65 works across 1 implementing agency, recommended by 1 member of parliament. No allocation figure is published per district — every rupee below is summed from the works themselves.
The people a district authority actually supervises. Vendor concentration is counted from the payment records: an agency paying almost everything to one vendor is worth a question, not an accusation.
| # | Agency | Works | Completed | Sanctioned | To verify | Avg score | Top vendor |
|---|---|---|---|---|---|---|---|
| 1 | FARIDABAD(DEPUTY COMMISSIONER FARIDABAD_IDA) | 65 | 51 | ₹3.73 Cr | 3 | 17.9 | G P Kabulpur Patti Parvarish P Fund 8% of spend · 36 vendors |
Whose funds paid for this district’s works.
| Member | Works | Sanctioned | To verify |
|---|---|---|---|
| Krishan Pal Gurjar FARIDABAD | 65 | ₹3.73 Cr | 3 |
Sector read from each work’s description.
| Sector | Works | Sanctioned | To verify |
|---|---|---|---|
| Roads & Paving | 55 | ₹2.93 Cr | 1 |
| Community Buildings | 7 | ₹56.52 L | 1 |
| Drainage & Sanitation | 1 | ₹4.93 L | 0 |
| Street Lighting | 1 | ₹4.66 L | 0 |
| Water | 1 | ₹13.81 L | 1 |
Ranked by score. Cost is judged against comparable works in this district and sector, so a high cost score means unlike its neighbours — not overpriced.
| Work | Agency | Status | Sanctioned | Delay | Cost vs peers | Score | Band |
|---|---|---|---|---|---|---|---|
| 1. Const. of rasta from H/o manoj s/o Bhikam to h/o Manoj s/ ₹900,000 against a ₹474,000 median for Roads & Paving works in FARIDABAD (90% above, 68 peer works) | FARIDABAD(DEPUTY COMMISSIONER FARIDABAD_IDA) | Recommended | ₹9.00 L | 555 d | +90% | 50.2 | MEDIUM |
| Const. of boundary wall of Talab, near bada mandir village B Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range | FARIDABAD(DEPUTY COMMISSIONER FARIDABAD_IDA) | Recommended | ₹13.81 L | 566 d | 0% | 41.9 | MEDIUM |
| KASHMIRI PANDITS WELFARE ASSOCIATION CONSTRUCTION OF HALL Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range | FARIDABAD(DEPUTY COMMISSIONER FARIDABAD_IDA) | Recommended | ₹11.00 L | 555 d | +1% | 40.9 | MEDIUM |
| Const. of rasta from H/o Lala master to h/o billu Village P. 560 days beyond expected completion | FARIDABAD(DEPUTY COMMISSIONER FARIDABAD_IDA) | Recommended | ₹84,000 | 560 d | -82% | 36.6 | LOW |
| Construction of street H/o Dharam to H/o mamraj 555 days beyond expected completion | FARIDABAD(DEPUTY COMMISSIONER FARIDABAD_IDA) | Recommended | ₹4.68 L | 555 d | -1% | 36.1 | LOW |
| Construction of street Peer Baba to Sola Drain 555 days beyond expected completion | FARIDABAD(DEPUTY COMMISSIONER FARIDABAD_IDA) | Recommended | ₹4.93 L | 555 d | 0% | 36.0 | LOW |
| Construction of street H/o Omprakash to H/o Swiming pool 555 days beyond expected completion | FARIDABAD(DEPUTY COMMISSIONER FARIDABAD_IDA) | Recommended | ₹4.92 L | 555 d | +4% | 36.0 | LOW |
| Interlocking of tiles from Sehatpur main road to h/o Neeraj 558 days beyond expected completion | FARIDABAD(DEPUTY COMMISSIONER FARIDABAD_IDA) | Recommended | ₹4.50 L | 558 d | -5% | 35.9 | LOW |
| Repair of Harijan Chaupal, village Alampur 566 days beyond expected completion | FARIDABAD(DEPUTY COMMISSIONER FARIDABAD_IDA) | Recommended | ₹4.73 L | 566 d | -57% | 35.9 | LOW |
| Construction of drain from main road to H/o sanjid 555 days beyond expected completion | FARIDABAD(DEPUTY COMMISSIONER FARIDABAD_IDA) | Recommended | ₹3.79 L | 555 d | -20% | 35.8 | LOW |
| Construction of rasta, Instt. of inter locking tiles Tigaon 566 days beyond expected completion | FARIDABAD(DEPUTY COMMISSIONER FARIDABAD_IDA) | Recommended | ₹4.93 L | 566 d | +4% | 35.7 | LOW |
| Construction of Boundary wall Barat ghar near parjapat Choup 566 days beyond expected completion | FARIDABAD(DEPUTY COMMISSIONER FARIDABAD_IDA) | Recommended | ₹4.99 L | 566 d | -54% | 35.7 | LOW |
| Const. of rasta from Sudesh Firki to Kheda Devat village Moh 555 days beyond expected completion | FARIDABAD(DEPUTY COMMISSIONER FARIDABAD_IDA) | Recommended | ₹1.50 L | 555 d | -68% | 35.5 | LOW |
| Const. of rasta h/o Bedi to h/o Chatar Bhagat Ji, village Am 560 days beyond expected completion | FARIDABAD(DEPUTY COMMISSIONER FARIDABAD_IDA) | Recommended | ₹3.26 L | 560 d | -31% | 35.4 | LOW |
| Construction of interlocking tiles streets Completed work has no photographic documentation on record | FARIDABAD(DEPUTY COMMISSIONER FARIDABAD_IDA) | Completed | ₹10.30 L | — | +117% | 32.2 | LOW |