| 1 | Construction Teenshed at Trimurti dham, Gram Panchayat Umri, Religious & Cultural — BHIND(DISTRICT COLLECTOR BHIND_IDA) - ₹995,000 against a ₹250,000 median for Religious & Cultural works in BHIND (298% above, 10 peer works)
- 191 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- 84% of this agency's ₹50,485,526 spend went to one vendor (MP STATE AGRO INDUSTRIES DEV CORP LTD), across 29 vendors and 192 transactions
| BHIND | ₹9.95 L | HIGH 85
cost 25delay 25duplication 20 | |
| 2 | Banipur Road se Ramswaroop ke khet ke pas Khanba ki aor DevS Roads & Paving — BHIND(DISTRICT COLLECTOR BHIND_IDA) - ₹250,000 against a ₹76,581 median for Roads & Paving works in BHIND (226% above, 59 peer works)
- 809 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- 84% of this agency's ₹50,485,526 spend went to one vendor (MP STATE AGRO INDUSTRIES DEV CORP LTD), across 29 vendors and 192 transactions
| BHIND | ₹2.50 L | HIGH 85
cost 25delay 25duplication 20 | |
| 3 | Jagdish ke khet se Yogendra ki baithak ki aur Dev singh ka p Roads & Paving — BHIND(DISTRICT COLLECTOR BHIND_IDA) - ₹250,000 against a ₹76,581 median for Roads & Paving works in BHIND (226% above, 59 peer works)
- 809 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- 84% of this agency's ₹50,485,526 spend went to one vendor (MP STATE AGRO INDUSTRIES DEV CORP LTD), across 29 vendors and 192 transactions
| BHIND | ₹2.50 L | HIGH 85
cost 25delay 25duplication 20 | |
| 4 | community hall nirman Community Buildings — RAJGARH(DISTRICT COLLECTOR RAJGARH_IDA) - ₹1,000,000 against a ₹306,328 median for Community Buildings works in RAJGARH (226% above, 53 peer works)
- 716 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- 78% of this agency's ₹80,688,034 spend went to one vendor (MP Agro Biaora), across 19 vendors and 490 transactions
| RAJGARH | ₹10.00 L | HIGH 85
cost 25delay 25duplication 20 | |
| 5 | Construction Teenshed at Trimurti dham, Gram Panchayat Umri, Religious & Cultural — BHIND(DISTRICT COLLECTOR BHIND_IDA) - ₹995,000 against a ₹250,000 median for Religious & Cultural works in BHIND (298% above, 10 peer works)
- 191 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- 88% of this agency's ₹18,918,434 spend went to one vendor (MP STATE AGRO INDUSTRIES DEV CORP LTD), across 8 vendors and 131 transactions
| BHIND | ₹9.95 L | HIGH 85
cost 25delay 25duplication 20 | |
| 6 | Banipur Road se Ramswaroop ke khet ke pas Khanba ki aor DevS Roads & Paving — BHIND(DISTRICT COLLECTOR BHIND_IDA) - ₹250,000 against a ₹76,581 median for Roads & Paving works in BHIND (226% above, 59 peer works)
- 809 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- 88% of this agency's ₹18,918,434 spend went to one vendor (MP STATE AGRO INDUSTRIES DEV CORP LTD), across 8 vendors and 131 transactions
| BHIND | ₹2.50 L | HIGH 85
cost 25delay 25duplication 20 | |
| 7 | Jagdish ke khet se Yogendra ki baithak ki aur Dev singh ka p Roads & Paving — BHIND(DISTRICT COLLECTOR BHIND_IDA) - ₹250,000 against a ₹76,581 median for Roads & Paving works in BHIND (226% above, 59 peer works)
- 809 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- 88% of this agency's ₹18,918,434 spend went to one vendor (MP STATE AGRO INDUSTRIES DEV CORP LTD), across 8 vendors and 131 transactions
| BHIND | ₹2.50 L | HIGH 85
cost 25delay 25duplication 20 | |
| 8 | Gram panchayat Ahrolighat, Janpad panchayat Ater ke gram Ahr Community Buildings — BHIND(DISTRICT COLLECTOR BHIND_IDA) - ₹150,000 against a ₹76,581 median for Community Buildings works in BHIND (96% above, 44 peer works)
