| 1 | Construction of Community hall near Sitaramaanjaneya temple, Community Buildings — HANUMAKONDA(DISTRICT COLLECTOR HANUMAKONDA_IDA) - ₹5,000,000 against a ₹499,000 median for Community Buildings works in HANUMAKONDA (902% above, 29 peer works)
- 157 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- 1 payment still in progress, oldest 1092 days
| HANUMAKONDA | ₹50.00 L | HIGH 82
cost 25delay 22duplication 20 | |
| 2 | Construction Of Multi purpose Hall at Kaldhari Village,Undra Community Buildings — EAST GODAVARI(DISTRICT COLLECTOR, EAST GODAVARI) - ₹5,000,000 against a ₹2,500,000 median for Community Buildings works in EAST GODAVARI (100% above, 38 peer works)
- 246 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- Implementing agency has a 42% delay rate across its projects
| EAST GODAVARI | ₹50.00 L | HIGH 76
cost 25delay 25duplication 20 | |
| 3 | Construction Of Multi purpose Hall at Kaldhari Village,Undra Community Buildings — EAST GODAVARI(DISTRICT COLLECTOR, EAST GODAVARI) - ₹5,000,000 against a ₹2,500,000 median for Community Buildings works in EAST GODAVARI (100% above, 38 peer works)
- 246 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- Implementing agency has a 42% delay rate across its projects
| EAST GODAVARI | ₹50.00 L | HIGH 76
cost 25delay 25duplication 20 | |
| 4 | Construction of additional infrastructure at Phule Ambedkar Community Buildings — EAST GODAVARI(DISTRICT COLLECTOR, EAST GODAVARI) - ₹8,000,000 against a ₹2,500,000 median for Community Buildings works in EAST GODAVARI (220% above, 38 peer works)
- 183 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- Implementing agency has a 42% delay rate across its projects
| EAST GODAVARI | ₹80.00 L | HIGH 76
cost 25delay 25duplication 20 | |
| 5 | Construction of Community Hall in Chakirala Village of Kanig Community Buildings — PRAKASAM(DISTRICT COLLECTOR PRAKASAM_IDA) - ₹2,000,000 against a ₹950,000 median for Community Buildings works in PRAKASAM (111% above, 23 peer works)
- 241 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| PRAKASAM | ₹20.00 L | HIGH 76
cost 25delay 25duplication 20 | |
| 6 | Construction of Community Hall in Chakirala Village of Kanig Community Buildings — PRAKASAM(DISTRICT COLLECTOR PRAKASAM_IDA) - ₹2,000,000 against a ₹950,000 median for Community Buildings works in PRAKASAM (111% above, 23 peer works)
- 241 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| PRAKASAM | ₹20.00 L | HIGH 76
cost 25delay 25duplication 20 | |
| 7 | Providing drainage from G Rajsekhar house to K Hari babu hou Drainage & Sanitation — Annamayya(DISTRICT COLLECTOR ANNAMAYYA_IDA) - ₹500,000 against a ₹244,126 median for Drainage & Sanitation works in ANNAMAYYA (105% above, 42 peer works)
- 203 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| ANNAMAYYA | ₹5.00 L | HIGH 74
cost 25delay 25duplication 20 | |
| 8 | Providing drainage in Peddamadigapalli H/o in D.Racchapalli Drainage & Sanitation — Annamayya(DISTRICT COLLECTOR ANNAMAYYA_IDA) - ₹490,000 against a ₹244,126 median for Drainage & Sanitation works in ANNAMAYYA (101% above, 42 peer works)
- 302 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| ANNAMAYYA | ₹4.90 L | HIGH 74
cost 25delay 25duplication 20 | |
| 9 | Providing drainage from G Rajsekhar house to K Hari babu hou Drainage & Sanitation — Annamayya(DISTRICT COLLECTOR ANNAMAYYA_IDA) - ₹500,000 against a ₹244,126 median for Drainage & Sanitation works in ANNAMAYYA (105% above, 42 peer works)
- 203 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| ANNAMAYYA | ₹5.00 L | HIGH 74
cost 25delay 25duplication 20 | |
| 10 | Providing drainage in Peddamadigapalli H/o in D.Racchapalli Drainage & Sanitation — Annamayya(DISTRICT COLLECTOR ANNAMAYYA_IDA) - ₹490,000 against a ₹244,126 median for Drainage & Sanitation works in ANNAMAYYA (101% above, 42 peer works)
- 302 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| ANNAMAYYA | ₹4.90 L | HIGH 74
cost 25delay 25duplication 20 | |
| 11 | Providing Amenities to BC Burial Ground Religious & Cultural — Eluru(DISTRICT COLLECTOR ELURU_IDA) - ₹800,000 against a ₹350,000 median for Religious & Cultural works in ELURU (129% above, 16 peer works)
- 545 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| ELURU | ₹8.00 L | HIGH 74
cost 25delay 25duplication 20 | |
| 12 | Construction of community centers and community halls Community Buildings — Alluri Sitharama Raju(DISTRICT COLLECTOR ALLURI SITHARAMARAJU_IDA) - ₹3,000,000 against a ₹500,000 median for Community Buildings works in ALLURI SITHARAMA RAJU (500% above, 15 peer works)
- 258 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| ALLURI SITHARAMA RAJU | ₹30.00 L | HIGH 73
cost 25delay 25duplication 20 | |
| 13 | Development of Physical infrastructure and purchase of labor Education — Y.S.R. Kadapa(DISTRICT COLLECTOR CUDDAPAH_IDA) - ₹998,996 against a ₹498,000 median for Education works in Y.S.R. KADAPA (101% above, 21 peer works)
