| 1 | Setting up of Soil Testing Labouratory by CRDS FPO at Rippon Equipment & Vehicles — SHIVAMOGGA(DEPUTY COMMISSIONER SHIMOGA_IDA) - ₹500,000 against a ₹100,000 median for Equipment & Vehicles works in SHIVAMOGGA (400% above, 38 peer works)
- 624 days beyond expected completion
Read more (1 more)Show less- 53% of this agency's ₹76,492,740 spend went to one vendor (Nirmithi Kendra Shivamogga), across 11 vendors and 333 transactions
| SHIVAMOGGA | ₹5.00 L | MEDIUM 58 | |
| 2 | Setting up of Soil Testing Labouratory by CRDS FPO at Bharan Equipment & Vehicles — SHIVAMOGGA(DEPUTY COMMISSIONER SHIMOGA_IDA) - ₹500,000 against a ₹100,000 median for Equipment & Vehicles works in SHIVAMOGGA (400% above, 38 peer works)
- 624 days beyond expected completion
Read more (1 more)Show less- 53% of this agency's ₹76,492,740 spend went to one vendor (Nirmithi Kendra Shivamogga), across 11 vendors and 333 transactions
| SHIVAMOGGA | ₹5.00 L | MEDIUM 58 | |
| 3 | Construction of outdoor Stadium in Holalur village of Holalu Sports — SHIVAMOGGA(DEPUTY COMMISSIONER SHIMOGA_IDA) - ₹3,500,000 against a ₹633,500 median for Sports works in SHIVAMOGGA (452% above, 8 peer works)
- 638 days beyond expected completion
Read more (1 more)Show less- 53% of this agency's ₹76,492,740 spend went to one vendor (Nirmithi Kendra Shivamogga), across 11 vendors and 333 transactions
| SHIVAMOGGA | ₹35.00 L | MEDIUM 58 | |
| 4 | Construction of Building Community Buildings — SHIVAMOGGA(DEPUTY COMMISSIONER SHIMOGA_IDA) - ₹1,000,000 against a ₹415,000 median for Community Buildings works in SHIVAMOGGA (141% above, 117 peer works)
- 239 days beyond expected completion
Read more (1 more)Show less- 51% of this agency's ₹64,252,561 spend went to one vendor (Nirmithi Kendra Shivamogga), across 9 vendors and 274 transactions
| SHIVAMOGGA | ₹10.00 L | MEDIUM 58 | |
| 5 | Construction of Milk Co Op Society (Women) Building in Mulak Community Buildings — SHIVAMOGGA(DEPUTY COMMISSIONER SHIMOGA_IDA) - ₹900,000 against a ₹415,000 median for Community Buildings works in SHIVAMOGGA (117% above, 117 peer works)
- 255 days beyond expected completion
Read more (1 more)Show less- 51% of this agency's ₹64,252,561 spend went to one vendor (Nirmithi Kendra Shivamogga), across 9 vendors and 274 transactions
| SHIVAMOGGA | ₹9.00 L | MEDIUM 58 | |
| 6 | Ongoing work of Shri Sewalal Banjar Youth Association Commun Community Buildings — SHIVAMOGGA(DEPUTY COMMISSIONER SHIMOGA_IDA) - ₹1,000,000 against a ₹415,000 median for Community Buildings works in SHIVAMOGGA (141% above, 117 peer works)
- 259 days beyond expected completion
Read more (1 more)Show less- 51% of this agency's ₹64,252,561 spend went to one vendor (Nirmithi Kendra Shivamogga), across 9 vendors and 274 transactions
| SHIVAMOGGA | ₹10.00 L | MEDIUM 58 | |
| 7 | installation of Pure Drinking Water Plant at Government High Water — SHIVAMOGGA(DEPUTY COMMISSIONER SHIMOGA_IDA) - 649 days beyond expected completion
- 98% similarity with another nearby work
Read more (1 more)Show less- 53% of this agency's ₹76,492,740 spend went to one vendor (Nirmithi Kendra Shivamogga), across 11 vendors and 333 transactions
| SHIVAMOGGA | ₹1.00 L | MEDIUM 56
delay 25duplication 14cost 9 | |
| 8 | installation of Pure Drinking Water Plant at Government High Water — SHIVAMOGGA(DEPUTY COMMISSIONER SHIMOGA_IDA) - 649 days beyond expected completion
- 98% similarity with another nearby work
Read more (1 more)Show less- 53% of this agency's ₹76,492,740 spend went to one vendor (Nirmithi Kendra Shivamogga), across 11 vendors and 333 transactions
