| 1 | Construction of Culture Centre near Tingrai Chariali Durga M Religious & Cultural — DIBRUGARH(DEPUTY COMMISSIONER DIBRUGARH_IDA) - ₹1,000,000 against a ₹500,000 median for Religious & Cultural works in DIBRUGARH (100% above, 41 peer works)
- 551 days beyond expected completion
Read more (1 more)Show less- Implementing agency has a 77% delay rate across its projects
| DIBRUGARH | ₹10.00 L | MEDIUM 62 | |
| 2 | Development of Cultural Centre near Nemupather Siv Mandir, P Religious & Cultural — DIBRUGARH(DEPUTY COMMISSIONER DIBRUGARH_IDA) - ₹1,000,000 against a ₹500,000 median for Religious & Cultural works in DIBRUGARH (100% above, 41 peer works)
- 551 days beyond expected completion
Read more (1 more)Show less- Implementing agency has a 77% delay rate across its projects
| DIBRUGARH | ₹10.00 L | MEDIUM 62 | |
| 3 | Haladhibari Chaolkara Gaon Cultural Centre Religious & Cultural — DIBRUGARH(DEPUTY COMMISSIONER DIBRUGARH_IDA) - ₹1,000,000 against a ₹500,000 median for Religious & Cultural works in DIBRUGARH (100% above, 41 peer works)
- 618 days beyond expected completion
Read more (1 more)Show less- Implementing agency has a 77% delay rate across its projects
| DIBRUGARH | ₹10.00 L | MEDIUM 62 | |
| 4 | Teliapather Punya Aranya Cultural Center Religious & Cultural — DIBRUGARH(DEPUTY COMMISSIONER DIBRUGARH_IDA) - ₹1,000,000 against a ₹500,000 median for Religious & Cultural works in DIBRUGARH (100% above, 41 peer works)
- 635 days beyond expected completion
Read more (1 more)Show less- Implementing agency has a 77% delay rate across its projects
| DIBRUGARH | ₹10.00 L | MEDIUM 62 | |
| 5 | Infrastructure development of Naharkatia Bihu Mancha Phase-I Religious & Cultural — DIBRUGARH(DEPUTY COMMISSIONER DIBRUGARH_IDA) - ₹1,500,000 against a ₹500,000 median for Religious & Cultural works in DIBRUGARH (200% above, 41 peer works)
- 635 days beyond expected completion
Read more (1 more)Show less- Implementing agency has a 77% delay rate across its projects
| DIBRUGARH | ₹15.00 L | MEDIUM 62 | |
| 6 | Construction of Pavers Block Road at LPG Bottling Plant to H Roads & Paving — TINSUKIA(DC Tinsukia) - ₹1,250,000 against a ₹500,000 median for Roads & Paving works in TINSUKIA (150% above, 22 peer works)
- 572 days beyond expected completion
Read more (1 more)Show less- Implementing agency has a 71% delay rate across its projects
| TINSUKIA | ₹12.50 L | MEDIUM 61 | |
| 7 | Construction of Pavers Block Road at Nabapur Path Bali Jan Roads & Paving — TINSUKIA(DC Tinsukia) - ₹1,250,000 against a ₹500,000 median for Roads & Paving works in TINSUKIA (150% above, 22 peer works)
- 572 days beyond expected completion
Read more (1 more)Show less- Implementing agency has a 71% delay rate across its projects
| TINSUKIA | ₹12.50 L | MEDIUM 61 | |
| 8 | Construction of Pavers Block Road at Tingrai Gaon Roads & Paving — TINSUKIA(DC Tinsukia) - ₹1,500,000 against a ₹500,000 median for Roads & Paving works in TINSUKIA (200% above, 22 peer works)
- 572 days beyond expected completion
Read more (1 more)Show less- Implementing agency has a 71% delay rate across its projects
| TINSUKIA | ₹15.00 L | MEDIUM 61 | |
| 9 | Construction of Pavers Block Road infront of RKB School Roads & Paving — TINSUKIA(DC Tinsukia) - ₹1,000,000 against a ₹500,000 median for Roads & Paving works in TINSUKIA (100% above, 22 peer works)
- 572 days beyond expected completion
Read more (1 more)Show less- Implementing agency has a 71% delay rate across its projects
| TINSUKIA | ₹10.00 L | MEDIUM 61 | |
| 10 | Construction of Pavers Block Road at Tokowani Roads & Paving — TINSUKIA(DC Tinsukia) - ₹1,500,000 against a ₹500,000 median for Roads & Paving works in TINSUKIA (200% above, 22 peer works)
- 572 days beyond expected completion
Read more (1 more)Show less- Implementing agency has a 71% delay rate across its projects
| TINSUKIA | ₹15.00 L | MEDIUM 61 | |
| 11 | Construction of RCC Bridge at Namdang Basti Line Ph-I Roads & Paving — TINSUKIA(DC Tinsukia) - ₹1,000,000 against a ₹500,000 median for Roads & Paving works in TINSUKIA (100% above, 22 peer works)
- 636 days beyond expected completion
Read more (1 more)Show less- Implementing agency has a 71% delay rate across its projects
| TINSUKIA | ₹10.00 L | MEDIUM 61 | |
| 12 | Development of Auditorium of Margherita P.H.S. School Education — TINSUKIA(DC Tinsukia) - ₹1,000,000 against a ₹500,000 median for Education works in TINSUKIA (100% above, 19 peer works)
- 636 days beyond expected completion
