Kasauti can only be opened on a desktop or laptop.

Open this link on a larger screen to see the verification queue.

← Back to works

Construction of Playground in High School, VisaVada Village.

Education

Gujarat / PORBANDAR — PORBANDAR(DISTRICT COLLECTOR PORBANDAR_IDA) · Mansukh Mandaviya (PORBANDAR)

Overall risk score
35/100
Blended from the five components below, each weighted as shown.
LOW

Risk components

Cost26
Delay100
Duplication0
Agency21
Compliance0
Sanctioned
₹2.50 L
Delay
197d
Cost deviation
—
Fewer than 8 comparable works in this district and sector
Work status
Recommended

AI powered · gemini-flash-liteWhy was this flagged?

  • 197 days beyond expected completionPublished dates

Decision trail

Nobody has recorded a decision on this work yet.