| SHIVAMOGGA | ₹1.00 L | MEDIUM 56
delay 25duplication 14cost 9 | |
| 9 | Setting up of Soil Testing Labouratory by CRDS FPO at Chowda Other — SHIVAMOGGA(DEPUTY COMMISSIONER SHIMOGA_IDA) - ₹500,000 against a ₹325,000 median for Other works in SHIVAMOGGA (54% above, 16 peer works)
- 624 days beyond expected completion
Read more (1 more)Show less- 53% of this agency's ₹76,492,740 spend went to one vendor (Nirmithi Kendra Shivamogga), across 11 vendors and 333 transactions
| SHIVAMOGGA | ₹5.00 L | MEDIUM 53 | |
| 10 | Setting up of Soil Testing Labouratory by CRDS FPO at Udugan Other — SHIVAMOGGA(DEPUTY COMMISSIONER SHIMOGA_IDA) - ₹500,000 against a ₹325,000 median for Other works in SHIVAMOGGA (54% above, 16 peer works)
- 624 days beyond expected completion
Read more (1 more)Show less- 53% of this agency's ₹76,492,740 spend went to one vendor (Nirmithi Kendra Shivamogga), across 11 vendors and 333 transactions
| SHIVAMOGGA | ₹5.00 L | MEDIUM 53 | |
| 11 | Setting up of Soil Testing Labouratory by CRDS FPO at Malena Other — SHIVAMOGGA(DEPUTY COMMISSIONER SHIMOGA_IDA) - ₹500,000 against a ₹325,000 median for Other works in SHIVAMOGGA (54% above, 16 peer works)
- 624 days beyond expected completion
Read more (1 more)Show less- 53% of this agency's ₹76,492,740 spend went to one vendor (Nirmithi Kendra Shivamogga), across 11 vendors and 333 transactions
| SHIVAMOGGA | ₹5.00 L | MEDIUM 53 | |
| 12 | Setting up of Soil Testing Labouratory by CRDS FPO at Manda Other — SHIVAMOGGA(DEPUTY COMMISSIONER SHIMOGA_IDA) - ₹500,000 against a ₹325,000 median for Other works in SHIVAMOGGA (54% above, 16 peer works)
- 624 days beyond expected completion
Read more (1 more)Show less- 53% of this agency's ₹76,492,740 spend went to one vendor (Nirmithi Kendra Shivamogga), across 11 vendors and 333 transactions
| SHIVAMOGGA | ₹5.00 L | MEDIUM 53 | |
| 13 | installation of Pure Drinking Water Plant at Government High Water — SHIVAMOGGA(DEPUTY COMMISSIONER SHIMOGA_IDA) - 649 days beyond expected completion
- 97% similarity with another nearby work
Read more (1 more)Show less- 53% of this agency's ₹76,492,740 spend went to one vendor (Nirmithi Kendra Shivamogga), across 11 vendors and 333 transactions
| SHIVAMOGGA | ₹1.00 L | MEDIUM 53
delay 25duplication 11cost 9 | |
| 14 | Installation of street lights in Bhadravati Nagar Ward No.10 Street Lighting — SHIVAMOGGA(DEPUTY COMMISSIONER SHIMOGA_IDA) - 665 days beyond expected completion
- 96% similarity with another nearby work
Read more (1 more)Show less- 53% of this agency's ₹76,492,740 spend went to one vendor (Nirmithi Kendra Shivamogga), across 11 vendors and 333 transactions
| SHIVAMOGGA | ₹1.00 L | MEDIUM 51
delay 25cost 9duplication 8 | |
| 15 | Tirthahalli Taluk Salgadi Dist. Construction of additional r Education — SHIVAMOGGA(DEPUTY COMMISSIONER SHIMOGA_IDA) - ₹800,000 against a ₹495,000 median for Education works in SHIVAMOGGA (62% above, 41 peer works)
- 671 days beyond expected completion
Read more (1 more)Show less- 53% of this agency's ₹76,492,740 spend went to one vendor (Nirmithi Kendra Shivamogga), across 11 vendors and 333 transactions
| SHIVAMOGGA | ₹8.00 L | MEDIUM 49 | |
| 16 | Construction of outdoor Stadium in Holalur village of Holalu Sports — SHIVAMOGGA(DEPUTY COMMISSIONER SHIMOGA_IDA) - ₹1,000,000 against a ₹633,500 median for Sports works in SHIVAMOGGA (58% above, 8 peer works)
- 638 days beyond expected completion
