405 works across 1 implementing agency, recommended by 5 members of parliament. No allocation figure is published per district — every rupee below is summed from the works themselves.
The people a district authority actually supervises. Vendor concentration is counted from the payment records: an agency paying almost everything to one vendor is worth a question, not an accusation.
| # | Agency | Works | Completed | Sanctioned | To verify | Avg score | Top vendor |
|---|---|---|---|---|---|---|---|
| 1 | PRAKASAM(DISTRICT COLLECTOR PRAKASAM_IDA) 1 high risk | 405 | 226 | ₹22.12 Cr | 74 | 27.1 | CHAIRMAN HWC AKAVEEDU 5% of spend · 135 vendors |
Whose funds paid for this district’s works.
| Member | Works | Sanctioned | To verify |
|---|---|---|---|
| Magunta Sreenivasulu Reddy ONGOLE | 342 | ₹17.75 Cr | 39 |
| Yerram Venkata Subba Reddy Sitting Rajya Sabha | 52 | ₹3.58 Cr | 29 |
| V. Vijayendra Prasad Nominated Rajya Sabha | 5 | ₹25.00 L | 5 |
| Nandigam Suresh BAPATLA | 5 | ₹24.13 L | 0 |
| Paka Venkata Satyanarayana Sitting Rajya Sabha | 1 | ₹30.00 L | 1 |
Sector read from each work’s description.
| Sector | Works | Sanctioned | To verify |
|---|---|---|---|
| Roads & Paving | 264 | ₹13.91 Cr | 13 |
| Water | 74 | ₹2.29 Cr | 42 |
| Drainage & Sanitation | 21 | ₹1.09 Cr | 1 |
| Community Buildings | 15 | ₹2.12 Cr | 5 |
| Religious & Cultural | 9 | ₹72.69 L | 3 |
| Education | 7 | ₹89.27 L | 4 |
| Sports | 4 | ₹16.50 L | 2 |
| Health | 3 | ₹45.72 L | 1 |
| Equipment & Vehicles | 3 | ₹21.17 L | 1 |
| Boundary & Protection | 3 | ₹15.00 L | 2 |
Patterns across an agency’s whole book of work. None of these move any individual work’s score.
The whole population fails the textbook test — the median agency scores 6.2 where Nigrini calls 1.5 nonconformant — because MPLADS amounts are capped, rounded and repeated by design. This ranks agencies against each other, not against the law. It is the weakest signal here and is never evidence on its own.
An agency whose sanctions all arrive in the last quarter looks identical. This is a spending pattern, not a finding.
An agency whose sanctions all arrive in the last quarter looks identical. This is a spending pattern, not a finding.
Ranked by score. Cost is judged against comparable works in this district and sector, so a high cost score means unlike its neighbours — not overpriced.
