122 works across 1 implementing agency, recommended by 4 members of parliament. No allocation figure is published per district — every rupee below is summed from the works themselves.
The people a district authority actually supervises. Vendor concentration is counted from the payment records: an agency paying almost everything to one vendor is worth a question, not an accusation.
| # | Agency | Works | Completed | Sanctioned | To verify | Avg score | Top vendor |
|---|---|---|---|---|---|---|---|
| 1 | UDALGURI(DEPUTY COMMISSIONER Udalguri_IDA) 2 high risk | 122 | 33 | ₹3.43 Cr | 5 | 31.0 | Lucky Enterprise 18% of spend · 39 vendors |
Whose funds paid for this district’s works.
| Member | Works | Sanctioned | To verify |
|---|---|---|---|
| Dilip Saikia Darrang-Udalguri | 115 | ₹2.89 Cr | 2 |
| Rwngwra Narzary Sitting Rajya Sabha | 4 | ₹40.00 L | 3 |
| Pramod Boro Sitting Rajya Sabha | 2 | ₹8.00 L | 0 |
| Birendra Prasad Baishya Sitting Rajya Sabha | 1 | ₹6.00 L | 0 |
Sector read from each work’s description.
| Sector | Works | Sanctioned | To verify |
|---|---|---|---|
| Community Buildings | 51 | ₹1.32 Cr | 0 |
| Religious & Cultural | 40 | ₹1.06 Cr | 2 |
| Education | 11 | ₹32.00 L | 1 |
| Boundary & Protection | 10 | ₹26.00 L | 0 |
| Roads & Paving | 7 | ₹41.50 L | 2 |
| Drainage & Sanitation | 3 | ₹6.50 L | 0 |
Patterns across an agency’s whole book of work. None of these move any individual work’s score.
Round figures are normal and similar works legitimately cost the same. One figure covering nearly every work is what this looks for, and it means the costing is worth seeing, not that it is wrong.
The whole population fails the textbook test — the median agency scores 6.2 where Nigrini calls 1.5 nonconformant — because MPLADS amounts are capped, rounded and repeated by design. This ranks agencies against each other, not against the law. It is the weakest signal here and is never evidence on its own.
Ranked by score. Cost is judged against comparable works in this district and sector, so a high cost score means unlike its neighbours — not overpriced.
| Work | Agency | Status | Sanctioned | Delay | Cost vs peers | Score | Band |
|---|---|---|---|---|---|---|---|
| construction of RCC Box culvert at Dhupguri village approach ₹1,000,000 against a ₹500,000 median for Roads & Paving works in UDALGURI (100% above, 14 peer works) | UDALGURI(DEPUTY COMMISSIONER Udalguri_IDA) | Recommended | ₹10.00 L | 451 d | +100% | 75.6 | HIGH |
| Construction of Harimu Jousang at Swrang Hadang( Mahaliapara ₹1,500,000 against a ₹300,000 median for Religious & Cultural works in UDALGURI (400% above, 86 peer works) | UDALGURI(DEPUTY COMMISSIONER Udalguri_IDA) | Recommended | ₹15.00 L | 451 d | +400% | 75.6 | HIGH |
| construction of Culvert at connecting road Bholabari to FCI ₹1,000,000 against a ₹500,000 median for Roads & Paving works in UDALGURI (100% above, 14 peer works) | UDALGURI(DEPUTY COMMISSIONER Udalguri_IDA) | Recommended | ₹10.00 L | — | +100% | 50.6 | MEDIUM |
| Construction of Additional Class Room at Jhargaon Shankardev ₹500,000 against a ₹300,000 median for Education works in UDALGURI (67% above, 14 peer works) | UDALGURI(DEPUTY COMMISSIONER Udalguri_IDA) | Recommended | ₹5.00 L | 681 d | +67% | 47.3 | MEDIUM |
| Construction of Boundary Wall near Brahma Mandir at No. 1 Bh 612 days beyond expected completion | UDALGURI(DEPUTY COMMISSIONER Udalguri_IDA) | Recommended | ₹2.00 L | 612 d | -33% | 41.5 | MEDIUM |
| Construction/Renovation of Additional Class Room at Mazbat H 676 days beyond expected completion | UDALGURI(DEPUTY COMMISSIONER Udalguri_IDA) | Recommended | ₹4.00 L | 676 d | +33% | 39.9 | LOW |
| Construction/Renovation of Additional Class Room at Shankard 677 days beyond expected completion | UDALGURI(DEPUTY COMMISSIONER Udalguri_IDA) | Recommended | ₹4.00 L | 677 d | +33% | 39.9 | LOW |
| Renovation of office of All Assam Bhojpuri Yuva Chatra Paris 680 days beyond expected completion | UDALGURI(DEPUTY COMMISSIONER Udalguri_IDA) | Recommended | ₹1.50 L | 680 d | -50% | 39.9 | LOW |
| Construction of Ranga Mancha at Sengapathar 680 days beyond expected completion | UDALGURI(DEPUTY COMMISSIONER Udalguri_IDA) | Recommended | ₹2.00 L | 680 d | -33% | 39.5 | LOW |
| Construction/Repairing of Community Hall of Jhargaon Dakshin 681 days beyond expected completion | UDALGURI(DEPUTY COMMISSIONER Udalguri_IDA) | Recommended | ₹2.00 L | 681 d | -33% | 39.5 | LOW |
| Construction/Repairing of Community Hall of Kalaigaon Gerua 681 days beyond expected completion | UDALGURI(DEPUTY COMMISSIONER Udalguri_IDA) | Recommended | ₹2.00 L | 681 d | -33% | 39.5 | LOW |
| Construction/Repairing of community hall of 2 No. Batabariga 681 days beyond expected completion | UDALGURI(DEPUTY COMMISSIONER Udalguri_IDA) | Recommended | ₹2.00 L | 681 d | -33% | 39.5 | LOW |
| Construction/Renovation of Cultural stage near Harisinga Ras 676 days beyond expected completion | UDALGURI(DEPUTY COMMISSIONER Udalguri_IDA) | Recommended | ₹2.00 L | 676 d | -33% | 39.4 | LOW |
| Construction/renovation of Community hall near Gobindabari M 676 days beyond expected completion | UDALGURI(DEPUTY COMMISSIONER Udalguri_IDA) | Recommended | ₹2.00 L | 676 d | -33% | 39.4 | LOW |
| Renovation of Boundary Wall near No. 1 Kalaigaon Sanatan Man 677 days beyond expected completion | UDALGURI(DEPUTY COMMISSIONER Udalguri_IDA) | Recommended | ₹2.00 L | 677 d | -33% | 39.4 | LOW |