Open this link on a larger screen to see the verification queue.
181 works across 1 implementing agency, recommended by 2 members of parliament. No allocation figure is published per district — every rupee below is summed from the works themselves.
The people a district authority actually supervises. Vendor concentration is counted from the payment records: an agency paying almost everything to one vendor is worth a question, not an accusation.
| # | Agency | Works | Completed | Sanctioned | To verify | Avg score | Top vendor |
|---|---|---|---|---|---|---|---|
| 1 | KORBA(Collector-Korba) | 181 | 79 | ₹6.54 Cr | 23 | 22.0 | MUKHYA KARYAPALAN ADHIKARI JANPAD PANCHAYAT PONDI UPRODA 6% of spend · 118 vendors |
Whose funds paid for this district’s works.
| Member | Works | Sanctioned | To verify |
|---|---|---|---|
| Jyotsna Charandas Mahant KORBA | 179 | ₹6.29 Cr | 21 |
| Laxmi Verma Sitting Rajya Sabha | 2 | ₹25.00 L | 2 |
Sector read from each work’s description.
| Sector | Works | Sanctioned | To verify |
|---|---|---|---|
| Religious & Cultural | 71 | ₹2.24 Cr | 14 |
| Water | 36 | ₹91.28 L | 4 |
| Community Buildings | 32 | ₹1.43 Cr | 0 |
| Roads & Paving | 24 | ₹1.26 Cr | 2 |
| Education | 10 | ₹40.00 L | 3 |
| Boundary & Protection | 5 | ₹17.99 L | 0 |
| Drainage & Sanitation | 2 | ₹4.00 L | 0 |
| Health | 1 | ₹7.50 L | 0 |
Ranked by score. Cost is judged against comparable works in this district and sector, so a high cost score means unlike its neighbours — not overpriced.
| Work | Agency | Status | Sanctioned | Delay | Cost vs peers | Score | Band |
|---|---|---|---|---|---|---|---|
| Construction of Mahila Bhawan at Batra, in School Ground.
Gr ₹600,000 against a ₹300,000 median for Education works in KORBA (100% above, 16 peer works) | KORBA(Collector-Korba) | Recommended | ₹6.00 L | 361 d | +100% | 54.4 | MEDIUM |
| Embankment construction work on the Korvapara access road. ₹1,500,000 against a ₹499,982 median for Roads & Paving works in KORBA (200% above, 46 peer works) | KORBA(Collector-Korba) | Recommended | ₹15.00 L | — | +200% | 49.4 | MEDIUM |
| CC Road Construction Work: From Vinay's House towards Tikrip ₹1,000,000 against a ₹499,982 median for Roads & Paving works in KORBA (100% above, 46 peer works) | KORBA(Collector-Korba) | Recommended | ₹10.00 L | — | +100% | 49.4 | MEDIUM |
| Construction of Chhatdaar Manch in Gram Panchayat - Kachhar, 361 days beyond expected completion | KORBA(Collector-Korba) | Recommended | ₹4.00 L | 361 d | +33% | 49.2 | MEDIUM |
| Manch construction at Gram Panchayat - Lalpur , Vikas Khand 281 days beyond expected completion | KORBA(Collector-Korba) | Recommended | ₹4.00 L | 281 d | +33% | 47.4 | MEDIUM |
| Manch Construction at Gram Panchayat - Lepra, Vikas Khand - 269 days beyond expected completion | KORBA(Collector-Korba) | Recommended | ₹3.00 L | 269 d | 0% | 46.8 | MEDIUM |
| Construction of Manch at Yadav Mohalla in Ashrit Gram - Koda ₹500,000 against a ₹300,000 median for Religious & Cultural works in KORBA (67% above, 85 peer works) | KORBA(Collector-Korba) | Recommended | ₹5.00 L | 268 d | +67% | 46.0 | MEDIUM |
| Sarvajanik Manch construction at Gram Panchayat - Kesla, Vik ₹500,000 against a ₹300,000 median for Religious & Cultural works in KORBA (67% above, 85 peer works) | KORBA(Collector-Korba) | Recommended | ₹5.00 L | 275 d | +67% | 46.0 | MEDIUM |
| Ahata construction at school in Kuteshwar Nagoi, Vikas khand ₹500,000 against a ₹300,000 median for Education works in KORBA (67% above, 16 peer works) | KORBA(Collector-Korba) | Recommended | ₹5.00 L | 278 d | +67% | 46.0 | MEDIUM |
| Mukti Dham construction in Village - Iraf, Vikas khand - Pal ₹500,000 against a ₹300,000 median for Religious & Cultural works in KORBA (67% above, 85 peer works) | KORBA(Collector-Korba) | Recommended | ₹5.00 L | 305 d | +67% | 46.0 | MEDIUM |
| Manch Construction. 117 days beyond expected completion | KORBA(Collector-Korba) | Recommended | ₹2.50 L | 117 d | -17% | 45.6 | MEDIUM |
| Manch Construction. 117 days beyond expected completion | KORBA(Collector-Korba) | Recommended | ₹2.50 L | 117 d | -17% | 45.6 | MEDIUM |
| Manch Construction. 117 days beyond expected completion | KORBA(Collector-Korba) | Recommended | ₹2.50 L | 117 d | -17% | 45.6 | MEDIUM |
| Manch Construction. 117 days beyond expected completion | KORBA(Collector-Korba) | Recommended | ₹2.50 L | 117 d | -17% | 45.6 | MEDIUM |
| Manch construction 117 days beyond expected completion | KORBA(Collector-Korba) | Recommended | ₹2.50 L | 117 d | -17% | 45.6 | MEDIUM |