- 795 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| Y.S.R. KADAPA | ₹9.99 L | HIGH 72
cost 25delay 25duplication 20 | |
| 14 | Construction of Community hall near Sitaramaanjaneya temple, Community Buildings — HANUMAKONDA(DISTRICT COLLECTOR HANUMAKONDA_IDA) - ₹5,000,000 against a ₹499,000 median for Community Buildings works in HANUMAKONDA (902% above, 29 peer works)
- 157 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| HANUMAKONDA | ₹50.00 L | HIGH 72
cost 25delay 22duplication 20 | |
| 15 | Repairs to the sluice of Appala Reddy Cheruvu in Palakolanu Water — KURNOOL(DISTRICT COLLECTOR KURNOOL_IDA) - ₹499,988 against a ₹199,992 median for Water works in KURNOOL (150% above, 440 peer works)
- 270 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| KURNOOL | ₹5.00 L | HIGH 71
cost 25delay 25duplication 20 | |
| 16 | Providing CC Drains (Reach - II) at B.C. Colony of Nallagutt Drainage & Sanitation — Annamayya(DISTRICT COLLECTOR ANNAMAYYA_IDA) - ₹500,000 against a ₹244,126 median for Drainage & Sanitation works in ANNAMAYYA (105% above, 42 peer works)
- 607 days beyond expected completion
Read more (1 more)Show less- 99% similarity with another nearby work
| ANNAMAYYA | ₹5.00 L | HIGH 71
cost 25delay 25duplication 17 | |
| 17 | Construction of Multipurpose Building Community Buildings — Dr. B.R. Ambedkar Konaseema(DISTRICT COLLECTOR Dr B R AMBEDKAR KONASEEMA_IDA) - ₹4,000,000 against a ₹500,000 median for Community Buildings works in DR. B.R. AMBEDKAR KONASEEMA (700% above, 43 peer works)
- 736 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| DR. B.R. AMBEDKAR KONASEEMA | ₹40.00 L | HIGH 71
cost 25delay 25duplication 20 | |
| 18 | The renovation of old Hospital Block and Construction of new Health — EAST GODAVARI(DISTRICT COLLECTOR, EAST GODAVARI) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 251 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- Implementing agency has a 42% delay rate across its projects
| EAST GODAVARI | ₹50.00 L | HIGH 71
delay 25duplication 20cost 20 | |
| 19 | The renovation of old Hospital Block and Construction of new Health — EAST GODAVARI(DISTRICT COLLECTOR, EAST GODAVARI) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 251 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- Implementing agency has a 42% delay rate across its projects
| EAST GODAVARI | ₹50.00 L | HIGH 71
delay 25duplication 20cost 20 | |
| 20 | Construction of 1000 mm dia 4 Row RCC pipe Culvert in Km 0/0 Roads & Paving — Sri Potti Sriramulu Nellore(DISTRICT COLLECTOR NELLORE_IDA) - ₹1,483,285 against a ₹499,868 median for Roads & Paving works in SRI POTTI SRIRAMULU NELLORE (197% above, 233 peer works)
- 303 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| SRI POTTI SRIRAMULU NELLORE | ₹14.83 L | HIGH 71
cost 25delay 25duplication 20 | |
| 21 | Construction of new floor of the existing building of Netaji Education — Visakhapatnam(DISTRICT COLLECTOR VISAKHAPATNAM_IDA) - ₹8,000,000 against a ₹1,700,000 median for Education works in VISAKHAPATNAM (371% above, 32 peer works)
- 153 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| VISAKHAPATNAM | ₹80.00 L | HIGH 70
cost 25delay 21duplication 20 | |
| 22 | Construction of new floor of the existing building of Netaji Education — Visakhapatnam(DISTRICT COLLECTOR VISAKHAPATNAM_IDA) - ₹8,000,000 against a ₹1,700,000 median for Education works in VISAKHAPATNAM (371% above, 32 peer works)
- 153 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| VISAKHAPATNAM | ₹80.00 L | HIGH 70
cost 25delay 21duplication 20 | |
| 23 | Construction of community hall in Sno.182 B.Yaleru village A Community Buildings — Ananthapuramu(DISTRICT COLLECTOR ANANTAPUR_IDA) - ₹1,000,000 against a ₹500,000 median for Community Buildings works in ANANTHAPURAMU (100% above, 95 peer works)
- 256 days beyond expected completion
Read more (1 more)Show less- 99% similarity with another nearby work
| ANANTHAPURAMU | ₹10.00 L | MEDIUM 70
cost 25delay 25duplication 18 | |
| 24 | Construction of community hall in Sno.203 B. Yaleru village Community Buildings — Ananthapuramu(DISTRICT COLLECTOR ANANTAPUR_IDA) - ₹1,000,000 against a ₹500,000 median for Community Buildings works in ANANTHAPURAMU (100% above, 95 peer works)
- 256 days beyond expected completion
Read more (1 more)Show less- 99% similarity with another nearby work
| ANANTHAPURAMU | ₹10.00 L | MEDIUM 70
cost 25delay 25duplication 18 | |
| 25 | Upgrade infrastructure in Gosha Hospital at Vizianagaram dis Health — VIZIANAGARAM(DISTRICT COLLECTOR VIZIANAGARAM_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 268 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| VIZIANAGARAM | ₹50.00 L | MEDIUM 69
delay 25duplication 20cost 20 | |