- 567 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- 84% of this agency's ₹50,485,526 spend went to one vendor (MP STATE AGRO INDUSTRIES DEV CORP LTD), across 29 vendors and 192 transactions
| BHIND | ₹1.50 L | HIGH 84
delay 25cost 24duplication 20 | |
| 9 | Gram panchayat Ahrolighat, Janpad panchayat Ater ke gram Ahr Community Buildings — BHIND(DISTRICT COLLECTOR BHIND_IDA) - ₹150,000 against a ₹76,581 median for Community Buildings works in BHIND (96% above, 44 peer works)
- 567 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- 88% of this agency's ₹18,918,434 spend went to one vendor (MP STATE AGRO INDUSTRIES DEV CORP LTD), across 8 vendors and 131 transactions
| BHIND | ₹1.50 L | HIGH 84
delay 25cost 24duplication 20 | |
| 10 | Construction of community hall at gram Eklahara, gram Pancha Community Buildings — BETUL(DISTRICT COLLECTOR BETUL_IDA) - ₹1,000,000 against a ₹250,000 median for Community Buildings works in BETUL (300% above, 221 peer works)
- 808 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- 74% of this agency's ₹56,741,127 spend went to one vendor (MP STATE AGRO INDUSTRIES DEVELOPMENT CORP LTD), across 113 vendors and 439 transactions
| BETUL | ₹10.00 L | HIGH 83
cost 25delay 25duplication 20 | |
| 11 | Construction work of culvert over drain in village Anhori Be Roads & Paving — RAISEN(DISTRICT COLLECTOR RAISEN_IDA) - ₹1,500,000 against a ₹300,000 median for Roads & Paving works in RAISEN (400% above, 89 peer works)
- 271 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- Implementing agency has a 85% delay rate across its projects
| RAISEN | ₹15.00 L | HIGH 83
cost 25delay 25duplication 20 | |
| 12 | Common work sheds for artisans Community Buildings — RAISEN(DISTRICT COLLECTOR RAISEN_IDA) - ₹500,000 against a ₹150,000 median for Community Buildings works in RAISEN (233% above, 94 peer works)
- 714 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- Implementing agency has a 85% delay rate across its projects
| RAISEN | ₹5.00 L | HIGH 83
cost 25delay 25duplication 20 | |
| 13 | Common work sheds for artisans Community Buildings — RAISEN(DISTRICT COLLECTOR RAISEN_IDA) - ₹300,000 against a ₹150,000 median for Community Buildings works in RAISEN (100% above, 94 peer works)
- 714 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- Implementing agency has a 85% delay rate across its projects
| RAISEN | ₹3.00 L | HIGH 83
cost 25delay 25duplication 20 | |
| 14 | Construction of roads, approach roads, link roads and pathwa Roads & Paving — RAISEN(DISTRICT COLLECTOR RAISEN_IDA) - ₹1,000,000 against a ₹300,000 median for Roads & Paving works in RAISEN (233% above, 89 peer works)
- 714 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- Implementing agency has a 85% delay rate across its projects
| RAISEN | ₹10.00 L | HIGH 83
cost 25delay 25duplication 20 | |
| 15 | COMMUNITY HALL Community Buildings — RAISEN(DISTRICT COLLECTOR RAISEN_IDA) - ₹601,300 against a ₹150,000 median for Community Buildings works in RAISEN (301% above, 94 peer works)
- 772 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- Implementing agency has a 85% delay rate across its projects
| RAISEN | ₹6.01 L | HIGH 83
cost 25delay 25duplication 20 | |
| 16 | Construction work of culvert over drain in village Anhori Be Roads & Paving — RAISEN(DISTRICT COLLECTOR RAISEN_IDA) - ₹1,500,000 against a ₹300,000 median for Roads & Paving works in RAISEN (400% above, 89 peer works)
- 271 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- Implementing agency has a 85% delay rate across its projects
| RAISEN | ₹15.00 L | HIGH 83
cost 25delay 25duplication 20 | |
| 17 | Construction CC Road with drainage at badera sopan teh. Bha Roads & Paving — DATIA(District Collector Datia_IDA) - ₹1,000,000 against a ₹404,000 median for Roads & Paving works in DATIA (148% above, 11 peer works)
