144 works across 1 implementing agency, recommended by 2 members of parliament. No allocation figure is published per district — every rupee below is summed from the works themselves.
The people a district authority actually supervises. Vendor concentration is counted from the payment records: an agency paying almost everything to one vendor is worth a question, not an accusation.
| # | Agency | Works | Completed | Sanctioned | To verify | Avg score | Top vendor |
|---|---|---|---|---|---|---|---|
| 1 | HAZARIBAGH(DEPUTY COMMISSIONER HAZARIBAGH_IDA) | 144 | 4 | ₹6.88 Cr | 0 | 7.3 | RAJ KUMAR SAGAR 100% of spend · 1 vendors |
Whose funds paid for this district’s works.
| Member | Works | Sanctioned | To verify |
|---|---|---|---|
| Manish Jaiswal HAZARIBAGH | 118 | ₹5.90 Cr | 0 |
| Annpurna Devi KODARMA | 26 | ₹98.48 L | 0 |
Sector read from each work’s description.
| Sector | Works | Sanctioned | To verify |
|---|---|---|---|
| Roads & Paving | 75 | ₹3.44 Cr | 0 |
| Community Buildings | 31 | ₹1.56 Cr | 0 |
| Religious & Cultural | 14 | ₹65.99 L | 0 |
| Water | 9 | ₹44.00 L | 0 |
| Drainage & Sanitation | 8 | ₹40.00 L | 0 |
| Boundary & Protection | 4 | ₹20.00 L | 0 |
| Education | 2 | ₹15.00 L | 0 |
| Other | 1 | ₹3.00 L | 0 |
Patterns across an agency’s whole book of work. None of these move any individual work’s score.
Round figures are normal and similar works legitimately cost the same. One figure covering nearly every work is what this looks for, and it means the costing is worth seeing, not that it is wrong.
Ranked by score. Cost is judged against comparable works in this district and sector, so a high cost score means unlike its neighbours — not overpriced.
| Work | Agency | Status | Sanctioned | Delay | Cost vs peers | Score | Band |
|---|---|---|---|---|---|---|---|
| Construction of a shed with a stage at Barkatha Stadium, loc ₹1,000,000 against a ₹500,000 median for Community Buildings works in HAZARIBAGH (100% above, 50 peer works) | HAZARIBAGH(DEPUTY COMMISSIONER HAZARIBAGH_IDA) | Recommended | ₹10.00 L | — | +100% | 27.7 | LOW |
| Construction of stairs in the Ghat located in village Tuio o 119 days beyond expected completion | HAZARIBAGH(DEPUTY COMMISSIONER HAZARIBAGH_IDA) | Recommended | ₹3.00 L | 119 d | -40% | 24.7 | LOW |
| Construction of paver blocks at Pahari Baba in Gaipahadi Pan 119 days beyond expected completion | HAZARIBAGH(DEPUTY COMMISSIONER HAZARIBAGH_IDA) | Recommended | ₹3.00 L | 119 d | -40% | 24.7 | LOW |
| Construction of PCC Roads in Various Villages of Sadar Block 100% similarity with another nearby work | HAZARIBAGH(DEPUTY COMMISSIONER HAZARIBAGH_IDA) | Recommended | ₹5.00 L | — | 0% | 22.9 | LOW |
| Construction of PCC Roads in Various Villages of Sadar Block 100% similarity with another nearby work | HAZARIBAGH(DEPUTY COMMISSIONER HAZARIBAGH_IDA) | Recommended | ₹5.00 L | — | 0% | 22.9 | LOW |
| Construction of PCC Roads in Various Villages of Sadar Block 100% similarity with another nearby work | HAZARIBAGH(DEPUTY COMMISSIONER HAZARIBAGH_IDA) | Recommended | ₹5.00 L | — | 0% | 22.9 | LOW |
| Construction of PCC Roads in Various Villages of Sadar Block 100% similarity with another nearby work | HAZARIBAGH(DEPUTY COMMISSIONER HAZARIBAGH_IDA) | Recommended | ₹5.00 L | — | 0% | 22.9 | LOW |
| Construction of Drain in Village Pauta and Bahari Sadar Bloc 100% similarity with another nearby work | HAZARIBAGH(DEPUTY COMMISSIONER HAZARIBAGH_IDA) | Recommended | ₹5.00 L | — | 0% | 22.9 | LOW |
| Construction of Drain in Village Pauta and Bahari Sadar Bloc 100% similarity with another nearby work | HAZARIBAGH(DEPUTY COMMISSIONER HAZARIBAGH_IDA) | Recommended | ₹5.00 L | — | 0% | 22.9 | LOW |
| Construction of PCC Roads in Various Villages of Keredari Bl 100% similarity with another nearby work | HAZARIBAGH(DEPUTY COMMISSIONER HAZARIBAGH_IDA) | Recommended | ₹5.00 L | — | 0% | 22.9 | LOW |
| Construction of PCC Roads in Various Villages of Keredari Bl 100% similarity with another nearby work | HAZARIBAGH(DEPUTY COMMISSIONER HAZARIBAGH_IDA) | Recommended | ₹5.00 L | — | 0% | 22.9 | LOW |
| Construction of PCC Roads in Various Villages of Keredari Bl 100% similarity with another nearby work | HAZARIBAGH(DEPUTY COMMISSIONER HAZARIBAGH_IDA) | Recommended | ₹5.00 L | — | 0% | 22.9 | LOW |
| Construction of PCC Roads in Various Villages of Keredari Bl 100% similarity with another nearby work | HAZARIBAGH(DEPUTY COMMISSIONER HAZARIBAGH_IDA) | Recommended | ₹5.00 L | — | 0% | 22.9 | LOW |
| Construction of PCC Roads in Various Villages of Keredari Bl 100% similarity with another nearby work | HAZARIBAGH(DEPUTY COMMISSIONER HAZARIBAGH_IDA) | Recommended | ₹5.00 L | — | 0% | 22.9 | LOW |
| Construction of PCC Roads in Various Villages of Keredari Bl 100% similarity with another nearby work | HAZARIBAGH(DEPUTY COMMISSIONER HAZARIBAGH_IDA) | Recommended | ₹5.00 L | — | 0% | 22.9 | LOW |