27 works across 1 implementing agency, recommended by 5 members of parliament. No allocation figure is published per district — every rupee below is summed from the works themselves.
The people a district authority actually supervises. Vendor concentration is counted from the payment records: an agency paying almost everything to one vendor is worth a question, not an accusation.
| # | Agency | Works | Completed | Sanctioned | To verify | Avg score | Top vendor |
|---|---|---|---|---|---|---|---|
| 1 | NALBARI(DEPUTY COMMISSIONER NALBARI_IDA) 2 high risk | 27 | 10 | ₹2.92 Cr | 9 | 33.3 | Friendship Enterprise 29% of spend · 24 vendors |
Whose funds paid for this district’s works.
| Member | Works | Sanctioned | To verify |
|---|---|---|---|
| Dilip Saikia Darrang-Udalguri | 10 | ₹25.50 L | 0 |
| Abdul Khaleque BARPETA | 8 | ₹31.00 L | 3 |
| Birendra Prasad Baishya Sitting Rajya Sabha | 4 | ₹1.00 Cr | 3 |
| Rwngwra Narzary Sitting Rajya Sabha | 3 | ₹35.00 L | 1 |
| Pabitra Margherita Sitting Rajya Sabha | 2 | ₹1.00 Cr | 2 |
Sector read from each work’s description.
| Sector | Works | Sanctioned | To verify |
|---|---|---|---|
| Community Buildings | 11 | ₹1.12 Cr | 5 |
| Religious & Cultural | 5 | ₹12.00 L | 1 |
| Boundary & Protection | 4 | ₹64.50 L | 1 |
| Roads & Paving | 4 | ₹63.50 L | 2 |
| Street Lighting | 2 | ₹35.00 L | 0 |
| Sports | 1 | ₹5.00 L | 0 |
Ranked by score. Cost is judged against comparable works in this district and sector, so a high cost score means unlike its neighbours — not overpriced.
| Work | Agency | Status | Sanctioned | Delay | Cost vs peers | Score | Band |
|---|---|---|---|---|---|---|---|
| Construction of District Fencing Academy at Ward No. 4 & 7, ₹5,000,000 against a ₹700,000 median for Boundary & Protection works in NALBARI (614% above, 9 peer works) | NALBARI(DEPUTY COMMISSIONER NALBARI_IDA) | Recommended | ₹50.00 L | 276 d | +614% | 75.6 | HIGH |
| Construction of Sabhagriha at Hatorbari, Bardhanara, Ghograp ₹5,000,000 against a ₹600,000 median for Community Buildings works in NALBARI (733% above, 19 peer works) | NALBARI(DEPUTY COMMISSIONER NALBARI_IDA) | Recommended | ₹50.00 L | 175 d | +733% | 74.9 | HIGH |
| Construction of Cultural Bhawan Near Thetha Gohain Than at D ₹2,500,000 against a ₹600,000 median for Community Buildings works in NALBARI (317% above, 19 peer works) | NALBARI(DEPUTY COMMISSIONER NALBARI_IDA) | Recommended | ₹25.00 L | — | +317% | 50.6 | MEDIUM |
| Improvement of ICBP road Hajo Nalbari Road Utsab Khettra to ₹3,500,000 against a ₹600,000 median for Roads & Paving works in NALBARI (483% above, 9 peer works) | NALBARI(DEPUTY COMMISSIONER NALBARI_IDA) | Recommended | ₹35.00 L | — | +483% | 50.6 | MEDIUM |
| Construction and renovation of Bagals road Naboclay Sangha u ₹2,000,000 against a ₹600,000 median for Roads & Paving works in NALBARI (233% above, 9 peer works) | NALBARI(DEPUTY COMMISSIONER NALBARI_IDA) | Completed | ₹20.00 L | — | +233% | 50.6 | MEDIUM |
| Construction of Guest House at BBSB Milan Idgah Maidan Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range | NALBARI(DEPUTY COMMISSIONER NALBARI_IDA) | Recommended | ₹5.00 L | 794 d | -17% | 43.4 | MEDIUM |
| Belsor Anchalik Krira Sangha Building Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range | NALBARI(DEPUTY COMMISSIONER NALBARI_IDA) | Recommended | ₹5.00 L | 794 d | -17% | 43.4 | MEDIUM |
| Construction of Commnuty Hall Near Shree Shree Manaprabhu Ba ₹1,000,000 against a ₹600,000 median for Community Buildings works in NALBARI (67% above, 19 peer works) | NALBARI(DEPUTY COMMISSIONER NALBARI_IDA) | Recommended | ₹10.00 L | — | +67% | 42.3 | MEDIUM |
| Boundary Wall of Batshor Surchuri Milanpur Masjid. 713 days beyond expected completion | NALBARI(DEPUTY COMMISSIONER NALBARI_IDA) | Recommended | ₹2.50 L | 713 d | 0% | 40.0 | MEDIUM |
| Construction of BT Road and RCC Drain at MarowaGunespa with Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range | NALBARI(DEPUTY COMMISSIONER NALBARI_IDA) | Recommended | ₹30.00 L | — | 0% | 39.2 | LOW |
| Renovation of Boundary Wall near Bhelebari Shankardev Namgha 659 days beyond expected completion | NALBARI(DEPUTY COMMISSIONER NALBARI_IDA) | Recommended | ₹2.00 L | 659 d | -71% | 38.7 | LOW |
| Installation of Solar Street light at Billesor Dewaloy 608 days beyond expected completion | NALBARI(DEPUTY COMMISSIONER NALBARI_IDA) | Recommended | ₹5.00 L | 608 d | 0% | 38.6 | LOW |
| Construction of road from Belsor Kakaya link road to Nadirpa 608 days beyond expected completion | NALBARI(DEPUTY COMMISSIONER NALBARI_IDA) | Recommended | ₹5.00 L | 608 d | -17% | 38.6 | LOW |
| Renovation of Community Hall near Kalbari Kali Mandir, Dehar 659 days beyond expected completion | NALBARI(DEPUTY COMMISSIONER NALBARI_IDA) | Recommended | ₹2.50 L | 659 d | -58% | 38.5 | LOW |
| Construction of road from Palla road to Annalay"s house conn 570 days beyond expected completion | NALBARI(DEPUTY COMMISSIONER NALBARI_IDA) | Recommended | ₹3.50 L | 570 d | -42% | 38.3 | LOW |