71 works across 1 implementing agency, recommended by 4 members of parliament. No allocation figure is published per district — every rupee below is summed from the works themselves.
The people a district authority actually supervises. Vendor concentration is counted from the payment records: an agency paying almost everything to one vendor is worth a question, not an accusation.
| # | Agency | Works | Completed | Sanctioned | To verify | Avg score | Top vendor |
|---|---|---|---|---|---|---|---|
| 1 | SONITPUR(Deputy Commissioner Sonitpur, Tezpur) 1 high risk | 71 | 37 | ₹4.52 Cr | 39 | 36.5 | MAHAMAYA CONSTRUCTION 77% of spend · 6 vendors |
Whose funds paid for this district’s works.
| Member | Works | Sanctioned | To verify |
|---|---|---|---|
| Pallab Lochan Das Sonitpur | 68 | ₹3.77 Cr | 36 |
| Pabitra Margherita Sitting Rajya Sabha | 1 | ₹45.00 L | 1 |
| Rwngwra Narzary Sitting Rajya Sabha | 1 | ₹19.99 L | 1 |
| Birendra Prasad Baishya Sitting Rajya Sabha | 1 | ₹9.95 L | 1 |
Sector read from each work’s description.
| Sector | Works | Sanctioned | To verify |
|---|---|---|---|
| Community Buildings | 37 | ₹2.10 Cr | 22 |
| Religious & Cultural | 24 | ₹1.17 Cr | 12 |
| Education | 6 | ₹44.99 L | 3 |
| Roads & Paving | 2 | ₹50.00 L | 1 |
| Boundary & Protection | 1 | ₹5.00 L | 0 |
| Equipment & Vehicles | 1 | ₹25.00 L | 1 |
Patterns across an agency’s whole book of work. None of these move any individual work’s score.
An agency whose sanctions all arrive in the last quarter looks identical. This is a spending pattern, not a finding.
Ranked by score. Cost is judged against comparable works in this district and sector, so a high cost score means unlike its neighbours — not overpriced.
| Work | Agency | Status | Sanctioned | Delay | Cost vs peers | Score | Band |
|---|---|---|---|---|---|---|---|
| Construction of protective sheds for preservation of Bhomora Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range | SONITPUR(Deputy Commissioner Sonitpur, Tezpur) | Recommended | ₹45.00 L | 231 d | 0% | 78.8 | HIGH |
| Construction of C/Hall in Seva Bharati, Missamari ₹1,000,000 against a ₹500,000 median for Community Buildings works in SONITPUR (100% above, 73 peer works) | SONITPUR(Deputy Commissioner Sonitpur, Tezpur) | Recommended | ₹10.00 L | 594 d | +100% | 65.0 | MEDIUM |
| Const of C/Hall at ACMS Tezpur Branch, Ward No 7 ₹1,000,000 against a ₹500,000 median for Community Buildings works in SONITPUR (100% above, 73 peer works) | SONITPUR(Deputy Commissioner Sonitpur, Tezpur) | Recommended | ₹10.00 L | 597 d | +100% | 65.0 | MEDIUM |
| Construction of additional class room at Batachipur Milon Bo ₹1,999,059 against a ₹500,000 median for Education works in SONITPUR (300% above, 13 peer works) | SONITPUR(Deputy Commissioner Sonitpur, Tezpur) | Completed | ₹19.99 L | — | +300% | 60.0 | MEDIUM |
| Construction of Community Hall Near Mahabhairab Temple ₹995,373 against a ₹500,000 median for Community Buildings works in SONITPUR (99% above, 73 peer works) | SONITPUR(Deputy Commissioner Sonitpur, Tezpur) | Completed | ₹9.95 L | — | +99% | 59.8 | MEDIUM |
| Elevator facility for Divyang and Elderly Citizens at DC Off Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range | SONITPUR(Deputy Commissioner Sonitpur, Tezpur) | Recommended | ₹25.00 L | 574 d | 0% | 57.6 | MEDIUM |
| Construction of C/Hall near Kali Mandir (Cremation Ground) , 546 days beyond expected completion | SONITPUR(Deputy Commissioner Sonitpur, Tezpur) | Recommended | ₹5.00 L | 546 d | 0% | 48.5 | MEDIUM |
| Const of C/Hall near Radha Krishna Mandir, 2 No Bagipukhuri 546 days beyond expected completion | SONITPUR(Deputy Commissioner Sonitpur, Tezpur) | Recommended | ₹5.00 L | 546 d | 0% | 48.5 | MEDIUM |
| Development of Kenduguri Bura Dangoria Than 581 days beyond expected completion | SONITPUR(Deputy Commissioner Sonitpur, Tezpur) | Recommended | ₹5.00 L | 581 d | 0% | 47.9 | MEDIUM |
| Construction of Staircase at Jugalani Chhat Ghat 581 days beyond expected completion | SONITPUR(Deputy Commissioner Sonitpur, Tezpur) | Recommended | ₹5.00 L | 581 d | 0% | 47.9 | MEDIUM |
| Development of Gejangaguri Namghar, Lakhi Mandir, Mijibari, 581 days beyond expected completion | SONITPUR(Deputy Commissioner Sonitpur, Tezpur) | Recommended | ₹5.00 L | 581 d | 0% | 47.9 | MEDIUM |
| Const. of C/Hall at near Dibrudarrang TE Kali Mandir, Dibrud 595 days beyond expected completion | SONITPUR(Deputy Commissioner Sonitpur, Tezpur) | Recommended | ₹5.00 L | 595 d | 0% | 47.9 | MEDIUM |
| Const. of C/Hall near Durga Puja Mandap, Narayanpur TE 595 days beyond expected completion | SONITPUR(Deputy Commissioner Sonitpur, Tezpur) | Recommended | ₹5.00 L | 595 d | 0% | 47.9 | MEDIUM |
| Const. of C/Hall at Sankardev Sishu Niketan, Dhekiajuli, War 595 days beyond expected completion | SONITPUR(Deputy Commissioner Sonitpur, Tezpur) | Recommended | ₹5.00 L | 595 d | 0% | 47.9 | MEDIUM |
| Construction of Boundary Wall near Moila Ali Laxmi Nrayan Ma 595 days beyond expected completion | SONITPUR(Deputy Commissioner Sonitpur, Tezpur) | Recommended | ₹5.00 L | 595 d | 0% | 47.9 | MEDIUM |