| 1 | Laying of RCC Pipeline at Village Birpind, Block Nakodar, Di Water — JALANDHAR(DEPUTY COMMISSIONER JALANDHAR_IDA) - ₹2,500,000 against a ₹365,800 median for Water works in JALANDHAR (583% above, 251 peer works)
- 250 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- 1 payment still in progress, oldest 718 days
| JALANDHAR | ₹25.00 L | HIGH 85
cost 25delay 25duplication 20 | |
| 2 | Construction of Community Centre Community Buildings — JALANDHAR(DEPUTY COMMISSIONER JALANDHAR_IDA) - ₹600,000 against a ₹300,000 median for Community Buildings works in JALANDHAR (100% above, 81 peer works)
- 142 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- 1 payment still in progress, oldest 718 days
| JALANDHAR | ₹6.00 L | HIGH 79
cost 25duplication 20delay 20 | |
| 3 | Construction of building for the New Operation Theatre Compl Health — JALANDHAR(DEPUTY COMMISSIONER JALANDHAR_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 216 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- 1 payment still in progress, oldest 718 days
| JALANDHAR | ₹20.00 L | HIGH 74
delay 25duplication 20agency 15 | |
| 4 | Construction of Guru Hargobind Sahib Sports Park in Village- Sports — RUPNAGAR(DEPUTY COMMISSIONER ROOPNAGAR_IDA) - ₹5,000,000 against a ₹300,000 median for Sports works in RUPNAGAR (1567% above, 63 peer works)
- 250 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| RUPNAGAR | ₹50.00 L | HIGH 73
cost 25delay 25duplication 20 | |
| 5 | Construction of Guru Hargobind Sahib Sports Park in Village- Sports — RUPNAGAR(DEPUTY COMMISSIONER ROOPNAGAR_IDA) - ₹5,000,000 against a ₹300,000 median for Sports works in RUPNAGAR (1567% above, 63 peer works)
- 250 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| RUPNAGAR | ₹50.00 L | HIGH 73
cost 25delay 25duplication 20 | |
| 6 | Laying of RCC Pipeline at Village Birpind, Block Nakodar, Di Water — JALANDHAR(DEPUTY COMMISSIONER JALANDHAR_IDA) - ₹2,500,000 against a ₹365,800 median for Water works in JALANDHAR (583% above, 251 peer works)
- 250 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| JALANDHAR | ₹25.00 L | HIGH 73
cost 25delay 25duplication 20 | |
| 7 | Construction of Bathrooms in Shree Guru Ravidass Community H Community Buildings — JALANDHAR(DEPUTY COMMISSIONER JALANDHAR_IDA) - ₹1,000,000 against a ₹300,000 median for Community Buildings works in JALANDHAR (233% above, 81 peer works)
- 90 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- 1 payment still in progress, oldest 718 days
| JALANDHAR | ₹10.00 L | HIGH 72
cost 25duplication 20agency 15 | |
| 8 | Completion of Road Construction from Skoda Showroom NH ONE t Roads & Paving — KAPURTHALA(DEPUTY COMMISSIONER KAPURTHALA_IDA) - ₹1,000,000 against a ₹500,000 median for Roads & Paving works in KAPURTHALA (100% above, 44 peer works)
- 126 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| KAPURTHALA | ₹10.00 L | MEDIUM 68
cost 25duplication 20delay 18 | |
| 9 | Completion of Road Construction from Skoda Showroom NH ONE t Roads & Paving — KAPURTHALA(DEPUTY COMMISSIONER KAPURTHALA_IDA) - ₹1,000,000 against a ₹500,000 median for Roads & Paving works in KAPURTHALA (100% above, 44 peer works)
- 126 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| KAPURTHALA | ₹10.00 L | MEDIUM 68
cost 25duplication 20delay 18 | |
| 10 | Construction of Community Centre Community Buildings — JALANDHAR(DEPUTY COMMISSIONER JALANDHAR_IDA) - ₹600,000 against a ₹300,000 median for Community Buildings works in JALANDHAR (100% above, 81 peer works)
- 142 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| JALANDHAR | ₹6.00 L | MEDIUM 68
cost 25duplication 20delay 20 | |
| 11 | construction of rooms in Chandrashekhar Azad Prathmik Vidyal Education — SULTANPUR(DISTRICT MAGISTRATE SULTANPUR_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 387 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- Implementing agency has a 42% delay rate across its projects
| SULTANPUR | ₹20.00 L | MEDIUM 67
delay 25duplication 20cost 16 | |
| 12 | construction of rooms in Chandrashekhar Azad Prathmik Vidyal Education — SULTANPUR(DISTRICT MAGISTRATE SULTANPUR_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 387 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- Implementing agency has a 42% delay rate across its projects
| SULTANPUR | ₹20.00 L | MEDIUM 67
delay 25duplication 20cost 16 | |
| 13 | Upgradation of Cremation Ground (Sand filling on Child buria Boundary & Protection — JALANDHAR(DEPUTY COMMISSIONER JALANDHAR_IDA) - 184 days beyond expected completion
- 100% similarity with another nearby work
Read more (1 more)Show less- 1 payment still in progress, oldest 718 days
| JALANDHAR | ₹4.65 L | MEDIUM 66
delay 25duplication 20agency 15 | |
