| 1 | CONSTRUTION OF COMUNNITY HALL AT ANTARDA UNDER TARBHA NAC Community Buildings — Subarnapur(District Collector Subarnapur_IDA) - ₹600,000 against a ₹200,000 median for Community Buildings works in SUBARNAPUR (200% above, 139 peer works)
- 548 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- Implementing agency has a 59% delay rate across its projects
| SUBARNAPUR | ₹6.00 L | HIGH 79
cost 25delay 25duplication 20 | |
| 2 | Construction of Community Centre at Village Sukhlasar Community Buildings — Subarnapur(District Collector Subarnapur_IDA) - ₹400,000 against a ₹200,000 median for Community Buildings works in SUBARNAPUR (100% above, 139 peer works)
- 616 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- Implementing agency has a 59% delay rate across its projects
| SUBARNAPUR | ₹4.00 L | HIGH 79
cost 25delay 25duplication 20 | |
| 3 | Construction of Community Centre at Village Ainlapali Community Buildings — Subarnapur(District Collector Subarnapur_IDA) - ₹400,000 against a ₹200,000 median for Community Buildings works in SUBARNAPUR (100% above, 139 peer works)
- 616 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- Implementing agency has a 59% delay rate across its projects
| SUBARNAPUR | ₹4.00 L | HIGH 79
cost 25delay 25duplication 20 | |
| 4 | CONSTRUTION OF COMUNNITY HALL AT ANTARDA UNDER TARBHA NAC Community Buildings — Subarnapur(District Collector Subarnapur_IDA) - ₹600,000 against a ₹200,000 median for Community Buildings works in SUBARNAPUR (200% above, 139 peer works)
- 548 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- Implementing agency has a 59% delay rate across its projects
| SUBARNAPUR | ₹6.00 L | HIGH 79
cost 25delay 25duplication 20 | |
| 5 | Construction of Community Centre at Village Sukhlasar Community Buildings — Subarnapur(District Collector Subarnapur_IDA) - ₹400,000 against a ₹200,000 median for Community Buildings works in SUBARNAPUR (100% above, 139 peer works)
- 616 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- Implementing agency has a 59% delay rate across its projects
| SUBARNAPUR | ₹4.00 L | HIGH 79
cost 25delay 25duplication 20 | |
| 6 | Construction of Community Centre at Village Ainlapali Community Buildings — Subarnapur(District Collector Subarnapur_IDA) - ₹400,000 against a ₹200,000 median for Community Buildings works in SUBARNAPUR (100% above, 139 peer works)
- 616 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- Implementing agency has a 59% delay rate across its projects
| SUBARNAPUR | ₹4.00 L | HIGH 79
cost 25delay 25duplication 20 | |
| 7 | Cremation center near burial ground in Rajapur village in Ga Religious & Cultural — GANJAM(DISTRICT COLLECTOR GANJAM_IDA) - ₹1,000,000 against a ₹300,000 median for Religious & Cultural works in GANJAM (233% above, 112 peer works)
- 302 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- Implementing agency has a 57% delay rate across its projects
| GANJAM | ₹10.00 L | HIGH 79
cost 25delay 25duplication 20 | |
| 8 | Cremation center near burial ground in Rajapur village in Ga Religious & Cultural — GANJAM(DISTRICT COLLECTOR GANJAM_IDA) - ₹1,000,000 against a ₹300,000 median for Religious & Cultural works in GANJAM (233% above, 112 peer works)
- 302 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- Implementing agency has a 57% delay rate across its projects
| GANJAM | ₹10.00 L | HIGH 79
cost 25delay 25duplication 20 | |
| 9 | construction of the Lawyers Association Building District Ba Community Buildings — MALKANGIRI(District Collector Malkangiri_IDA) - ₹1,000,000 against a ₹300,000 median for Community Buildings works in MALKANGIRI (233% above, 101 peer works)
- 705 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- Implementing agency has a 53% delay rate across its projects
| MALKANGIRI | ₹10.00 L | HIGH 78
cost 25delay 25duplication 20 | |
| 10 | construction of the Lawyers Association Building District Ba Community Buildings — MALKANGIRI(District Collector Malkangiri_IDA) - ₹1,000,000 against a ₹300,000 median for Community Buildings works in MALKANGIRI (233% above, 101 peer works)
- 705 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- Implementing agency has a 53% delay rate across its projects
| MALKANGIRI | ₹10.00 L | HIGH 78
cost 25delay 25duplication 20 | |
| 11 | Construction of New India Library Building at Borapada Dhenk Education — DHENKANAL(DISTRICT COLLECTOR DHENKANAL_IDA) - ₹998,000 against a ₹400,000 median for Education works in DHENKANAL (150% above, 59 peer works)
- 264 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- Implementing agency has a 42% delay rate across its projects
| DHENKANAL | ₹9.98 L | HIGH 76
cost 25delay 25duplication 20 | |
| 12 | Construction of New India Library Building at Borapada Dhenk Education — DHENKANAL(DISTRICT COLLECTOR DHENKANAL_IDA) - ₹998,000 against a ₹400,000 median for Education works in DHENKANAL (150% above, 59 peer works)
- 264 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- Implementing agency has a 42% delay rate across its projects
| DHENKANAL | ₹9.98 L | HIGH 76
cost 25delay 25duplication 20 | |
| 13 | Renovation of Christian Cemetery in Jatni Town, Khurda distr Religious & Cultural — KHORDHA(DISTRICT COLLECTOR KHORDHA_IDA) - ₹500,000 against a ₹250,000 median for Religious & Cultural works in KHORDHA (100% above, 128 peer works)
