| 1 | Construction of Samudaya Bhavana at Mallinatha Pura Grama, R Community Buildings — HASSAN(DEPUTY COMMISSIONER HASSAN_IDA) - ₹500,000 against a ₹300,000 median for Community Buildings works in HASSAN (67% above, 293 peer works)
- 219 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- 10 payments still in progress, oldest 633 days
| HASSAN | ₹5.00 L | HIGH 74
delay 25duplication 20cost 17 | |
| 2 | Construction of Rooms for government school, Hedtale Village Education — MYSURU(DEPUTY COMMISSIONER MYSORE_IDA) - ₹1,000,000 against a ₹500,000 median for Education works in MYSURU (100% above, 38 peer works)
- 79 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- 92% of this agency's ₹73,408,556 spend went to one vendor (Mysore Nirmithi Kendra), across 7 vendors and 192 transactions
| MYSURU | ₹10.00 L | HIGH 71
cost 25duplication 20agency 15 | |
| 3 | Construction of Samudaya Bhavana at Mallinatha Pura Grama, R Community Buildings — HASSAN(DEPUTY COMMISSIONER HASSAN_IDA) - ₹500,000 against a ₹300,000 median for Community Buildings works in HASSAN (67% above, 293 peer works)
- 219 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| HASSAN | ₹5.00 L | MEDIUM 67
delay 25duplication 20cost 17 | |
| 4 | Bangalore Urban District, Jayanagar Vidhanasabha constituenc Roads & Paving — BENGALURU URBAN(DEPUTY COMMISSIONER BANGALORE URBAN_IDA) - ₹2,500,000 against a ₹499,575 median for Roads & Paving works in BENGALURU URBAN (400% above, 567 peer works)
- 132 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| BENGALURU URBAN | ₹25.00 L | MEDIUM 65
cost 25duplication 20delay 18 | |
| 5 | Bangalore Urban district, Jayanagar assembly constituency, w Roads & Paving — BENGALURU URBAN(DEPUTY COMMISSIONER BANGALORE URBAN_IDA) - ₹2,500,000 against a ₹499,575 median for Roads & Paving works in BENGALURU URBAN (400% above, 567 peer works)
- 132 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| BENGALURU URBAN | ₹25.00 L | MEDIUM 65
cost 25duplication 20delay 18 | |
| 6 | Bangalore Urban district, Jayanagar assembly constituency, w Roads & Paving — BENGALURU URBAN(DEPUTY COMMISSIONER BANGALORE URBAN_IDA) - ₹2,000,000 against a ₹499,575 median for Roads & Paving works in BENGALURU URBAN (300% above, 567 peer works)
- 132 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| BENGALURU URBAN | ₹20.00 L | MEDIUM 65
cost 25duplication 20delay 18 | |
| 7 | Bangalore Urban District, Jayanagar Vidhanasabha constituenc Roads & Paving — BENGALURU URBAN(DEPUTY COMMISSIONER BANGALORE URBAN_IDA) - ₹2,500,000 against a ₹499,575 median for Roads & Paving works in BENGALURU URBAN (400% above, 567 peer works)
- 132 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| BENGALURU URBAN | ₹25.00 L | MEDIUM 65
cost 25duplication 20delay 18 | |
| 8 | Bangalore Urban district, Jayanagar assembly constituency, w Roads & Paving — BENGALURU URBAN(DEPUTY COMMISSIONER BANGALORE URBAN_IDA) - ₹2,500,000 against a ₹499,575 median for Roads & Paving works in BENGALURU URBAN (400% above, 567 peer works)
- 132 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| BENGALURU URBAN | ₹25.00 L | MEDIUM 65
cost 25duplication 20delay 18 | |
| 9 | Bangalore Urban district, Jayanagar assembly constituency, w Roads & Paving — BENGALURU URBAN(DEPUTY COMMISSIONER BANGALORE URBAN_IDA) - ₹2,000,000 against a ₹499,575 median for Roads & Paving works in BENGALURU URBAN (300% above, 567 peer works)