- 191 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- 68% of this agency's ₹12,585,834 spend went to one vendor (M P STATE AGRO INDUSTRIES DEV CORP LTD), across 4 vendors and 49 transactions
| DATIA | ₹10.00 L | HIGH 82
cost 25delay 25duplication 20 | |
| 18 | Gram Khapa, Gram Panchayat Banurkhapa, Vikaskhand Multai Dis Roads & Paving — BETUL(DISTRICT COLLECTOR BETUL_IDA) - ₹610,000 against a ₹259,942 median for Roads & Paving works in BETUL (135% above, 51 peer works)
- 171 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- 74% of this agency's ₹56,741,127 spend went to one vendor (MP STATE AGRO INDUSTRIES DEVELOPMENT CORP LTD), across 113 vendors and 439 transactions
| BETUL | ₹6.10 L | HIGH 82
cost 25delay 24duplication 20 | |
| 19 | Installation work of solar street lights in Gram panchayats Street Lighting — REWA(DISTRICT COLLECTOR REWA_IDA) - ₹1,971,292 against a ₹697,800 median for Street Lighting works in REWA (182% above, 54 peer works)
- 239 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- Implementing agency has a 77% delay rate across its projects
| REWA | ₹19.71 L | HIGH 82
cost 25delay 25duplication 20 | |
| 20 | Fitting of Sitting RCC Benches in Public Places Equipment & Vehicles — REWA(DISTRICT COLLECTOR REWA_IDA) - ₹2,770,770 against a ₹874,980 median for Equipment & Vehicles works in REWA (217% above, 27 peer works)
- 595 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- Implementing agency has a 77% delay rate across its projects
| REWA | ₹27.71 L | HIGH 82
cost 25delay 25duplication 20 | |
| 21 | Construction of additional rooms and halls in the existing p Community Buildings — REWA(DISTRICT COLLECTOR REWA_IDA) - ₹1,000,000 against a ₹500,000 median for Community Buildings works in REWA (100% above, 18 peer works)
- 727 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- Implementing agency has a 77% delay rate across its projects
| REWA | ₹10.00 L | HIGH 82
cost 25delay 25duplication 20 | |
| 22 | Construction of additional rooms and halls in the existing p Community Buildings — REWA(DISTRICT COLLECTOR REWA_IDA) - ₹1,000,000 against a ₹500,000 median for Community Buildings works in REWA (100% above, 18 peer works)
- 727 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- Implementing agency has a 77% delay rate across its projects
| REWA | ₹10.00 L | HIGH 82
cost 25delay 25duplication 20 | |
| 23 | Solar Lighting of public spaces and Street Street Lighting — REWA(DISTRICT COLLECTOR REWA_IDA) - ₹1,395,600 against a ₹697,800 median for Street Lighting works in REWA (100% above, 54 peer works)
- 727 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- Implementing agency has a 77% delay rate across its projects
| REWA | ₹13.96 L | HIGH 82
cost 25delay 25duplication 20 | |
| 24 | Installation work of solar street lights in Gram panchayats Street Lighting — REWA(DISTRICT COLLECTOR REWA_IDA) - ₹1,971,292 against a ₹697,800 median for Street Lighting works in REWA (182% above, 54 peer works)
- 239 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- Implementing agency has a 77% delay rate across its projects
| REWA | ₹19.71 L | HIGH 82
cost 25delay 25duplication 20 | |
| 25 | Construction of Grewal Road Roads & Paving — REWA(DISTRICT COLLECTOR REWA_IDA) - ₹2,444,000 against a ₹500,000 median for Roads & Paving works in REWA (389% above, 29 peer works)
- 213 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- Implementing agency has a 77% delay rate across its projects
| REWA | ₹24.44 L | HIGH 82
cost 25delay 25duplication 20 | |