61 works across 1 implementing agency, recommended by 4 members of parliament. No allocation figure is published per district — every rupee below is summed from the works themselves.
The people a district authority actually supervises. Vendor concentration is counted from the payment records: an agency paying almost everything to one vendor is worth a question, not an accusation.
| # | Agency | Works | Completed | Sanctioned | To verify | Avg score | Top vendor |
|---|---|---|---|---|---|---|---|
| 1 | KAMRUP(DEPUTY COMMISSIONER KAMRUP_IDA) 1 high risk | 61 | 16 | ₹2.93 Cr | 7 | 33.1 | Hiranya Pathak 44% of spend · 37 vendors |
Whose funds paid for this district’s works.
| Member | Works | Sanctioned | To verify |
|---|---|---|---|
| Dilip Saikia Darrang-Udalguri | 53 | ₹1.38 Cr | 3 |
| Queen Oja GUWAHATI | 5 | ₹1.20 Cr | 1 |
| Pabitra Margherita Sitting Rajya Sabha | 2 | ₹25.00 L | 2 |
| Birendra Prasad Baishya Sitting Rajya Sabha | 1 | ₹10.00 L | 1 |
Sector read from each work’s description.
| Sector | Works | Sanctioned | To verify |
|---|---|---|---|
| Community Buildings | 36 | ₹1.39 Cr | 5 |
| Religious & Cultural | 11 | ₹25.00 L | 0 |
| Boundary & Protection | 5 | ₹14.50 L | 1 |
| Education | 5 | ₹25.00 L | 1 |
| Roads & Paving | 4 | ₹89.99 L | 0 |
Patterns across an agency’s whole book of work. None of these move any individual work’s score.
Round figures are normal and similar works legitimately cost the same. One figure covering nearly every work is what this looks for, and it means the costing is worth seeing, not that it is wrong.
Ranked by score. Cost is judged against comparable works in this district and sector, so a high cost score means unlike its neighbours — not overpriced.
| Work | Agency | Status | Sanctioned | Delay | Cost vs peers | Score | Band |
|---|---|---|---|---|---|---|---|
| Construction of Bus Stand at Boko College, Jarapara, Boko, K ₹1,500,000 against a ₹300,000 median for Education works in KAMRUP (400% above, 11 peer works) | KAMRUP(DEPUTY COMMISSIONER KAMRUP_IDA) | Recommended | ₹15.00 L | 254 d | +400% | 75.9 | HIGH |
| construction of Milan Sangha building at Sarpara, Palashbar ₹3,000,000 against a ₹300,000 median for Community Buildings works in KAMRUP (900% above, 67 peer works) | KAMRUP(DEPUTY COMMISSIONER KAMRUP_IDA) | Recommended | ₹30.00 L | 555 d | +900% | 55.9 | MEDIUM |
| Construction of Community Hall near Sarbajanin Sri Sri Laxmi ₹1,000,000 against a ₹300,000 median for Community Buildings works in KAMRUP (233% above, 67 peer works) | KAMRUP(DEPUTY COMMISSIONER KAMRUP_IDA) | Recommended | ₹10.00 L | — | +233% | 50.9 | MEDIUM |
| Construction of Sajei Dagaon Chowk Rajahuwa Sabha Ghar, Daga ₹1,000,000 against a ₹300,000 median for Community Buildings works in KAMRUP (233% above, 67 peer works) | KAMRUP(DEPUTY COMMISSIONER KAMRUP_IDA) | Recommended | ₹10.00 L | — | +233% | 50.9 | MEDIUM |
| Construction of Community Hall near Ischadgharia Sri Sri Jag ₹500,000 against a ₹300,000 median for Community Buildings works in KAMRUP (67% above, 67 peer works) | KAMRUP(DEPUTY COMMISSIONER KAMRUP_IDA) | Recommended | ₹5.00 L | 659 d | +67% | 47.6 | MEDIUM |
| Construction of Community hall near Sri Sri Maha Bishnu Jagy ₹500,000 against a ₹300,000 median for Community Buildings works in KAMRUP (67% above, 67 peer works) | KAMRUP(DEPUTY COMMISSIONER KAMRUP_IDA) | Recommended | ₹5.00 L | 665 d | +67% | 47.6 | MEDIUM |
| Construction of Boundary wall near AGP office, Rangia 680 days beyond expected completion | KAMRUP(DEPUTY COMMISSIONER KAMRUP_IDA) | Recommended | ₹5.00 L | 680 d | 0% | 40.8 | MEDIUM |
| Construction/Repairing of community hall of Kaliram Bishnu J 680 days beyond expected completion | KAMRUP(DEPUTY COMMISSIONER KAMRUP_IDA) | Recommended | ₹2.00 L | 680 d | -33% | 39.9 | LOW |
| Renovation of Nabasuruj Puthibharal, Rangia 680 days beyond expected completion | KAMRUP(DEPUTY COMMISSIONER KAMRUP_IDA) | Recommended | ₹2.00 L | 680 d | -33% | 39.9 | LOW |
| Construction/Repairing of Community Hall near Panara Shiv Ma 678 days beyond expected completion | KAMRUP(DEPUTY COMMISSIONER KAMRUP_IDA) | Recommended | ₹2.00 L | 678 d | -33% | 39.8 | LOW |
| Construction/Renovation of community hall near Sri sri Gopal 677 days beyond expected completion | KAMRUP(DEPUTY COMMISSIONER KAMRUP_IDA) | Recommended | ₹2.00 L | 677 d | -33% | 39.8 | LOW |
| Construction/Renovation of Cultural Stage near Ganesh Mandir 677 days beyond expected completion | KAMRUP(DEPUTY COMMISSIONER KAMRUP_IDA) | Recommended | ₹2.00 L | 677 d | -33% | 39.8 | LOW |
| Construction/Renovation of Cultural Stage near Basudev Doul 677 days beyond expected completion | KAMRUP(DEPUTY COMMISSIONER KAMRUP_IDA) | Recommended | ₹2.00 L | 677 d | -33% | 39.8 | LOW |
| Construction/Renovation of Community Hall near Bathou Thansa 677 days beyond expected completion | KAMRUP(DEPUTY COMMISSIONER KAMRUP_IDA) | Recommended | ₹2.00 L | 677 d | -33% | 39.8 | LOW |
| Construction/Renovation of Community Hall near Borochuburi S 677 days beyond expected completion | KAMRUP(DEPUTY COMMISSIONER KAMRUP_IDA) | Recommended | ₹2.00 L | 677 d | -33% | 39.8 | LOW |