| 1 | SANSKRITIK BHAWAN NIRMAN KARY Community Buildings — BILASPUR(DISTRICT COLLECTOR BILASPUR_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 731 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| BILASPUR | ₹5.00 L | MEDIUM 62
delay 25duplication 20cost 11 | |
| 2 | SANSKRITIK MANCH NIRMAN KARY Religious & Cultural — BILASPUR(DISTRICT COLLECTOR BILASPUR_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 731 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| BILASPUR | ₹2.50 L | MEDIUM 61
delay 25duplication 20cost 10 | |
| 3 | SANSKRITIK MANCH NIRMAN KARY Religious & Cultural — BILASPUR(DISTRICT COLLECTOR BILASPUR_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 731 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| BILASPUR | ₹2.50 L | MEDIUM 61
delay 25duplication 20cost 10 | |
| 4 | SANSKRITIK BHAWAN NIRMAN KARY Community Buildings — BILASPUR(DISTRICT COLLECTOR BILASPUR_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 712 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| BILASPUR | ₹5.00 L | MEDIUM 61
delay 25duplication 20cost 10 | |
| 5 | SANSKRITIK BHAWAN NIRMAN KARY Community Buildings — BILASPUR(DISTRICT COLLECTOR BILASPUR_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 712 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| BILASPUR | ₹5.00 L | MEDIUM 61
delay 25duplication 20cost 10 | |
| 6 | SANSKRITIK BHAWAN NIRMAN KARY Community Buildings — BILASPUR(DISTRICT COLLECTOR BILASPUR_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 712 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| BILASPUR | ₹5.00 L | MEDIUM 61
delay 25duplication 20cost 10 | |
| 7 | SANSKRITIK BHAWAN NIRMAN KARY Community Buildings — MUNGELI(Collector Mungeli_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 712 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| MUNGELI | ₹5.00 L | MEDIUM 58
delay 25duplication 20cost 10 | |
| 8 | SANSKRITIK BHAWAN NIRMAN KARY Community Buildings — MUNGELI(Collector Mungeli_IDA) - 712 days beyond expected completion
- 100% similarity with another nearby work
| MUNGELI | ₹2.50 L | MEDIUM 57
delay 25duplication 20cost 9 | |
| 9 | C.C.ROAD NIRMAN KARY (KHAIRWAR PARA MANDIR CHAUK SE MUKHY RO Roads & Paving — BILASPUR(DISTRICT COLLECTOR BILASPUR_IDA) - ₹500,000 against a ₹200,000 median for Roads & Paving works in BILASPUR (150% above, 157 peer works)
- 731 days beyond expected completion
| BILASPUR | ₹5.00 L | MEDIUM 55 | |
| 10 | C.C.NALI NIRMAN KARY Drainage & Sanitation — BILASPUR(DISTRICT COLLECTOR BILASPUR_IDA) - ₹500,000 against a ₹200,000 median for Drainage & Sanitation works in BILASPUR (150% above, 9 peer works)
- 731 days beyond expected completion
| BILASPUR | ₹5.00 L | MEDIUM 55 | |
| 11 | Near Bhakta Mata Karma Bhawan Khamtarai Community Buildings — BILASPUR(DISTRICT COLLECTOR BILASPUR_IDA) - ₹1,000,000 against a ₹500,000 median for Community Buildings works in BILASPUR (100% above, 93 peer works)
- 740 days beyond expected completion
| BILASPUR | ₹10.00 L | MEDIUM 55 | |
| 12 | First Floor, Community Hall Community Buildings — BILASPUR(DISTRICT COLLECTOR BILASPUR_IDA) - ₹1,000,000 against a ₹500,000 median for Community Buildings works in BILASPUR (100% above, 93 peer works)
- 100% similarity with another nearby work
| BILASPUR | ₹10.00 L | MEDIUM 50
cost 25duplication 20agency 5 | |
| 13 | C.C.ROAD NIRMAN KARY Roads & Paving — BILASPUR(DISTRICT COLLECTOR BILASPUR_IDA) - ₹500,000 against a ₹200,000 median for Roads & Paving works in BILASPUR (150% above, 157 peer works)