- 132 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| BENGALURU URBAN | ₹20.00 L | MEDIUM 65
cost 25duplication 20delay 18 | |
| 10 | Development of road work from Basavapattana and Belavadi mai Roads & Paving — HASSAN(DEPUTY COMMISSIONER HASSAN_IDA) - 219 days beyond expected completion
- 100% similarity with another nearby work
Read more (1 more)Show less- 10 payments still in progress, oldest 633 days
| HASSAN | ₹5.00 L | MEDIUM 65
delay 25duplication 20agency 13 | |
| 11 | Development of road work from Thattavalu main road to Siddan Roads & Paving — HASSAN(DEPUTY COMMISSIONER HASSAN_IDA) - 219 days beyond expected completion
- 100% similarity with another nearby work
Read more (1 more)Show less- 10 payments still in progress, oldest 633 days
| HASSAN | ₹5.00 L | MEDIUM 65
delay 25duplication 20agency 13 | |
| 12 | Development of Concrete drainage from Pundu house to Masale Drainage & Sanitation — HASSAN(DEPUTY COMMISSIONER HASSAN_IDA) - 219 days beyond expected completion
- 100% similarity with another nearby work
Read more (1 more)Show less- 10 payments still in progress, oldest 633 days
| HASSAN | ₹5.00 L | MEDIUM 65
delay 25duplication 20agency 13 | |
| 13 | construction of concrete road from venkatanarasamma home to Roads & Paving — BENGALURU RURAL(DEPUTY COMMISSIONER BANGALORE RURAL SBM URBAN) - 288 days beyond expected completion
- 100% similarity with another nearby work
Read more (1 more)Show less- 66% of this agency's ₹21,224,131 spend went to one vendor (NIRMITHI KENDRA BANGALORE RURAL DISTRICT), across 15 vendors and 90 transactions
| BENGALURU RURAL | ₹4.90 L | MEDIUM 64
delay 25duplication 20agency 11 | |
| 14 | construction of concrete road from lakshminarasimha swamy te Roads & Paving — BENGALURU RURAL(DEPUTY COMMISSIONER BANGALORE RURAL SBM URBAN) - 288 days beyond expected completion
- 100% similarity with another nearby work
Read more (1 more)Show less- 66% of this agency's ₹21,224,131 spend went to one vendor (NIRMITHI KENDRA BANGALORE RURAL DISTRICT), across 15 vendors and 90 transactions
| BENGALURU RURAL | ₹4.90 L | MEDIUM 64
delay 25duplication 20agency 11 | |
| 15 | Construction of Rooms for government school, Hedtale Village Education — MYSURU(DEPUTY COMMISSIONER MYSORE_IDA) - ₹1,000,000 against a ₹500,000 median for Education works in MYSURU (100% above, 38 peer works)
- 79 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| MYSURU | ₹10.00 L | MEDIUM 62
cost 25duplication 20delay 11 | |
| 16 | construction of bridge near chitradurga district, challakere Roads & Paving — CHITRADURGA(DEPUTY COMMISSIONER CHITRADURGA_IDA) - 261 days beyond expected completion
- 100% similarity with another nearby work
Read more (1 more)Show less- Implementing agency has a 59% delay rate across its projects
| CHITRADURGA | ₹4.90 L | MEDIUM 62
delay 25duplication 20agency 9 | |
| 17 | construction of roads from talakunayakanahatti to obayanahat Roads & Paving — CHITRADURGA(DEPUTY COMMISSIONER CHITRADURGA_IDA) - 261 days beyond expected completion
- 100% similarity with another nearby work
Read more (1 more)Show less- Implementing agency has a 59% delay rate across its projects
| CHITRADURGA | ₹4.90 L | MEDIUM 62
delay 25duplication 20agency 9 | |
