| 1 | Shri Krishnayan gaurakshashala sabal garh (Bhaguwala) Bijnor Community Buildings — BIJNOR(DISTRICT MAGISTRATE BIJNOR_IDA) - ₹4,997,529 against a ₹849,900 median for Community Buildings works in BIJNOR (488% above, 11 peer works)
- 169 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| BIJNOR | ₹49.98 L | HIGH 70
cost 25delay 23duplication 20 | |
| 2 | Interlinking construction work from Devidayal house to Vijay Religious & Cultural — UNNAO(DISTRICT MAGIISTRATE UNNAO_IDA) - ₹862,000 against a ₹194,818 median for Religious & Cultural works in UNNAO (342% above, 8 peer works)
- 213 days beyond expected completion
| UNNAO | ₹8.62 L | MEDIUM 55 | |
| 3 | Interlinking construction work from Kashiram asphalt road to Roads & Paving — UNNAO(DISTRICT MAGIISTRATE UNNAO_IDA) - ₹2,335,000 against a ₹1,282,620 median for Roads & Paving works in UNNAO (82% above, 113 peer works)
- 213 days beyond expected completion
| UNNAO | ₹23.35 L | MEDIUM 50 | |
| 4 | ?? ?? Other — UNNAO(DISTRICT MAGIISTRATE UNNAO_IDA) - ₹2,145,797 against a ₹957,221 median for Other works in UNNAO (124% above, 22 peer works)
- 100% similarity with another nearby work
| UNNAO | ₹21.46 L | MEDIUM 50
cost 25duplication 20agency 5 | |
| 5 | Trilokpur Rata Khera rasulpur me Baratshaala nirman karya. Community Buildings — UNNAO(DISTRICT MAGIISTRATE UNNAO_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 674 days beyond expected completion
Read more (1 more)Show less- 65% of this agency's ₹146,544,390 spend went to one vendor (DHIRENDRA SINGH), across 21 vendors and 177 transactions
| UNNAO | ₹11.80 L | MEDIUM 49 | |
| 6 | sainpur sagaura madarnagar road se deepu singh ke darwaje ta Roads & Paving — UNNAO(DISTRICT MAGIISTRATE UNNAO_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 674 days beyond expected completion
Read more (1 more)Show less- 65% of this agency's ₹146,544,390 spend went to one vendor (DHIRENDRA SINGH), across 21 vendors and 177 transactions
| UNNAO | ₹9.80 L | MEDIUM 49 | |
| 7 | gram sabha kuhumbhi me harijan basti me mohd. safi ke ghar s Religious & Cultural — UNNAO(DISTRICT MAGIISTRATE UNNAO_IDA) - ₹1,224,000 against a ₹194,818 median for Religious & Cultural works in UNNAO (528% above, 8 peer works)
- 132 days beyond expected completion
| UNNAO | ₹12.24 L | MEDIUM 48 | |
| 8 | Gram Bhartipur abadi bhag me 05 high mast light Street Lighting — UNNAO(DISTRICT MAGIISTRATE UNNAO_IDA) - ₹1,150,000 against a ₹270,000 median for Street Lighting works in UNNAO (326% above, 117 peer works)
- 132 days beyond expected completion
| UNNAO | ₹11.50 L | MEDIUM 48 | |
| 9 | BLOCK BIGHAPUR ME GRAM KATRA ME SARVAJANIK STHAL (DR. BHIMRA Boundary & Protection — UNNAO(DISTRICT MAGIISTRATE UNNAO_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 616 days beyond expected completion
Read more (1 more)Show less- 65% of this agency's ₹146,544,390 spend went to one vendor (DHIRENDRA SINGH), across 21 vendors and 177 transactions
| UNNAO | ₹9.75 L | MEDIUM 47 | |
| 10 | Chak nihali kheda me Sonu ke Engine ke thoda aage se Mauragi Roads & Paving — UNNAO(DISTRICT MAGIISTRATE UNNAO_IDA) - ₹2,500,000 against a ₹1,282,620 median for Roads & Paving works in UNNAO (95% above, 113 peer works)
- 132 days beyond expected completion
| UNNAO | ₹25.00 L | MEDIUM 47 | |
| 11 | Shri Krishnayan gaurakshashala sabal garh (Bhaguwala) Bijnor Community Buildings — BIJNOR(DISTRICT MAGISTRATE BIJNOR_IDA) - ₹4,997,529 against a ₹849,900 median for Community Buildings works in BIJNOR (488% above, 11 peer works)
- 100% similarity with another nearby work
| BIJNOR | ₹49.98 L | MEDIUM 47
cost 25duplication 20agency 2 | |
| 12 | CHANDRIKA MANDIR KE PASS EK HAND PUMP Water — UNNAO(DISTRICT MAGIISTRATE UNNAO_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 545 days beyond expected completion
Read more (1 more)Show less- 65% of this agency's ₹146,544,390 spend went to one vendor (DHIRENDRA SINGH), across 21 vendors and 177 transactions
