Open this link on a larger screen to see the verification queue.
77 works across 1 implementing agency, recommended by 2 members of parliament. No allocation figure is published per district — every rupee below is summed from the works themselves.
The people a district authority actually supervises. Vendor concentration is counted from the payment records: an agency paying almost everything to one vendor is worth a question, not an accusation.
| # | Agency | Works | Completed | Sanctioned | To verify | Avg score | Top vendor |
|---|---|---|---|---|---|---|---|
| 1 | KATIHAR(DISTRICT PLANNING OFFICER KATIHAR_IDA) | 77 | 76 | ₹6.29 Cr | 1 | 15.5 | R K Construction 55% of spend · 10 vendors |
Whose funds paid for this district’s works.
| Member | Works | Sanctioned | To verify |
|---|---|---|---|
| Dulal Chandra Goswami KATIHAR | 59 | ₹4.77 Cr | 1 |
| Santosh Kumar PURNEA | 18 | ₹1.52 Cr | 0 |
Sector read from each work’s description.
| Sector | Works | Sanctioned | To verify |
|---|---|---|---|
| Street Lighting | 38 | ₹3.28 Cr | 0 |
| Roads & Paving | 24 | ₹1.73 Cr | 1 |
| Community Buildings | 8 | ₹78.81 L | 0 |
| Religious & Cultural | 6 | ₹46.33 L | 0 |
| Education | 1 | ₹2.73 L | 0 |
Patterns across an agency’s whole book of work. None of these move any individual work’s score.
Round figures are normal and similar works legitimately cost the same. One figure covering nearly every work is what this looks for, and it means the costing is worth seeing, not that it is wrong.
Ranked by score. Cost is judged against comparable works in this district and sector, so a high cost score means unlike its neighbours — not overpriced.
| Work | Agency | Status | Sanctioned | Delay | Cost vs peers | Score | Band |
|---|---|---|---|---|---|---|---|
| Construction of Pebher Block and Drain road from Jhameli Dev 580 days beyond expected completion | KATIHAR(DISTRICT PLANNING OFFICER KATIHAR_IDA) | Recommended | ₹5.00 L | 580 d | -31% | 40.5 | MEDIUM |
| 16 meter Highmast LED (150x8) light, Korha Prakhand antargat Completed work has no photographic documentation on record | KATIHAR(DISTRICT PLANNING OFFICER KATIHAR_IDA) | Completed | ₹8.64 L | — | -10% | 32.0 | LOW |
| 16 meter Highmast LED (150x8) light, Korha prakhand antargat 99% similarity with another nearby work | KATIHAR(DISTRICT PLANNING OFFICER KATIHAR_IDA) | Completed | ₹8.64 L | — | -10% | 29.0 | LOW |
| 16 meter Highmast LED (150x8) light, Korha Prakhand antargat 99% similarity with another nearby work | KATIHAR(DISTRICT PLANNING OFFICER KATIHAR_IDA) | Completed | ₹8.64 L | — | -10% | 29.0 | LOW |
| Modernization and beautification work of the building of Tow ₹1,499,750 against a ₹867,826 median for Community Buildings works in KATIHAR (73% above, 8 peer works) | KATIHAR(DISTRICT PLANNING OFFICER KATIHAR_IDA) | Completed | ₹15.00 L | — | +73% | 25.7 | LOW |
| Construction work of hall on the upper floor of the southern ₹1,499,384 against a ₹867,826 median for Community Buildings works in KATIHAR (73% above, 8 peer works) | KATIHAR(DISTRICT PLANNING OFFICER KATIHAR_IDA) | Completed | ₹14.99 L | — | +73% | 25.7 | LOW |
| Construction work of PCC road from Hardev Mandal's house in ₹1,243,654 against a ₹722,937 median for Roads & Paving works in KATIHAR (72% above, 25 peer works) | KATIHAR(DISTRICT PLANNING OFFICER KATIHAR_IDA) | Completed | ₹12.44 L | — | +72% | 25.5 | LOW |
| 16 meter Highmast LED (150x8) light, Falka Prakhand antargat 97% similarity with another nearby work | KATIHAR(DISTRICT PLANNING OFFICER KATIHAR_IDA) | Completed | ₹8.64 L | — | -10% | 24.9 | LOW |
| 16 meter Highmast LED (150x8) light, Falka Prakhand antargat 97% similarity with another nearby work | KATIHAR(DISTRICT PLANNING OFFICER KATIHAR_IDA) | Completed | ₹8.64 L | — | -10% | 24.9 | LOW |
| Korha Prakhand antargat dakshini Simariya Panchayat Nakkipur ₹1,207,038 against a ₹722,937 median for Roads & Paving works in KATIHAR (67% above, 25 peer works) | KATIHAR(DISTRICT PLANNING OFFICER KATIHAR_IDA) | Completed | ₹12.07 L | — | +67% | 24.3 | LOW |
| Construction work of PCC road from National Highway-31 Kurse ₹1,165,261 against a ₹722,937 median for Roads & Paving works in KATIHAR (61% above, 25 peer works) | KATIHAR(DISTRICT PLANNING OFFICER KATIHAR_IDA) | Completed | ₹11.65 L | — | +61% | 22.8 | LOW |
| Construction of Samudaik Bhawan at near of Durga Mandir Camp ₹1,390,545 against a ₹867,826 median for Community Buildings works in KATIHAR (60% above, 8 peer works) | KATIHAR(DISTRICT PLANNING OFFICER KATIHAR_IDA) | Completed | ₹13.91 L | — | +60% | 22.6 | LOW |
| Work of installation of one high-mast light near Malharia Pa 55% of this agency's ₹62,387,452 spend went to one vendor (R K Construction), across 10 vendors and 77 transactions | KATIHAR(DISTRICT PLANNING OFFICER KATIHAR_IDA) | Completed | ₹8.64 L | — | -10% | 19.9 | LOW |
| Work of installation of one high-mast light near Chhohar Pan 55% of this agency's ₹62,387,452 spend went to one vendor (R K Construction), across 10 vendors and 77 transactions | KATIHAR(DISTRICT PLANNING OFFICER KATIHAR_IDA) | Completed | ₹8.64 L | — | -10% | 19.9 | LOW |
| Construction work of PCC road from Muradpur main road to Man ₹1,066,405 against a ₹722,937 median for Roads & Paving works in KATIHAR (48% above, 25 peer works) | KATIHAR(DISTRICT PLANNING OFFICER KATIHAR_IDA) | Completed | ₹10.66 L | — | +48% | 19.4 | LOW |