| 18 | construction of bridge near chitradurga district, challakere Roads & Paving — CHITRADURGA(DEPUTY COMMISSIONER CHITRADURGA_IDA) - 261 days beyond expected completion
- 100% similarity with another nearby work
Read more (1 more)Show less- Implementing agency has a 59% delay rate across its projects
| CHITRADURGA | ₹4.90 L | MEDIUM 62
delay 25duplication 20agency 9 | |
| 19 | construction of roads from talakunayakanahatti to obayanahat Roads & Paving — CHITRADURGA(DEPUTY COMMISSIONER CHITRADURGA_IDA) - 261 days beyond expected completion
- 100% similarity with another nearby work
Read more (1 more)Show less- Implementing agency has a 59% delay rate across its projects
| CHITRADURGA | ₹4.90 L | MEDIUM 62
delay 25duplication 20agency 9 | |
| 20 | construction of shivayogishwara hostel at turuvekere town, T Education — TUMAKURU(DEPUTY COMMISSIONER TUMKUR_IDA) - ₹2,500,000 against a ₹742,087 median for Education works in TUMAKURU (237% above, 42 peer works)
- 75 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- 25 payments still in progress, oldest 368 days
| TUMAKURU | ₹25.00 L | MEDIUM 62
cost 25duplication 20delay 10 | |
| 21 | construction of shivayogishwara hostel at turuvekere town, T Education — TUMAKURU(DEPUTY COMMISSIONER TUMKUR_IDA) - ₹2,500,000 against a ₹742,087 median for Education works in TUMAKURU (237% above, 42 peer works)
- 75 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| TUMAKURU | ₹25.00 L | MEDIUM 61
cost 25duplication 20delay 10 | |
| 22 | Construction of Samudhaya Bhavan at the premises of Shivamog Roads & Paving — SHIVAMOGGA(DEPUTY COMMISSIONER SHIMOGA_IDA) - ₹1,000,000 against a ₹500,000 median for Roads & Paving works in SHIVAMOGGA (100% above, 118 peer works)
- 100% similarity with another nearby work
Read more (1 more)Show less- 53% of this agency's ₹76,492,740 spend went to one vendor (Nirmithi Kendra Shivamogga), across 11 vendors and 333 transactions
| SHIVAMOGGA | ₹10.00 L | MEDIUM 60
cost 25duplication 20agency 8 | |
| 23 | construction of shree Cheluvarayaswamy samudhaya bhavana at Community Buildings — MANDYA(DEPUTY COMMISSIONER MANDYA_IDA) - ₹1,000,000 against a ₹500,000 median for Community Buildings works in MANDYA (100% above, 177 peer works)
- 100% similarity with another nearby work
Read more (1 more)Show less- 90% of this agency's ₹44,437,263 spend went to one vendor (PROJECT MANAGER NIRMITHI KENDRA MANDYA), across 4 vendors and 119 transactions
| MANDYA | ₹10.00 L | MEDIUM 60
cost 25duplication 20agency 15 | |
| 24 | Construction of Samudhaya Bhavan at the premises of Shivamog Roads & Paving — SHIVAMOGGA(DEPUTY COMMISSIONER SHIMOGA_IDA) - ₹1,000,000 against a ₹500,000 median for Roads & Paving works in SHIVAMOGGA (100% above, 118 peer works)
- 100% similarity with another nearby work
Read more (1 more)Show less- 51% of this agency's ₹64,252,561 spend went to one vendor (Nirmithi Kendra Shivamogga), across 9 vendors and 274 transactions
| SHIVAMOGGA | ₹10.00 L | MEDIUM 60
cost 25duplication 20agency 8 | |
| 25 | Construction of Rooms of Ravidasiya (SC)Community Hall at St Roads & Paving — KAITHAL(DC CUM NODAL OFFICERS MPLADS) - 264 days beyond expected completion
- 100% similarity with another nearby work
Read more (1 more)Show less- Implementing agency has a 43% delay rate across its projects
| KAITHAL | ₹4.00 L | MEDIUM 60
delay 25duplication 20cost 8 | |