| 14 | Construction of building for the New Operation Theatre Compl Health — JALANDHAR(DEPUTY COMMISSIONER JALANDHAR_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 216 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| JALANDHAR | ₹20.00 L | MEDIUM 62
delay 25duplication 20cost 14 | |
| 15 | Construction of Bathrooms in Shree Guru Ravidass Community H Community Buildings — JALANDHAR(DEPUTY COMMISSIONER JALANDHAR_IDA) - ₹1,000,000 against a ₹300,000 median for Community Buildings works in JALANDHAR (233% above, 81 peer works)
- 90 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| JALANDHAR | ₹10.00 L | MEDIUM 60
cost 25duplication 20delay 13 | |
| 16 | installation of solar light in the village-hasanpur, dist- s Street Lighting — SULTANPUR(DISTRICT MAGISTRATE SULTANPUR_IDA) - 387 days beyond expected completion
- 100% similarity with another nearby work
Read more (1 more)Show less- Implementing agency has a 42% delay rate across its projects
| SULTANPUR | ₹5.00 L | MEDIUM 60
delay 25duplication 20cost 9 | |
| 17 | installation of solar light in the village-hasanpur, dist- s Street Lighting — SULTANPUR(DISTRICT MAGISTRATE SULTANPUR_IDA) - 387 days beyond expected completion
- 100% similarity with another nearby work
Read more (1 more)Show less- Implementing agency has a 42% delay rate across its projects
| SULTANPUR | ₹5.00 L | MEDIUM 60
delay 25duplication 20cost 9 | |
| 18 | Construction of Classrooms (halls) in Cantt.Board Boys Sr. S Education — JALANDHAR(DEPUTY COMMISSIONER JALANDHAR_IDA) - ₹1,500,000 against a ₹478,289 median for Education works in JALANDHAR (214% above, 33 peer works)
- 100% similarity with another nearby work
Read more (1 more)Show less- 1 payment still in progress, oldest 718 days
| JALANDHAR | ₹15.00 L | MEDIUM 60
cost 25duplication 20agency 15 | |
| 19 | Purchase of 02 Medical Equipments for wound healing with com Equipment & Vehicles — JALANDHAR(DEPUTY COMMISSIONER JALANDHAR_IDA) - ₹2,000,000 against a ₹214,995 median for Equipment & Vehicles works in JALANDHAR (830% above, 35 peer works)
- 100% similarity with another nearby work
Read more (1 more)Show less- 1 payment still in progress, oldest 718 days
| JALANDHAR | ₹20.00 L | MEDIUM 60
cost 25duplication 20agency 15 | |
| 20 | Construction of structures of cremation ground in Harnam Das Religious & Cultural — JALANDHAR(DEPUTY COMMISSIONER JALANDHAR_IDA) - ₹4,957,030 against a ₹300,000 median for Religious & Cultural works in JALANDHAR (1552% above, 51 peer works)
- 100% similarity with another nearby work
Read more (1 more)Show less- 1 payment still in progress, oldest 718 days
| JALANDHAR | ₹49.57 L | MEDIUM 60
cost 25duplication 20agency 15 | |
| 21 | Construction of structures of cremation ground (Shed for cre Community Buildings — JALANDHAR(DEPUTY COMMISSIONER JALANDHAR_IDA) - ₹4,989,000 against a ₹300,000 median for Community Buildings works in JALANDHAR (1563% above, 81 peer works)
- 100% similarity with another nearby work
Read more (1 more)Show less- 1 payment still in progress, oldest 718 days
| JALANDHAR | ₹49.89 L | MEDIUM 60
cost 25duplication 20agency 15 | |
| 22 | Construction work on cremation ground in Ram Bagh, Deep Naga Religious & Cultural — JALANDHAR(DEPUTY COMMISSIONER JALANDHAR_IDA) - ₹9,998,224 against a ₹300,000 median for Religious & Cultural works in JALANDHAR (3233% above, 51 peer works)
- 100% similarity with another nearby work
Read more (1 more)Show less- 1 payment still in progress, oldest 718 days
| JALANDHAR | ₹99.98 L | MEDIUM 60
cost 25duplication 20agency 15 | |
| 23 | Maintenance of Crematorium structures in Krishanpura, Jaland Religious & Cultural — JALANDHAR(DEPUTY COMMISSIONER JALANDHAR_IDA) - ₹4,996,091 against a ₹300,000 median for Religious & Cultural works in JALANDHAR (1565% above, 51 peer works)
- 100% similarity with another nearby work
Read more (1 more)Show less- 1 payment still in progress, oldest 718 days
| JALANDHAR | ₹49.96 L | MEDIUM 60
cost 25duplication 20agency 15 | |
| 24 | construction of community hall in above mentioned NGO Community Buildings — JALANDHAR(DEPUTY COMMISSIONER JALANDHAR_IDA) - ₹997,135 against a ₹300,000 median for Community Buildings works in JALANDHAR (232% above, 81 peer works)
- 100% similarity with another nearby work
Read more (1 more)Show less- 1 payment still in progress, oldest 718 days
| JALANDHAR | ₹9.97 L | MEDIUM 60
cost 25duplication 20agency 15 | |
| 25 | (i) Sewer Suction Machine having capacity of 6000 ltr capa Drainage & Sanitation — JALANDHAR(DEPUTY COMMISSIONER JALANDHAR_IDA) - ₹8,987,658 against a ₹500,000 median for Drainage & Sanitation works in JALANDHAR (1698% above, 19 peer works)
- 100% similarity with another nearby work
Read more (1 more)Show less- 1 payment still in progress, oldest 718 days
| JALANDHAR | ₹89.88 L | MEDIUM 60
cost 25duplication 20agency 15 | |