52 works across 1 implementing agency, recommended by 2 members of parliament. No allocation figure is published per district — every rupee below is summed from the works themselves.
The people a district authority actually supervises. Vendor concentration is counted from the payment records: an agency paying almost everything to one vendor is worth a question, not an accusation.
| # | Agency | Works | Completed | Sanctioned | To verify | Avg score | Top vendor |
|---|---|---|---|---|---|---|---|
| 1 | PALWAL(CEO DRDA MPLADS PALWAL) | 52 | 2 | ₹3.94 Cr | 0 | 17.4 | Mentiz Infratech India 39% of spend · 8 vendors |
Whose funds paid for this district’s works.
| Member | Works | Sanctioned | To verify |
|---|---|---|---|
| Krishan Pal Gurjar FARIDABAD | 51 | ₹3.89 Cr | 0 |
| Subhash Barala Sitting Rajya Sabha | 1 | ₹5.00 L | 0 |
Sector read from each work’s description.
| Sector | Works | Sanctioned | To verify |
|---|---|---|---|
| Roads & Paving | 21 | ₹1.60 Cr | 0 |
| Street Lighting | 14 | ₹64.06 L | 0 |
| Community Buildings | 12 | ₹1.18 Cr | 0 |
| Sports | 2 | ₹20.63 L | 0 |
| Water | 2 | ₹26.59 L | 0 |
| Drainage & Sanitation | 1 | ₹4.90 L | 0 |
Ranked by score. Cost is judged against comparable works in this district and sector, so a high cost score means unlike its neighbours — not overpriced.
| Work | Agency | Status | Sanctioned | Delay | Cost vs peers | Score | Band |
|---|---|---|---|---|---|---|---|
| construction of rasta from PWD Road to Manvir and Manvir to ₹2,000,000 against a ₹602,000 median for Roads & Paving works in PALWAL (232% above, 78 peer works) | PALWAL(CEO DRDA MPLADS PALWAL) | Recommended | ₹20.00 L | — | +232% | 33.6 | LOW |
| Electrification work in Vijaypal Baisla ki Dhani ₹745,000 against a ₹358,872 median for Street Lighting works in PALWAL (108% above, 20 peer works) | PALWAL(CEO DRDA MPLADS PALWAL) | Recommended | ₹7.45 L | — | +108% | 33.6 | LOW |
| Interlocking of tiles from Deshraj Gher to House of Ashok Pe ₹1,800,000 against a ₹602,000 median for Roads & Paving works in PALWAL (199% above, 78 peer works) | PALWAL(CEO DRDA MPLADS PALWAL) | Recommended | ₹18.00 L | — | +199% | 33.6 | LOW |
| Interlocking of tiles from PWD Bamnikhera - Nangal Brahman r ₹2,000,000 against a ₹602,000 median for Roads & Paving works in PALWAL (232% above, 78 peer works) | PALWAL(CEO DRDA MPLADS PALWAL) | Recommended | ₹20.00 L | — | +232% | 33.6 | LOW |
| Providing Domestic Supply to Netrpal Dagar, Keshav Dagar, Dh ₹1,355,577 against a ₹358,872 median for Street Lighting works in PALWAL (278% above, 20 peer works) | PALWAL(CEO DRDA MPLADS PALWAL) | Recommended | ₹13.56 L | — | +278% | 33.6 | LOW |
| interlocking of tiles from house of Charan Member to shamsha ₹1,200,000 against a ₹602,000 median for Roads & Paving works in PALWAL (99% above, 78 peer works) | PALWAL(CEO DRDA MPLADS PALWAL) | Recommended | ₹12.00 L | — | +99% | 33.5 | LOW |
| Construction of additional Hall ₹2,000,000 against a ₹1,003,500 median for Community Buildings works in PALWAL (99% above, 30 peer works) | PALWAL(CEO DRDA MPLADS PALWAL) | Recommended | ₹20.00 L | — | +99% | 33.4 | LOW |
| Construction of hall 100% similarity with another nearby work | PALWAL(CEO DRDA MPLADS PALWAL) | Recommended | ₹11.00 L | — | +10% | 31.8 | LOW |
| Construction of Hall 100% similarity with another nearby work | PALWAL(CEO DRDA MPLADS PALWAL) | Recommended | ₹11.00 L | — | +10% | 31.8 | LOW |
| Electrification work at Bir Singh and Tukki ki Dhani at Vill ₹665,906 against a ₹358,872 median for Street Lighting works in PALWAL (86% above, 20 peer works) | PALWAL(CEO DRDA MPLADS PALWAL) | Recommended | ₹6.66 L | — | +86% | 30.0 | LOW |
| Electrification work in Atohan ki Dhani Village Atohan ₹650,000 against a ₹358,872 median for Street Lighting works in PALWAL (81% above, 20 peer works) | PALWAL(CEO DRDA MPLADS PALWAL) | Recommended | ₹6.50 L | — | +81% | 28.9 | LOW |
| Volleyball Ground, and Development of Public Park 100% similarity with another nearby work | PALWAL(CEO DRDA MPLADS PALWAL) | Recommended | ₹5.00 L | — | 0% | 28.8 | LOW |
| Installation of electricity Transformer under Dhani Scheme S 83 days beyond expected completion | PALWAL(CEO DRDA MPLADS PALWAL) | Recommended | ₹82,472 | 83 d | -77% | 27.1 | LOW |
| Const of IPB Street from Water Supply booster to Bharat Bhus Completed work has no photographic documentation on record | PALWAL(CEO DRDA MPLADS PALWAL) | Completed | ₹20.00 L | — | 0% | 27.0 | LOW |
| Installation of electricity Transformer under Dhani Scheme S 83 days beyond expected completion | PALWAL(CEO DRDA MPLADS PALWAL) | Recommended | ₹1.53 L | 83 d | -57% | 25.6 | LOW |