| Work | Agency | Status | Sanctioned | Delay | Cost vs peers | Score | Band |
|---|---|---|---|---|---|---|---|
| Construction of Community Hall in Chakirala Village of Kanig ₹2,000,000 against a ₹950,000 median for Community Buildings works in PRAKASAM (111% above, 23 peer works) | PRAKASAM(DISTRICT COLLECTOR PRAKASAM_IDA) | Recommended | ₹20.00 L | 241 d | +111% | 75.9 | HIGH |
| Construction of Library Building at Thallur Village, Thallur ₹3,500,000 against a ₹500,000 median for Education works in PRAKASAM (600% above, 18 peer works) | PRAKASAM(DISTRICT COLLECTOR PRAKASAM_IDA) | Recommended | ₹35.00 L | 126 d | +600% | 68.4 | MEDIUM |
| Construction of Community Hall in Vedulla Cheruvu Village an ₹2,000,000 against a ₹950,000 median for Community Buildings works in PRAKASAM (111% above, 23 peer works) | PRAKASAM(DISTRICT COLLECTOR PRAKASAM_IDA) | Recommended | ₹20.00 L | 66 d | +111% | 60.0 | MEDIUM |
| Construction of C.C.Road from Jagananna Colony (S.C.Locality 586 days beyond expected completion | PRAKASAM(DISTRICT COLLECTOR PRAKASAM_IDA) | Recommended | ₹5.00 L | 586 d | +0% | 58.6 | MEDIUM |
| Construction of C.C.Road from Jagananna Colony (S.C.Locality 586 days beyond expected completion | PRAKASAM(DISTRICT COLLECTOR PRAKASAM_IDA) | Recommended | ₹5.00 L | 586 d | +0% | 58.6 | MEDIUM |
| Providing 1000 LPH Reverse Osmosis Plant with Bore well, Mot 603 days beyond expected completion | PRAKASAM(DISTRICT COLLECTOR PRAKASAM_IDA) | Recommended | ₹1.80 L | 603 d | -42% | 58.1 | MEDIUM |
| Providing 1000 LPH Reverse Osmosis Plant with Bore well, Mot 603 days beyond expected completion | PRAKASAM(DISTRICT COLLECTOR PRAKASAM_IDA) | Recommended | ₹1.80 L | 603 d | -42% | 58.1 | MEDIUM |
| Providing 1000 LPH Reverse Osmosis Plant with Bore well, Mot 603 days beyond expected completion | PRAKASAM(DISTRICT COLLECTOR PRAKASAM_IDA) | Recommended | ₹1.80 L | 603 d | -42% | 58.1 | MEDIUM |
| Providing 1000 LPH Reverse Osmosis Plant with Bore well, Mot 603 days beyond expected completion | PRAKASAM(DISTRICT COLLECTOR PRAKASAM_IDA) | Recommended | ₹2.75 L | 603 d | -12% | 57.8 | MEDIUM |
| Providing 1000 LPH Reverse Osmosis Plant with Bore well, Mot 603 days beyond expected completion | PRAKASAM(DISTRICT COLLECTOR PRAKASAM_IDA) | Recommended | ₹3.00 L | 603 d | -4% | 57.6 | MEDIUM |
| Providing deep borewell and motor and pumpset and other mate ₹500,000 against a ₹312,500 median for Water works in PRAKASAM (60% above, 104 peer works) | PRAKASAM(DISTRICT COLLECTOR PRAKASAM_IDA) | Recommended | ₹5.00 L | 116 d | +60% | 57.0 | MEDIUM |
| Providing deep Borewell and motor and pumpset and other mate ₹500,000 against a ₹312,500 median for Water works in PRAKASAM (60% above, 104 peer works) | PRAKASAM(DISTRICT COLLECTOR PRAKASAM_IDA) | Recommended | ₹5.00 L | 114 d | +60% | 56.7 | MEDIUM |
| Construction of Spandana Meeting Hall at Sub Collector’s Off ₹5,500,000 against a ₹950,000 median for Community Buildings works in PRAKASAM (479% above, 23 peer works) | PRAKASAM(DISTRICT COLLECTOR PRAKASAM_IDA) | Recommended | ₹55.00 L | 573 d | +479% | 55.9 | MEDIUM |
| Construction of Community Hall (B.C. Bhavan) in Anjaiah Road ₹5,000,000 against a ₹499,573 median for Roads & Paving works in PRAKASAM (901% above, 290 peer works) | PRAKASAM(DISTRICT COLLECTOR PRAKASAM_IDA) | Recommended | ₹50.00 L | 586 d | +901% | 55.9 | MEDIUM |
| Construction of Internal C.C.Road and CD Works in Bellamkond ₹1,000,000 against a ₹499,573 median for Roads & Paving works in PRAKASAM (100% above, 290 peer works) | PRAKASAM(DISTRICT COLLECTOR PRAKASAM_IDA) | Recommended | ₹10.00 L | 600 d | +100% | 55.9 | MEDIUM |