Read more (1 more)Show less- 53% of this agency's ₹76,492,740 spend went to one vendor (Nirmithi Kendra Shivamogga), across 11 vendors and 333 transactions
| SHIVAMOGGA | ₹10.00 L | MEDIUM 48 | |
| 17 | Setting up of Soil Testing Labouratory by CRDS RAITHAMITRA F Other — SHIVAMOGGA(DEPUTY COMMISSIONER SHIMOGA_IDA) - ₹500,000 against a ₹325,000 median for Other works in SHIVAMOGGA (54% above, 16 peer works)
- 624 days beyond expected completion
Read more (1 more)Show less- 53% of this agency's ₹76,492,740 spend went to one vendor (Nirmithi Kendra Shivamogga), across 11 vendors and 333 transactions
| SHIVAMOGGA | ₹5.00 L | MEDIUM 47 | |
| 18 | Purchase of Tricycle Vehicle to Sri.Sridhar C.P S/o.Paramesh Equipment & Vehicles — SHIVAMOGGA(DEPUTY COMMISSIONER SHIMOGA_IDA) - ₹150,000 against a ₹100,000 median for Equipment & Vehicles works in SHIVAMOGGA (50% above, 38 peer works)
- 255 days beyond expected completion
Read more (1 more)Show less- 51% of this agency's ₹64,252,561 spend went to one vendor (Nirmithi Kendra Shivamogga), across 9 vendors and 274 transactions
| SHIVAMOGGA | ₹1.50 L | MEDIUM 45 | |
| 19 | Installation of Highmast Light near Sri Chandanamariyamma Te Street Lighting — SHIVAMOGGA(DEPUTY COMMISSIONER SHIMOGA_IDA) - ₹300,000 against a ₹200,000 median for Street Lighting works in SHIVAMOGGA (50% above, 113 peer works)
- 259 days beyond expected completion
Read more (1 more)Show less- 51% of this agency's ₹64,252,561 spend went to one vendor (Nirmithi Kendra Shivamogga), across 9 vendors and 274 transactions
| SHIVAMOGGA | ₹3.00 L | MEDIUM 45 | |
| 20 | installation of Pure Drinking Water Plant at Government Lowe Water — SHIVAMOGGA(DEPUTY COMMISSIONER SHIMOGA_IDA) - 649 days beyond expected completion
- 53% of this agency's ₹76,492,740 spend went to one vendor (Nirmithi Kendra Shivamogga), across 11 vendors and 333 transactions
| SHIVAMOGGA | ₹1.00 L | MEDIUM 45 | |
| 21 | CONSTRUCTION OF FARMERS TRAINING CENTER AT PRIMARY AGRICULTU Community Buildings — SHIVAMOGGA(DEPUTY COMMISSIONER SHIMOGA_IDA) - 616 days beyond expected completion
- 53% of this agency's ₹76,492,740 spend went to one vendor (Nirmithi Kendra Shivamogga), across 11 vendors and 333 transactions
| SHIVAMOGGA | ₹3.00 L | MEDIUM 44 | |
| 22 | Construction of CC Drainage and CC Road from Shivaramanagar Roads & Paving — SHIVAMOGGA(DEPUTY COMMISSIONER SHIMOGA_IDA) - 672 days beyond expected completion
- 53% of this agency's ₹76,492,740 spend went to one vendor (Nirmithi Kendra Shivamogga), across 11 vendors and 333 transactions
| SHIVAMOGGA | ₹5.00 L | MEDIUM 43 | |
| 23 | Providing pure Drinking Water Plant Unit to Seebinakere Gove Water — SHIVAMOGGA(DEPUTY COMMISSIONER SHIMOGA_IDA) - 675 days beyond expected completion
- 53% of this agency's ₹76,492,740 spend went to one vendor (Nirmithi Kendra Shivamogga), across 11 vendors and 333 transactions
| SHIVAMOGGA | ₹1.00 L | MEDIUM 43 | |
| 24 | Providing Pure Drinking Water plant at Government PU college Water — SHIVAMOGGA(DEPUTY COMMISSIONER SHIMOGA_IDA) - 675 days beyond expected completion
- 53% of this agency's ₹76,492,740 spend went to one vendor (Nirmithi Kendra Shivamogga), across 11 vendors and 333 transactions
| SHIVAMOGGA | ₹1.00 L | MEDIUM 43 | |
| 25 | Construction of new exercise school building and exercise eq Education — SHIVAMOGGA(DEPUTY COMMISSIONER SHIMOGA_IDA) - 665 days beyond expected completion
- 53% of this agency's ₹76,492,740 spend went to one vendor (Nirmithi Kendra Shivamogga), across 11 vendors and 333 transactions
| SHIVAMOGGA | ₹5.00 L | MEDIUM 43 | |