83 works across 1 implementing agency, recommended by 2 members of parliament. No allocation figure is published per district — every rupee below is summed from the works themselves.
The people a district authority actually supervises. Vendor concentration is counted from the payment records: an agency paying almost everything to one vendor is worth a question, not an accusation.
| # | Agency | Works | Completed | Sanctioned | To verify | Avg score | Top vendor |
|---|---|---|---|---|---|---|---|
| 1 | KORBA(Collector-Korba) | 83 | 70 | ₹4.07 Cr | 6 | 15.5 | GRAM PANCHAYAT MADAN 6% of spend · 73 vendors |
Whose funds paid for this district’s works.
| Member | Works | Sanctioned | To verify |
|---|---|---|---|
| Jyotsna Charandas Mahant KORBA | 81 | ₹3.82 Cr | 4 |
| Laxmi Verma Sitting Rajya Sabha | 2 | ₹25.00 L | 2 |
Sector read from each work’s description.
| Sector | Works | Sanctioned | To verify |
|---|---|---|---|
| Community Buildings | 28 | ₹1.60 Cr | 3 |
| Roads & Paving | 22 | ₹1.11 Cr | 2 |
| Religious & Cultural | 14 | ₹37.96 L | 0 |
| Boundary & Protection | 8 | ₹47.44 L | 0 |
| Education | 6 | ₹28.50 L | 1 |
| Water | 4 | ₹15.49 L | 0 |
| Drainage & Sanitation | 1 | ₹7.01 L | 0 |
Ranked by score. Cost is judged against comparable works in this district and sector, so a high cost score means unlike its neighbours — not overpriced.
| Work | Agency | Status | Sanctioned | Delay | Cost vs peers | Score | Band |
|---|---|---|---|---|---|---|---|
| Renovation of Rainbasera Near BDM Medical College. ₹750,000 against a ₹300,000 median for Education works in KORBA (150% above, 16 peer works) | KORBA(Collector-Korba) | Recommended | ₹7.50 L | 609 d | +150% | 54.4 | MEDIUM |
| Bathroom and Rest Area ₹750,000 against a ₹400,000 median for Community Buildings works in KORBA (88% above, 60 peer works) | KORBA(Collector-Korba) | Recommended | ₹7.50 L | 609 d | +88% | 51.3 | MEDIUM |
| Mangal Bhawan construction near Van Patta Khasra No. 235 Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range | KORBA(Collector-Korba) | Recommended | ₹5.00 L | 724 d | +25% | 50.6 | MEDIUM |
| Embankment construction work on the Korvapara access road. ₹1,500,000 against a ₹499,982 median for Roads & Paving works in KORBA (200% above, 46 peer works) | KORBA(Collector-Korba) | Recommended | ₹15.00 L | — | +200% | 49.4 | MEDIUM |
| CC Road Construction Work: From Vinay's House towards Tikrip ₹1,000,000 against a ₹499,982 median for Roads & Paving works in KORBA (100% above, 46 peer works) | KORBA(Collector-Korba) | Recommended | ₹10.00 L | — | +100% | 49.4 | MEDIUM |
| Mangal Bhawan construction Purani Basti, Rajgamar Chowk Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range | KORBA(Collector-Korba) | Recommended | ₹5.00 L | 723 d | +25% | 40.1 | MEDIUM |
| Renovation of existing Manch at Village Vimalta in Block Kor Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range | KORBA(Collector-Korba) | Recommended | ₹1.00 L | 706 d | -67% | 39.5 | LOW |
| Construction of Cultural Stage near Vidhvasini Temple in vil 724 days beyond expected completion | KORBA(Collector-Korba) | Recommended | ₹2.50 L | 724 d | -17% | 39.3 | LOW |
| Construction of Kitchen shed near Mazaar 706 days beyond expected completion | KORBA(Collector-Korba) | Recommended | ₹5.00 L | 706 d | +25% | 39.2 | LOW |
| Construction of shed in Chhinkonha 707 days beyond expected completion | KORBA(Collector-Korba) | Recommended | ₹3.00 L | 707 d | -25% | 38.5 | LOW |
| Construction of Shed near Dussehra Maidan, High school 707 days beyond expected completion | KORBA(Collector-Korba) | Recommended | ₹3.00 L | 707 d | 0% | 38.5 | LOW |
| Construction of chabutra at Middle School Kendai. 703 days beyond expected completion | KORBA(Collector-Korba) | Recommended | ₹3.00 L | 703 d | 0% | 38.2 | LOW |
| Shed construction at Laharapara Muktidhaam 610 days beyond expected completion | KORBA(Collector-Korba) | Recommended | ₹4.00 L | 610 d | 0% | 37.1 | LOW |
| 10,00,000? (10 Lakh Rupees) for Community Centre in Makundpu ₹1,000,000 against a ₹400,000 median for Community Buildings works in KORBA (150% above, 60 peer works) | KORBA(Collector-Korba) | Completed | ₹10.00 L | — | +150% | 29.4 | LOW |
| Construction of Bhawan, Near Kabir Ashram ₹1,899,847 against a ₹400,000 median for Community Buildings works in KORBA (375% above, 60 peer works) | KORBA(Collector-Korba) | Completed | ₹19.00 L | — | +375% | 29.4 | LOW |