110 works across 1 implementing agency, recommended by 1 member of parliament. No allocation figure is published per district — every rupee below is summed from the works themselves.
The people a district authority actually supervises. Vendor concentration is counted from the payment records: an agency paying almost everything to one vendor is worth a question, not an accusation.
| # | Agency | Works | Completed | Sanctioned | To verify | Avg score | Top vendor |
|---|---|---|---|---|---|---|---|
| 1 | PORBANDAR(DISTRICT COLLECTOR PORBANDAR_IDA) | 110 | 24 | ₹4.21 Cr | 1 | 11.8 | KUCHADI GRAM PANCHYAT 7% of spend · 34 vendors |
Whose funds paid for this district’s works.
| Member | Works | Sanctioned | To verify |
|---|---|---|---|
| Mansukh Mandaviya PORBANDAR | 110 | ₹4.21 Cr | 1 |
Sector read from each work’s description.
| Sector | Works | Sanctioned | To verify |
|---|---|---|---|
| Roads & Paving | 88 | ₹2.59 Cr | 1 |
| Equipment & Vehicles | 4 | ₹32.50 L | 0 |
| Community Buildings | 3 | ₹12.50 L | 0 |
| Health | 3 | ₹75.00 L | 0 |
| Religious & Cultural | 3 | ₹10.05 L | 0 |
| Education | 3 | ₹11.50 L | 0 |
| Street Lighting | 3 | ₹10.00 L | 0 |
| Water | 1 | ₹2.96 L | 0 |
| Drainage & Sanitation | 1 | ₹5.00 L | 0 |
| Boundary & Protection | 1 | ₹2.50 L | 0 |
Ranked by score. Cost is judged against comparable works in this district and sector, so a high cost score means unlike its neighbours — not overpriced.
| Work | Agency | Status | Sanctioned | Delay | Cost vs peers | Score | Band |
|---|---|---|---|---|---|---|---|
| Causeway Construction work on the way from Simar to Sankhala ₹486,726 against a ₹294,181 median for Roads & Paving works in PORBANDAR (65% above, 111 peer works) | PORBANDAR(DISTRICT COLLECTOR PORBANDAR_IDA) | Recommended | ₹4.87 L | 197 d | +65% | 44.6 | MEDIUM |
| Purchase of with ICU on Will Ambulances Van (Four wheelers) Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range | PORBANDAR(DISTRICT COLLECTOR PORBANDAR_IDA) | Recommended | ₹35.00 L | 121 d | 0% | 36.8 | LOW |
| Paver Block work near to New Chamunda Mataji Temple at Bakha 197 days beyond expected completion | PORBANDAR(DISTRICT COLLECTOR PORBANDAR_IDA) | Recommended | ₹3.91 L | 197 d | +33% | 36.4 | LOW |
| Work on Toilet and shed work at Semar High School in Semar V 197 days beyond expected completion | PORBANDAR(DISTRICT COLLECTOR PORBANDAR_IDA) | Recommended | ₹5.00 L | 197 d | 0% | 35.0 | LOW |
| Paver Block work in the Ground near to Satiai temple at Nagk 197 days beyond expected completion | PORBANDAR(DISTRICT COLLECTOR PORBANDAR_IDA) | Recommended | ₹3.47 L | 197 d | +18% | 35.0 | LOW |
| Construction work of C.C. Road from Raja Veja Kothari house 164 days beyond expected completion | PORBANDAR(DISTRICT COLLECTOR PORBANDAR_IDA) | Recommended | ₹4.00 L | 164 d | +36% | 35.0 | LOW |
| Construction of Playground in High School, VisaVada Village. 197 days beyond expected completion | PORBANDAR(DISTRICT COLLECTOR PORBANDAR_IDA) | Recommended | ₹2.50 L | 197 d | 0% | 34.7 | LOW |
| Purchase of Ambulances Van (Four wheelers) in Ranavav City, Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range | PORBANDAR(DISTRICT COLLECTOR PORBANDAR_IDA) | Recommended | ₹20.00 L | 121 d | 0% | 33.5 | LOW |
| Purchase of ambulances van (Four wheelers) in Kutiyana City, Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range | PORBANDAR(DISTRICT COLLECTOR PORBANDAR_IDA) | Recommended | ₹20.00 L | 121 d | 0% | 33.5 | LOW |
| Providing for public Drainage-Pipe work for drainage of rain 164 days beyond expected completion | PORBANDAR(DISTRICT COLLECTOR PORBANDAR_IDA) | Recommended | ₹2.96 L | 164 d | 0% | 32.1 | LOW |
| Construction work of C.C. Road on the road connecting Mandva 164 days beyond expected completion | PORBANDAR(DISTRICT COLLECTOR PORBANDAR_IDA) | Recommended | ₹2.96 L | 164 d | +1% | 32.1 | LOW |
| Construction of C.C. Road work from Gala Sarman house to Das 164 days beyond expected completion | PORBANDAR(DISTRICT COLLECTOR PORBANDAR_IDA) | Recommended | ₹3.00 L | 164 d | +2% | 32.1 | LOW |
| Construction of a Paver Block road from Balu Lakha house to 164 days beyond expected completion | PORBANDAR(DISTRICT COLLECTOR PORBANDAR_IDA) | Recommended | ₹3.00 L | 164 d | +2% | 32.1 | LOW |
| Construction of C.C. Road work from Panchayat office to Bhar 164 days beyond expected completion | PORBANDAR(DISTRICT COLLECTOR PORBANDAR_IDA) | Recommended | ₹2.46 L | 164 d | -16% | 31.9 | LOW |
| Paver block work from Bhima Vajshi Kandoria house to Ghanti 164 days beyond expected completion | PORBANDAR(DISTRICT COLLECTOR PORBANDAR_IDA) | Recommended | ₹2.47 L | 164 d | -16% | 31.9 | LOW |