35 works across 1 implementing agency, recommended by 5 members of parliament. No allocation figure is published per district — every rupee below is summed from the works themselves.
The people a district authority actually supervises. Vendor concentration is counted from the payment records: an agency paying almost everything to one vendor is worth a question, not an accusation.
| # | Agency | Works | Completed | Sanctioned | To verify | Avg score | Top vendor |
|---|---|---|---|---|---|---|---|
| 1 | DHEMAJI(DEPUTY COMMISSIONER DHEMAJI_IDA) 1 high risk | 35 | 24 | ₹2.57 Cr | 7 | 24.0 | Homen Pegu 21% of spend · 18 vendors |
Whose funds paid for this district’s works.
| Member | Works | Sanctioned | To verify |
|---|---|---|---|
| Pradan Baruah LAKHIMPUR | 30 | ₹1.55 Cr | 3 |
| Rwngwra Narzary Sitting Rajya Sabha | 2 | ₹32.00 L | 2 |
| Pabitra Margherita Sitting Rajya Sabha | 1 | ₹50.00 L | 1 |
| Birendra Prasad Baishya Sitting Rajya Sabha | 1 | ₹10.00 L | 1 |
| Jogen Mohan Sitting Rajya Sabha | 1 | ₹10.00 L | 0 |
Sector read from each work’s description.
| Sector | Works | Sanctioned | To verify |
|---|---|---|---|
| Community Buildings | 23 | ₹1.46 Cr | 4 |
| Education | 5 | ₹64.89 L | 2 |
| Religious & Cultural | 3 | ₹19.99 L | 1 |
| Health | 2 | ₹11.83 L | 0 |
| Drainage & Sanitation | 1 | ₹5.00 L | 0 |
| Roads & Paving | 1 | ₹10.00 L | 0 |
Ranked by score. Cost is judged against comparable works in this district and sector, so a high cost score means unlike its neighbours — not overpriced.
| Work | Agency | Status | Sanctioned | Delay | Cost vs peers | Score | Band |
|---|---|---|---|---|---|---|---|
| Construction of Community Hall at Jonai Mising Kristi Bhawan ₹5,000,000 against a ₹300,000 median for Community Buildings works in DHEMAJI (1567% above, 87 peer works) | DHEMAJI(DEPUTY COMMISSIONER DHEMAJI_IDA) | Recommended | ₹50.00 L | 275 d | +1567% | 74.7 | HIGH |
| Const. of Community Hall at Tanganapara Nepali Gaon near Har ₹600,000 against a ₹300,000 median for Community Buildings works in DHEMAJI (100% above, 87 peer works) | DHEMAJI(DEPUTY COMMISSIONER DHEMAJI_IDA) | Recommended | ₹6.00 L | 728 d | +100% | 54.7 | MEDIUM |
| construction of boundary wall with gate at Gobindapu village ₹1,200,000 against a ₹300,000 median for Community Buildings works in DHEMAJI (300% above, 87 peer works) | DHEMAJI(DEPUTY COMMISSIONER DHEMAJI_IDA) | Recommended | ₹12.00 L | — | +300% | 49.7 | MEDIUM |
| Construction Of Boundary Wall at Baruah Block High School, L ₹1,000,000 against a ₹500,000 median for Education works in DHEMAJI (100% above, 20 peer works) | DHEMAJI(DEPUTY COMMISSIONER DHEMAJI_IDA) | Recommended | ₹10.00 L | — | +100% | 49.7 | MEDIUM |
| Construction of Auditorium Hall at Mingmang Nalbari HS schoo ₹2,000,000 against a ₹500,000 median for Education works in DHEMAJI (300% above, 20 peer works) | DHEMAJI(DEPUTY COMMISSIONER DHEMAJI_IDA) | Completed | ₹20.00 L | — | +300% | 49.7 | MEDIUM |
| Construction of Borpak Gowalgoi Community Hall near Harimand ₹500,000 against a ₹300,000 median for Community Buildings works in DHEMAJI (67% above, 87 peer works) | DHEMAJI(DEPUTY COMMISSIONER DHEMAJI_IDA) | Recommended | ₹5.00 L | 720 d | +67% | 46.4 | MEDIUM |
| Infrastructure Development of Jorkata Bihattar Yuba Samaj Bi Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range | DHEMAJI(DEPUTY COMMISSIONER DHEMAJI_IDA) | Recommended | ₹10.00 L | 589 d | 0% | 42.2 | MEDIUM |
| Construction of Nagakhelia Community Hall near Hari Mandir u 720 days beyond expected completion | DHEMAJI(DEPUTY COMMISSIONER DHEMAJI_IDA) | Recommended | ₹3.00 L | 720 d | 0% | 39.4 | LOW |
| Construction of community hall near Moridhal Perabhari Harim 660 days beyond expected completion | DHEMAJI(DEPUTY COMMISSIONER DHEMAJI_IDA) | Recommended | ₹3.00 L | 660 d | 0% | 37.5 | LOW |
| Const. of community hall near Medhabari Harimandir, Ajuha GP 589 days beyond expected completion | DHEMAJI(DEPUTY COMMISSIONER DHEMAJI_IDA) | Recommended | ₹2.50 L | 589 d | -17% | 36.8 | LOW |
| Const. of community hall near Chamuah Gaon Namghar, Sissimuk 589 days beyond expected completion | DHEMAJI(DEPUTY COMMISSIONER DHEMAJI_IDA) | Recommended | ₹3.00 L | 589 d | 0% | 36.7 | LOW |
| Const. of RCC computer room at Jonai Girls' College, Murkong ₹1,998,811 against a ₹500,000 median for Education works in DHEMAJI (300% above, 20 peer works) | DHEMAJI(DEPUTY COMMISSIONER DHEMAJI_IDA) | Completed | ₹19.99 L | — | +300% | 29.7 | LOW |
| Const. of building at Nalbari Kristi Bhawan at Nalbari under ₹999,935 against a ₹300,000 median for Community Buildings works in DHEMAJI (233% above, 87 peer works) | DHEMAJI(DEPUTY COMMISSIONER DHEMAJI_IDA) | Completed | ₹10.00 L | — | +233% | 29.7 | LOW |
| Const. of Open Stage at Machkhowa Degree College, Machkhowa, ₹1,000,000 against a ₹500,000 median for Education works in DHEMAJI (100% above, 20 peer works) | DHEMAJI(DEPUTY COMMISSIONER DHEMAJI_IDA) | Completed | ₹10.00 L | — | +100% | 29.7 | LOW |
| CONSTRUCTION OF CHAW CHENG REN AT GHUGUHA GAON,DHEMAJI 100% similarity with another nearby work | DHEMAJI(DEPUTY COMMISSIONER DHEMAJI_IDA) | Recommended | ₹10.00 L | — | 0% | 27.3 | LOW |