| 1 | Common work sheds Community Buildings — Uttar Bastar Kanker(DISTRICT COLLECTOR KANKER_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 765 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- 56% of this agency's ₹53,357,768 spend went to one vendor (Samriddhi Enterprises), across 53 vendors and 113 transactions
| UTTAR BASTAR KANKER | ₹5.00 L | MEDIUM 64
delay 25duplication 20cost 12 | |
| 2 | Common work sheds Community Buildings — Uttar Bastar Kanker(DISTRICT COLLECTOR KANKER_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 765 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- 56% of this agency's ₹53,357,768 spend went to one vendor (Samriddhi Enterprises), across 53 vendors and 113 transactions
| UTTAR BASTAR KANKER | ₹3.00 L | MEDIUM 63
delay 25duplication 20cost 12 | |
| 3 | Community halls Community Buildings — Uttar Bastar Kanker(DISTRICT COLLECTOR KANKER_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 738 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- 56% of this agency's ₹53,357,768 spend went to one vendor (Samriddhi Enterprises), across 53 vendors and 113 transactions
| UTTAR BASTAR KANKER | ₹5.00 L | MEDIUM 63
delay 25duplication 20cost 11 | |
| 4 | Common work sheds Community Buildings — Uttar Bastar Kanker(DISTRICT COLLECTOR KANKER_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 733 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- 56% of this agency's ₹53,357,768 spend went to one vendor (Samriddhi Enterprises), across 53 vendors and 113 transactions
| UTTAR BASTAR KANKER | ₹2.00 L | MEDIUM 62
delay 25duplication 20cost 11 | |
| 5 | Community halls Community Buildings — Uttar Bastar Kanker(DISTRICT COLLECTOR KANKER_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 716 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- 56% of this agency's ₹53,357,768 spend went to one vendor (Samriddhi Enterprises), across 53 vendors and 113 transactions
| UTTAR BASTAR KANKER | ₹5.00 L | MEDIUM 62
delay 25duplication 20cost 10 | |
| 6 | Common word sheds Community Buildings — Uttar Bastar Kanker(DISTRICT COLLECTOR KANKER_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 710 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- 56% of this agency's ₹53,357,768 spend went to one vendor (Samriddhi Enterprises), across 53 vendors and 113 transactions
| UTTAR BASTAR KANKER | ₹5.00 L | MEDIUM 62
delay 25duplication 20cost 10 | |
| 7 | Cultural bulding Community Buildings — KONDAGAON(DISTRICT COLLECTOR KONDAGAON_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 763 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| KONDAGAON | ₹3.00 L | MEDIUM 62
delay 25duplication 20cost 12 | |
| 8 | Common work sheds(Teena sheds) Community Buildings — Uttar Bastar Kanker(DISTRICT COLLECTOR KANKER_IDA) - 621 days beyond expected completion
- 100% similarity with another nearby work
Read more (1 more)Show less- 56% of this agency's ₹53,357,768 spend went to one vendor (Samriddhi Enterprises), across 53 vendors and 113 transactions
| UTTAR BASTAR KANKER | ₹2.00 L | MEDIUM 59
delay 25duplication 20cost 7 | |
| 9 | Common work sheds Community Buildings — KONDAGAON(DISTRICT COLLECTOR KONDAGAON_IDA) - 705 days beyond expected completion
- 100% similarity with another nearby work
| KONDAGAON | ₹3.00 L | MEDIUM 59
delay 25duplication 20cost 9 | |
| 10 | Common work sheds(Teena sheds) Community Buildings — Uttar Bastar Kanker(DISTRICT COLLECTOR KANKER_IDA) - 615 days beyond expected completion
- 100% similarity with another nearby work
Read more (1 more)Show less- 56% of this agency's ₹53,357,768 spend went to one vendor (Samriddhi Enterprises), across 53 vendors and 113 transactions
| UTTAR BASTAR KANKER | ₹3.00 L | MEDIUM 59
delay 25duplication 20cost 7 | |
| 11 | Community culturul activities Other — Uttar Bastar Kanker(DISTRICT COLLECTOR KANKER_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 742 days beyond expected completion
Read more (1 more)Show less- 56% of this agency's ₹53,357,768 spend went to one vendor (Samriddhi Enterprises), across 53 vendors and 113 transactions
| UTTAR BASTAR KANKER | ₹6.00 L | MEDIUM 45 | |
| 12 | Yatri Prratichhalay Community Buildings — Uttar Bastar Kanker(DISTRICT COLLECTOR KANKER_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 733 days beyond expected completion
Read more (1 more)Show less- 56% of this agency's ₹53,357,768 spend went to one vendor (Samriddhi Enterprises), across 53 vendors and 113 transactions
| UTTAR BASTAR KANKER | ₹6.00 L | MEDIUM 44 | |
| 13 | Community buildings Cultural Community Buildings — Uttar Bastar Kanker(DISTRICT COLLECTOR KANKER_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 738 days beyond expected completion
Read more (1 more)Show less- 56% of this agency's ₹53,357,768 spend went to one vendor (Samriddhi Enterprises), across 53 vendors and 113 transactions
| UTTAR BASTAR KANKER | ₹3.00 L | MEDIUM 42 | |
| 14 | Community center bulding Community Buildings — KONDAGAON(DISTRICT COLLECTOR KONDAGAON_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 763 days beyond expected completion
| KONDAGAON | ₹3.00 L | MEDIUM 42 | |
| 15 | Aditional Rooms Education — Uttar Bastar Kanker(DISTRICT COLLECTOR KANKER_IDA) - 707 days beyond expected completion
- 56% of this agency's ₹53,357,768 spend went to one vendor (Samriddhi Enterprises), across 53 vendors and 113 transactions
| UTTAR BASTAR KANKER | ₹2.00 L | MEDIUM 41 | |