Read more (1 more)Show less- Implementing agency has a 71% delay rate across its projects
| TINSUKIA | ₹10.00 L | MEDIUM 61 | |
| 13 | Construction of Community Hall at Tekeri Yuba Sangha Community Buildings — TINSUKIA(DC Tinsukia) - ₹1,000,000 against a ₹500,000 median for Community Buildings works in TINSUKIA (100% above, 61 peer works)
- 636 days beyond expected completion
Read more (1 more)Show less- Implementing agency has a 71% delay rate across its projects
| TINSUKIA | ₹10.00 L | MEDIUM 61 | |
| 14 | Construction of Tea Tribe Library corn Guest house at Tea Tr Education — TINSUKIA(DC Tinsukia) - ₹1,000,000 against a ₹500,000 median for Education works in TINSUKIA (100% above, 19 peer works)
- 636 days beyond expected completion
Read more (1 more)Show less- Implementing agency has a 71% delay rate across its projects
| TINSUKIA | ₹10.00 L | MEDIUM 61 | |
| 15 | Infrastructure development of Joypur Forest Park Sports — DIBRUGARH(DEPUTY COMMISSIONER DIBRUGARH_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 635 days beyond expected completion
Read more (1 more)Show less- Implementing agency has a 77% delay rate across its projects
| DIBRUGARH | ₹25.00 L | MEDIUM 54 | |
| 16 | Infrastructure development of Tipam Sukafa Park Sports — DIBRUGARH(DEPUTY COMMISSIONER DIBRUGARH_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 635 days beyond expected completion
Read more (1 more)Show less- Implementing agency has a 77% delay rate across its projects
| DIBRUGARH | ₹25.00 L | MEDIUM 54 | |
| 17 | Construction of Ashok Path bye-lane-3 Roads & Paving — DIBRUGARH(DEPUTY COMMISSIONER DIBRUGARH_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 720 days beyond expected completion
Read more (1 more)Show less- Implementing agency has a 77% delay rate across its projects
| DIBRUGARH | ₹12.00 L | MEDIUM 52 | |
| 18 | Infrastructure development of Public Auditorium at Moran TE Community Buildings — DIBRUGARH(DEPUTY COMMISSIONER DIBRUGARH_IDA) - ₹1,500,000 against a ₹1,000,000 median for Community Buildings works in DIBRUGARH (50% above, 49 peer works)
- 618 days beyond expected completion
Read more (1 more)Show less- Implementing agency has a 77% delay rate across its projects
| DIBRUGARH | ₹15.00 L | MEDIUM 52 | |
| 19 | Construction of Nagakhelia Path Roads & Paving — DIBRUGARH(DEPUTY COMMISSIONER DIBRUGARH_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 720 days beyond expected completion
Read more (1 more)Show less- Implementing agency has a 77% delay rate across its projects
| DIBRUGARH | ₹10.00 L | MEDIUM 51 | |
| 20 | Construction of Baruah Pather Bye-Lane Roads & Paving — DIBRUGARH(DEPUTY COMMISSIONER DIBRUGARH_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 720 days beyond expected completion
Read more (1 more)Show less- Implementing agency has a 77% delay rate across its projects
| DIBRUGARH | ₹10.00 L | MEDIUM 51 | |
| 21 | Construction of Sashan Para bye-lane, near Dr. J. Dutta(R) Roads & Paving — DIBRUGARH(DEPUTY COMMISSIONER DIBRUGARH_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 720 days beyond expected completion
Read more (1 more)Show less- Implementing agency has a 77% delay rate across its projects
| DIBRUGARH | ₹10.00 L | MEDIUM 51 | |
| 22 | Construction of Jeuti Path Bye-Lane near Adv. Goswami(R) Roads & Paving — DIBRUGARH(DEPUTY COMMISSIONER DIBRUGARH_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 720 days beyond expected completion
Read more (1 more)Show less- Implementing agency has a 77% delay rate across its projects
| DIBRUGARH | ₹10.00 L | MEDIUM 51 | |
| 23 | Construction of Nandanpur Path Roads & Paving — DIBRUGARH(DEPUTY COMMISSIONER DIBRUGARH_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 720 days beyond expected completion
Read more (1 more)Show less- Implementing agency has a 77% delay rate across its projects
| DIBRUGARH | ₹10.00 L | MEDIUM 51 | |
| 24 | Construction of Boiragimoth bye-lane Roads & Paving — DIBRUGARH(DEPUTY COMMISSIONER DIBRUGARH_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 720 days beyond expected completion
Read more (1 more)Show less- Implementing agency has a 77% delay rate across its projects
| DIBRUGARH | ₹10.00 L | MEDIUM 51 | |
| 25 | Construction of Chapori Path bye-lane Roads & Paving — DIBRUGARH(DEPUTY COMMISSIONER DIBRUGARH_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 720 days beyond expected completion
Read more (1 more)Show less- Implementing agency has a 77% delay rate across its projects
| DIBRUGARH | ₹10.00 L | MEDIUM 51 | |