |
| Boundary & Protection | 1 | ₹3.00 L | 0 |
| Education | 1 | ₹3.00 L | 0 |
Ranked by score. Cost is judged against comparable works in this district and sector, so a high cost score means unlike its neighbours — not overpriced.
| Work | Agency | Status | Sanctioned | Delay | Cost vs peers | Score | Band |
|---|---|---|---|---|---|---|---|
| From Mr. Fhagu Mistry's house to Mr. Binesar Singh's house S ₹400,000 against a ₹250,000 median for Roads & Paving works in LATEHAR (60% above, 63 peer works) | LATEHAR(Deputy Commissioner latehar_IDA) | Recommended | ₹4.00 L | 559 d | +60% | 42.2 | MEDIUM |
| Moram path repair from Mandev Mistry's house to Tevrahi in V 559 days beyond expected completion | LATEHAR(Deputy Commissioner latehar_IDA) | Recommended | ₹3.00 L | 559 d | +20% | 34.3 | LOW |
| Construction of PCC road from Keshwari Singh's house to Raje 559 days beyond expected completion | LATEHAR(Deputy Commissioner latehar_IDA) | Recommended | ₹3.00 L | 559 d | +20% | 34.3 | LOW |
| Construction of PCC path from Rajesh Oraon's house to water 559 days beyond expected completion | LATEHAR(Deputy Commissioner latehar_IDA) | Recommended | ₹3.00 L | 559 d | 0% | 34.3 | LOW |
| Construction of soil moram path from Saryu main road to Ramc 559 days beyond expected completion | LATEHAR(Deputy Commissioner latehar_IDA) | Recommended | ₹3.00 L | 559 d | +20% | 34.3 | LOW |
| Renovation work of Dhartipatra Dam in Village-Nareshgarh. 559 days beyond expected completion | LATEHAR(Deputy Commissioner latehar_IDA) | Recommended | ₹3.00 L | 559 d | 0% | 34.3 | LOW |
| Construction of boundary wall of Ward No. 5, Duruva Communit 559 days beyond expected completion | LATEHAR(Deputy Commissioner latehar_IDA) | Recommended | ₹3.00 L | 559 d | +20% | 34.3 | LOW |
| Maintenance work of the well located in the market of Pancha 559 days beyond expected completion | LATEHAR(Deputy Commissioner latehar_IDA) | Recommended | ₹3.00 L | 559 d | 0% | 34.3 | LOW |
| PCC road construction from Gopal Singh's house to Sohar Bhui 559 days beyond expected completion | LATEHAR(Deputy Commissioner latehar_IDA) | Recommended | ₹3.00 L | 559 d | +20% | 34.3 | LOW |
| Construction of soil moram path from Chanakya Nagri ward num 559 days beyond expected completion | LATEHAR(Deputy Commissioner latehar_IDA) | Recommended | ₹3.00 L | 559 d | +20% | 34.3 | LOW |
| Construction of PCC road from village Serandag Balwant Yadav 559 days beyond expected completion | LATEHAR(Deputy Commissioner latehar_IDA) | Recommended | ₹3.00 L | 559 d | +20% | 34.3 | LOW |
| Construction of guard wall in village Dumri Pain of Panchaya 559 days beyond expected completion | LATEHAR(Deputy Commissioner latehar_IDA) | Recommended | ₹3.00 L | 559 d | 0% | 34.3 | LOW |
| Soil moram path leveling work from Panchayat Sinjo Bari to K Completed work has no photographic documentation on record | LATEHAR(Deputy Commissioner latehar_IDA) | Completed | ₹3.00 L | — | +20% | 11.7 | LOW |
| Repair of soil moram path from Bihari Singh's house to Simar Completed work has no photographic documentation on record | LATEHAR(Deputy Commissioner latehar_IDA) | Completed | ₹3.00 L | — | +20% | 11.7 | LOW |
| Construction of soil moram road from PWD road to Churra Sarn Completed work has no photographic documentation on record | LATEHAR(Deputy Commissioner latehar_IDA) | Completed | ₹3.00 L | — | +20% | 11.7 | LOW |