| UNNAO | ₹58,000 | MEDIUM 45 | |
| 13 | Construction work of Baraatshaala in village Harikheda Majra Community Buildings — UNNAO(DISTRICT MAGIISTRATE UNNAO_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 213 days beyond expected completion
| UNNAO | ₹18.43 L | MEDIUM 44 | |
| 14 | Interlinking construction work from near the house of former Roads & Paving — UNNAO(DISTRICT MAGIISTRATE UNNAO_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 213 days beyond expected completion
| UNNAO | ₹17.31 L | MEDIUM 44 | |
| 15 | Block Sikandarpur karan me Gram panchayat dubeypur me Mahars Roads & Paving — UNNAO(DISTRICT MAGIISTRATE UNNAO_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 213 days beyond expected completion
| UNNAO | ₹15.78 L | MEDIUM 43 | |
| 16 | GRAM PANCHAYAT JAJAMAU KE GRAM MANNA NAGARI ME SHIV KUMAR KE Roads & Paving — UNNAO(DISTRICT MAGIISTRATE UNNAO_IDA) - 628 days beyond expected completion
- 65% of this agency's ₹146,544,390 spend went to one vendor (DHIRENDRA SINGH), across 21 vendors and 177 transactions
| UNNAO | ₹3.30 L | MEDIUM 43 | |
| 17 | NIHALIKHEDA JHAKARPUR MARG PANI KI TANKI KE PAAS HIGH MASK L Roads & Paving — UNNAO(DISTRICT MAGIISTRATE UNNAO_IDA) - 616 days beyond expected completion
- 65% of this agency's ₹146,544,390 spend went to one vendor (DHIRENDRA SINGH), across 21 vendors and 177 transactions
| UNNAO | ₹1.95 L | MEDIUM 42 | |
| 18 | MAHAVEERAN MANDIR KE PASS HIGH MASK LIGHT Religious & Cultural — UNNAO(DISTRICT MAGIISTRATE UNNAO_IDA) - 616 days beyond expected completion
- 65% of this agency's ₹146,544,390 spend went to one vendor (DHIRENDRA SINGH), across 21 vendors and 177 transactions
| UNNAO | ₹1.95 L | MEDIUM 42 | |
| 19 | SADAR ME SHARDA CITY ME RAJESH KE GHAR KE SAMNE HIGH MASK LI Street Lighting — UNNAO(DISTRICT MAGIISTRATE UNNAO_IDA) - 616 days beyond expected completion
- 65% of this agency's ₹146,544,390 spend went to one vendor (DHIRENDRA SINGH), across 21 vendors and 177 transactions
| UNNAO | ₹1.95 L | MEDIUM 42 | |
| 20 | KISHORIKHEDA CHAURAHE PAR HIGH MASK LIGHT Street Lighting — UNNAO(DISTRICT MAGIISTRATE UNNAO_IDA) - 616 days beyond expected completion
- 65% of this agency's ₹146,544,390 spend went to one vendor (DHIRENDRA SINGH), across 21 vendors and 177 transactions
| UNNAO | ₹1.95 L | MEDIUM 42 | |
| 21 | DHANIKHEDA SAGWAR MARG PA KANY UCCHH PRIMARY SCHOOL KE PASS Roads & Paving — UNNAO(DISTRICT MAGIISTRATE UNNAO_IDA) - 616 days beyond expected completion
- 65% of this agency's ₹146,544,390 spend went to one vendor (DHIRENDRA SINGH), across 21 vendors and 177 transactions
| UNNAO | ₹1.95 L | MEDIUM 42 | |
| 22 | GRAM POST PURA NISF PANSARI HAR SIDDH MATA MANDIR KE PASS HI Religious & Cultural — UNNAO(DISTRICT MAGIISTRATE UNNAO_IDA) - 616 days beyond expected completion
- 65% of this agency's ₹146,544,390 spend went to one vendor (DHIRENDRA SINGH), across 21 vendors and 177 transactions
| UNNAO | ₹1.95 L | MEDIUM 42 | |
| 23 | VIKAS KHAND NAWABGANJ ME KUSHERI MATA MANDIR KE PASS HIGH MA Religious & Cultural — UNNAO(DISTRICT MAGIISTRATE UNNAO_IDA) - 616 days beyond expected completion
- 65% of this agency's ₹146,544,390 spend went to one vendor (DHIRENDRA SINGH), across 21 vendors and 177 transactions
| UNNAO | ₹1.95 L | MEDIUM 42 | |
| 24 | GOKUL BABA MANDIR KE PASS HIGH MASK LIGHT Religious & Cultural — UNNAO(DISTRICT MAGIISTRATE UNNAO_IDA) - 616 days beyond expected completion
- 65% of this agency's ₹146,544,390 spend went to one vendor (DHIRENDRA SINGH), across 21 vendors and 177 transactions
| UNNAO | ₹1.95 L | MEDIUM 42 | |
| 25 | CONSTRUCTION OF LIBRARY AT SCHOOL GROUND FLOOR Education — UNNAO(DISTRICT MAGIISTRATE UNNAO_IDA) - 553 days beyond expected completion
- 65% of this agency's ₹146,544,390 spend went to one vendor (DHIRENDRA SINGH), across 21 vendors and 177 transactions
| UNNAO | ₹3.00 L | MEDIUM 42 | |