- 100% similarity with another nearby work
| BILASPUR | ₹5.00 L | MEDIUM 50
cost 25duplication 20agency 5 | |
| 14 | SANSKRITIK BHAWAN NIRMAN KARY Community Buildings — BILASPUR(DISTRICT COLLECTOR BILASPUR_IDA) - ₹999,872 against a ₹500,000 median for Community Buildings works in BILASPUR (100% above, 93 peer works)
- 100% similarity with another nearby work
| BILASPUR | ₹10.00 L | MEDIUM 50
cost 25duplication 20agency 5 | |
| 15 | C.C.ROAD NIRMAN KARY Roads & Paving — BILASPUR(DISTRICT COLLECTOR BILASPUR_IDA) - ₹375,000 against a ₹200,000 median for Roads & Paving works in BILASPUR (88% above, 157 peer works)
- 100% similarity with another nearby work
| BILASPUR | ₹3.75 L | MEDIUM 47
cost 22duplication 20agency 5 | |
| 16 | SANSKRITIK MANCH NIRMAN KARY (WARD NO.05, MATA CHAURA MANDIR Religious & Cultural — BILASPUR(DISTRICT COLLECTOR BILASPUR_IDA) - ₹500,000 against a ₹300,000 median for Religious & Cultural works in BILASPUR (67% above, 32 peer works)
- 712 days beyond expected completion
| BILASPUR | ₹5.00 L | MEDIUM 47 | |
| 17 | SANSKRITIK MANCH SAH ATIRIKT KAKSH NIRMAN KARY Religious & Cultural — BILASPUR(DISTRICT COLLECTOR BILASPUR_IDA) - ₹500,000 against a ₹300,000 median for Religious & Cultural works in BILASPUR (67% above, 32 peer works)
- 731 days beyond expected completion
| BILASPUR | ₹5.00 L | MEDIUM 47 | |
| 18 | Kali Mandir Chowk, in front of Kotwar's house Khamtarai Religious & Cultural — BILASPUR(DISTRICT COLLECTOR BILASPUR_IDA) - ₹500,000 against a ₹300,000 median for Religious & Cultural works in BILASPUR (67% above, 32 peer works)
- 740 days beyond expected completion
| BILASPUR | ₹5.00 L | MEDIUM 47 | |
| 19 | Cultural Forum Near Siddha Bab, Nawaganv (salka) Religious & Cultural — BILASPUR(DISTRICT COLLECTOR BILASPUR_IDA) - ₹500,000 against a ₹300,000 median for Religious & Cultural works in BILASPUR (67% above, 32 peer works)
- 740 days beyond expected completion
| BILASPUR | ₹5.00 L | MEDIUM 47 | |
| 20 | Near Bilasa Hostel Science College Sarkanda Education — BILASPUR(DISTRICT COLLECTOR BILASPUR_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 740 days beyond expected completion
| BILASPUR | ₹5.00 L | MEDIUM 42 | |
| 21 | Tatidhar Other — BILASPUR(DISTRICT COLLECTOR BILASPUR_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 740 days beyond expected completion
| BILASPUR | ₹5.00 L | MEDIUM 42 | |
| 22 | C.C.ROAD NIRMAN KARY (PULER DUKAN SE NARAYAN KE DUKAN TAK) Roads & Paving — BILASPUR(DISTRICT COLLECTOR BILASPUR_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 731 days beyond expected completion
| BILASPUR | ₹2.00 L | MEDIUM 41 | |
| 23 | SANSKRITIK MANCH NIRMAN KARY (TALAB KE PASS) MATIYARI (BELTA Water — BILASPUR(DISTRICT COLLECTOR BILASPUR_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 731 days beyond expected completion
| BILASPUR | ₹2.00 L | MEDIUM 41 | |
| 24 | SANSKRITIK MANCH NIRMAN KARY (DHANUHAR MOHALLA ME) Religious & Cultural — BILASPUR(DISTRICT COLLECTOR BILASPUR_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 731 days beyond expected completion
| BILASPUR | ₹2.00 L | MEDIUM 41 | |
| 25 | SANSKRITIK MANCH NIRMAN KARY (DAIHANPARA ME) Religious & Cultural — BILASPUR(DISTRICT COLLECTOR BILASPUR_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 731 days beyond expected completion
| BILASPUR | ₹2.00 L | MEDIUM 41 | |