64 works across 1 implementing agency, recommended by 2 members of parliament. No allocation figure is published per district — every rupee below is summed from the works themselves.
The people a district authority actually supervises. Vendor concentration is counted from the payment records: an agency paying almost everything to one vendor is worth a question, not an accusation.
| # | Agency | Works | Completed | Sanctioned | To verify | Avg score | Top vendor |
|---|---|---|---|---|---|---|---|
| 1 | MARIGAON(District Development Commissioner Morigaon) | 64 | 28 | ₹2.09 Cr | 36 | 29.2 | ACHYUT SAIKIA 18% of spend · 51 vendors |
Whose funds paid for this district’s works.
| Member | Works | Sanctioned | To verify |
|---|---|---|---|
| Pradyut Bordoloi NOWGONG | 62 | ₹1.94 Cr | 34 |
| Jogen Mohan Sitting Rajya Sabha | 2 | ₹15.00 L | 2 |
Sector read from each work’s description.
| Sector | Works | Sanctioned | To verify |
|---|---|---|---|
| Community Buildings | 23 | ₹68.50 L | 12 |
| Religious & Cultural | 15 | ₹52.00 L | 9 |
| Boundary & Protection | 10 | ₹31.00 L | 4 |
| Education | 9 | ₹34.00 L | 7 |
| Roads & Paving | 3 | ₹8.49 L | 1 |
| Drainage & Sanitation | 2 | ₹6.50 L | 2 |
| Sports | 2 | ₹9.00 L | 1 |
Patterns across an agency’s whole book of work. None of these move any individual work’s score.
Round figures are normal and similar works legitimately cost the same. One figure covering nearly every work is what this looks for, and it means the costing is worth seeing, not that it is wrong.
Ranked by score. Cost is judged against comparable works in this district and sector, so a high cost score means unlike its neighbours — not overpriced.
| Work | Agency | Status | Sanctioned | Delay | Cost vs peers | Score | Band |
|---|---|---|---|---|---|---|---|
| Infastructure Development of Asto Prahor Palnam Than ₹1,000,000 against a ₹300,000 median for Religious & Cultural works in MARIGAON (233% above, 40 peer works) | MARIGAON(District Development Commissioner Morigaon) | Recommended | ₹10.00 L | — | +233% | 53.9 | MEDIUM |
| Construction of Rabha Griha at Niz Kapahera Sarbajanin Shiva ₹500,000 against a ₹300,000 median for Religious & Cultural works in MARIGAON (67% above, 40 peer works) | MARIGAON(District Development Commissioner Morigaon) | Recommended | ₹5.00 L | — | +67% | 45.6 | MEDIUM |
| Installation of Fixed Garden Gym Equipment at Charan Beel Mo 683 days beyond expected completion | MARIGAON(District Development Commissioner Morigaon) | Recommended | ₹5.00 L | 683 d | 0% | 43.8 | MEDIUM |
| Construction of Boundary Wall with Iron Gate at Kukuwari LP 683 days beyond expected completion | MARIGAON(District Development Commissioner Morigaon) | Recommended | ₹5.00 L | 683 d | +25% | 43.8 | MEDIUM |
| Construction of Digital Library Centre at Sr. Secondary Scho 683 days beyond expected completion | MARIGAON(District Development Commissioner Morigaon) | Recommended | ₹5.00 L | 683 d | +25% | 43.8 | MEDIUM |
| Construction of Toilet Block at Basna Ghat Chilarai Udyan S 683 days beyond expected completion | MARIGAON(District Development Commissioner Morigaon) | Recommended | ₹4.00 L | 683 d | 0% | 43.2 | MEDIUM |
| Construction of Community Hall with Boundary Wall for Sat Sa 683 days beyond expected completion | MARIGAON(District Development Commissioner Morigaon) | Recommended | ₹4.00 L | 683 d | +33% | 43.2 | MEDIUM |
| Construction of Building at Hazi Izzat Ali Memorial MEM at B 683 days beyond expected completion | MARIGAON(District Development Commissioner Morigaon) | Recommended | ₹4.00 L | 683 d | 0% | 43.2 | MEDIUM |
| Construction of Monikut for Bhagabati Mandir at Hatigarh, Pa 683 days beyond expected completion | MARIGAON(District Development Commissioner Morigaon) | Recommended | ₹2.50 L | 683 d | -17% | 42.8 | MEDIUM |
| Construction of Community Hall for Sri Sri Shani Mandir at B 683 days beyond expected completion | MARIGAON(District Development Commissioner Morigaon) | Recommended | ₹2.50 L | 683 d | -17% | 42.8 | MEDIUM |
| Construction of community hall for Novajay Yubak Sancha Saru 683 days beyond expected completion | MARIGAON(District Development Commissioner Morigaon) | Recommended | ₹2.50 L | 683 d | -17% | 42.8 | MEDIUM |
| Construction of Public Toilet near Purana Itavata, Bordubatu 683 days beyond expected completion | MARIGAON(District Development Commissioner Morigaon) | Recommended | ₹2.50 L | 683 d | 0% | 42.8 | MEDIUM |
| Construction of Community Hall near Sri Sri Kalhila Ananta D 684 days beyond expected completion | MARIGAON(District Development Commissioner Morigaon) | Recommended | ₹2.50 L | 684 d | -17% | 42.8 | MEDIUM |
| Construction of Janaja Ghar at Mikirbheta Muslim Gaon, Mori 683 days beyond expected completion | MARIGAON(District Development Commissioner Morigaon) | Recommended | ₹3.00 L | 683 d | 0% | 42.6 | MEDIUM |
| Construction of Community Hall for Sankari Kristi Bikash Ken 683 days beyond expected completion | MARIGAON(District Development Commissioner Morigaon) | Recommended | ₹3.00 L | 683 d | 0% | 42.6 | MEDIUM |