- 192 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- Implementing agency has a 41% delay rate across its projects
| KHORDHA | ₹5.00 L | HIGH 76
cost 25delay 25duplication 20 | |
| 14 | Repair and Renovation of KUMAR PATHAGARA, Kumarangasasan, Ba Community Buildings — KHORDHA(DISTRICT COLLECTOR KHORDHA_IDA) - ₹1,000,000 against a ₹500,000 median for Community Buildings works in KHORDHA (100% above, 144 peer works)
- 302 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- Implementing agency has a 41% delay rate across its projects
| KHORDHA | ₹10.00 L | HIGH 76
cost 25delay 25duplication 20 | |
| 15 | Construction of Community Center in Alisibindha Village, Blo Community Buildings — KHORDHA(DISTRICT COLLECTOR KHORDHA_IDA) - ₹1,000,000 against a ₹500,000 median for Community Buildings works in KHORDHA (100% above, 144 peer works)
- 342 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- Implementing agency has a 41% delay rate across its projects
| KHORDHA | ₹10.00 L | HIGH 76
cost 25delay 25duplication 20 | |
| 16 | Construction of Community Center in Chakeisihani Village, Wa Community Buildings — KHORDHA(DISTRICT COLLECTOR KHORDHA_IDA) - ₹1,000,000 against a ₹500,000 median for Community Buildings works in KHORDHA (100% above, 144 peer works)
- 350 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- Implementing agency has a 41% delay rate across its projects
| KHORDHA | ₹10.00 L | HIGH 76
cost 25delay 25duplication 20 | |
| 17 | Construction of Community Center in Salapadihi village under Community Buildings — KHORDHA(DISTRICT COLLECTOR KHORDHA_IDA) - ₹1,000,000 against a ₹500,000 median for Community Buildings works in KHORDHA (100% above, 144 peer works)
- 405 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- Implementing agency has a 41% delay rate across its projects
| KHORDHA | ₹10.00 L | HIGH 76
cost 25delay 25duplication 20 | |
| 18 | Construction of Additional Building and Renovation in Odisha Community Buildings — KHORDHA(DISTRICT COLLECTOR KHORDHA_IDA) - ₹1,000,000 against a ₹500,000 median for Community Buildings works in KHORDHA (100% above, 144 peer works)
- 419 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- Implementing agency has a 41% delay rate across its projects
| KHORDHA | ₹10.00 L | HIGH 76
cost 25delay 25duplication 20 | |
| 19 | CONSTRUTION OF COMMUNITY CENTRE AT BANPUR NAC WARD NO. 02 FO Community Buildings — KHORDHA(DISTRICT COLLECTOR KHORDHA_IDA) - ₹1,000,000 against a ₹500,000 median for Community Buildings works in KHORDHA (100% above, 144 peer works)
- 548 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- Implementing agency has a 41% delay rate across its projects
| KHORDHA | ₹10.00 L | HIGH 76
cost 25delay 25duplication 20 | |
| 20 | Construction of two additional classrooms of the B.B. Govt V Education — KHORDHA(DISTRICT COLLECTOR KHORDHA_IDA) - ₹1,500,000 against a ₹500,000 median for Education works in KHORDHA (200% above, 131 peer works)
- 594 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- Implementing agency has a 41% delay rate across its projects
| KHORDHA | ₹15.00 L | HIGH 76
cost 25delay 25duplication 20 | |
| 21 | Construction of two Guest Rooms inside the Hostel Premises o Education — KHORDHA(DISTRICT COLLECTOR KHORDHA_IDA) - ₹1,500,000 against a ₹500,000 median for Education works in KHORDHA (200% above, 131 peer works)
- 595 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- Implementing agency has a 41% delay rate across its projects
| KHORDHA | ₹15.00 L | HIGH 76
cost 25delay 25duplication 20 | |
| 22 | Construction of BATABRUKSHYA MANDAP COMMUNITY HALL near Daru Community Buildings — KHORDHA(DISTRICT COLLECTOR KHORDHA_IDA) - ₹1,000,000 against a ₹500,000 median for Community Buildings works in KHORDHA (100% above, 144 peer works)
- 620 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- Implementing agency has a 41% delay rate across its projects
| KHORDHA | ₹10.00 L | HIGH 76
cost 25delay 25duplication 20 | |
| 23 | Construction of Auditorium of BJB (Autonomous) College, BJB Education — KHORDHA(DISTRICT COLLECTOR KHORDHA_IDA) - ₹5,000,000 against a ₹500,000 median for Education works in KHORDHA (900% above, 131 peer works)
- 620 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- Implementing agency has a 41% delay rate across its projects
| KHORDHA | ₹50.00 L | HIGH 76
cost 25delay 25duplication 20 | |
| 24 | Commissioning of 20watt Semi Integrated Solar Lights, 30AH L Street Lighting — KHORDHA(DISTRICT COLLECTOR KHORDHA_IDA) - ₹1,865,000 against a ₹165,000 median for Street Lighting works in KHORDHA (1030% above, 25 peer works)
- 869 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- Implementing agency has a 41% delay rate across its projects
| KHORDHA | ₹18.65 L | HIGH 76
cost 25delay 25duplication 20 | |
| 25 | Commissioning of 20watt Semi Integrated Solar Lights, 30AH L Street Lighting — KHORDHA(DISTRICT COLLECTOR KHORDHA_IDA) - ₹1,790,000 against a ₹165,000 median for Street Lighting works in KHORDHA (985% above, 25 peer works)
- 869 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- Implementing agency has a 41% delay rate across its projects
| KHORDHA | ₹17.90 L | HIGH 76
cost 25delay 25duplication 20 | |