| 1 | Near Shanti Nagar Society, MIDC. Construction of pergola and Roads & Paving — MUMBAI SUBURBAN(DISTRICT COLLECTOR MUMBAI SUBURBAN_IDA) - ₹4,500,000 against a ₹2,000,000 median for Roads & Paving works in MUMBAI SUBURBAN (125% above, 272 peer works)
- 635 days beyond expected completion
Read more (1 more)Show less- Implementing agency has a 61% delay rate across its projects
| MUMBAI SUBURBAN | ₹45.00 L | MEDIUM 59 | |
| 2 | Construction of shed walkway at Hanjar Nagar, Pump House And Community Buildings — MUMBAI SUBURBAN(DISTRICT COLLECTOR MUMBAI SUBURBAN_IDA) - ₹4,000,000 against a ₹2,000,000 median for Community Buildings works in MUMBAI SUBURBAN (100% above, 60 peer works)
- 635 days beyond expected completion
Read more (1 more)Show less- Implementing agency has a 61% delay rate across its projects
| MUMBAI SUBURBAN | ₹40.00 L | MEDIUM 59 | |
| 3 | Construction of aqueducts, drains and footpaths at Tanaji Na Roads & Paving — MUMBAI SUBURBAN(DISTRICT COLLECTOR MUMBAI SUBURBAN_IDA) - ₹4,000,000 against a ₹2,000,000 median for Roads & Paving works in MUMBAI SUBURBAN (100% above, 272 peer works)
- 635 days beyond expected completion
Read more (1 more)Show less- Implementing agency has a 61% delay rate across its projects
| MUMBAI SUBURBAN | ₹40.00 L | MEDIUM 59 | |
| 4 | Construction of Sabhamandap shed, drains and footpaths at Va Roads & Paving — MUMBAI SUBURBAN(DISTRICT COLLECTOR MUMBAI SUBURBAN_IDA) - ₹4,500,000 against a ₹2,000,000 median for Roads & Paving works in MUMBAI SUBURBAN (125% above, 272 peer works)
- 635 days beyond expected completion
Read more (1 more)Show less- Implementing agency has a 61% delay rate across its projects
| MUMBAI SUBURBAN | ₹45.00 L | MEDIUM 59 | |
| 5 | Construction of sheds, gutters and footpaths at Malad (East) Roads & Paving — MUMBAI SUBURBAN(DISTRICT COLLECTOR MUMBAI SUBURBAN_IDA) - ₹4,000,000 against a ₹2,000,000 median for Roads & Paving works in MUMBAI SUBURBAN (100% above, 272 peer works)
- 635 days beyond expected completion
Read more (1 more)Show less- Implementing agency has a 61% delay rate across its projects
| MUMBAI SUBURBAN | ₹40.00 L | MEDIUM 59 | |
| 6 | Construction of auditorium, drains and footpaths at Mhada Po Roads & Paving — MUMBAI SUBURBAN(DISTRICT COLLECTOR MUMBAI SUBURBAN_IDA) - ₹4,000,000 against a ₹2,000,000 median for Roads & Paving works in MUMBAI SUBURBAN (100% above, 272 peer works)
- 635 days beyond expected completion
Read more (1 more)Show less- Implementing agency has a 61% delay rate across its projects
| MUMBAI SUBURBAN | ₹40.00 L | MEDIUM 59 | |
| 7 | Construction of toilet drains and footpaths at Shankar Warli Roads & Paving — MUMBAI SUBURBAN(DISTRICT COLLECTOR MUMBAI SUBURBAN_IDA) - ₹3,000,000 against a ₹2,000,000 median for Roads & Paving works in MUMBAI SUBURBAN (50% above, 272 peer works)
- 635 days beyond expected completion
Read more (1 more)Show less- Implementing agency has a 61% delay rate across its projects
| MUMBAI SUBURBAN | ₹30.00 L | MEDIUM 53 | |
| 8 | Reconstruction of toilet at C Ward, Municipal Colony, Santos Drainage & Sanitation — MUMBAI SUBURBAN(DISTRICT COLLECTOR MUMBAI SUBURBAN_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 635 days beyond expected completion
Read more (1 more)Show less- Implementing agency has a 61% delay rate across its projects
| MUMBAI SUBURBAN | ₹30.00 L | MEDIUM 53 | |
| 9 | Dhirubhai Brahma Bhatt Park, Near Ambe Mata Mandir, Jawahar Roads & Paving — MUMBAI SUBURBAN(DISTRICT COLLECTOR MUMBAI SUBURBAN_IDA) - ₹3,000,000 against a ₹2,000,000 median for Roads & Paving works in MUMBAI SUBURBAN (50% above, 272 peer works)
- 635 days beyond expected completion
Read more (1 more)Show less- Implementing agency has a 61% delay rate across its projects
| MUMBAI SUBURBAN | ₹30.00 L | MEDIUM 53 | |
| 10 | Construction of assembly shed, drains and footpaths at Bande Roads & Paving — MUMBAI SUBURBAN(DISTRICT COLLECTOR MUMBAI SUBURBAN_IDA) - ₹3,000,000 against a ₹2,000,000 median for Roads & Paving works in MUMBAI SUBURBAN (50% above, 272 peer works)
- 635 days beyond expected completion
Read more (1 more)Show less- Implementing agency has a 61% delay rate across its projects
| MUMBAI SUBURBAN | ₹30.00 L | MEDIUM 53 | |
| 11 | Construction of Kindergarten, Sewers and Footpaths at Rajiv Roads & Paving — MUMBAI SUBURBAN(DISTRICT COLLECTOR MUMBAI SUBURBAN_IDA) - ₹3,000,000 against a ₹2,000,000 median for Roads & Paving works in MUMBAI SUBURBAN (50% above, 272 peer works)
- 635 days beyond expected completion
Read more (1 more)Show less- Implementing agency has a 61% delay rate across its projects
| MUMBAI SUBURBAN | ₹30.00 L | MEDIUM 53 | |
| 12 | Construction of toilets, drains and footpaths at Laxman Naga Roads & Paving — MUMBAI SUBURBAN(DISTRICT COLLECTOR MUMBAI SUBURBAN_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 635 days beyond expected completion
Read more (1 more)Show less- Implementing agency has a 61% delay rate across its projects
| MUMBAI SUBURBAN | ₹25.00 L | MEDIUM 52 | |
| 13 | Construction of assembly hall shed, drains and footpaths at Roads & Paving — MUMBAI SUBURBAN(DISTRICT COLLECTOR MUMBAI SUBURBAN_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 635 days beyond expected completion
Read more (1 more)Show less- Implementing agency has a 61% delay rate across its projects
| MUMBAI SUBURBAN | ₹25.00 L | MEDIUM 52 | |
| 14 | Construction of Pickle Ball Court at Bangur Nagar, Goregaon Sports — MUMBAI SUBURBAN(DISTRICT COLLECTOR MUMBAI SUBURBAN_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 635 days beyond expected completion
Read more (1 more)Show less- Implementing agency has a 61% delay rate across its projects
| MUMBAI SUBURBAN | ₹25.00 L | MEDIUM 52 | |
| 15 | Construction of levee, drains and footpaths at Western Expre Roads & Paving — MUMBAI SUBURBAN(DISTRICT COLLECTOR MUMBAI SUBURBAN_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 635 days beyond expected completion
Read more (1 more)Show less- Implementing agency has a 61% delay rate across its projects
| MUMBAI SUBURBAN | ₹25.00 L | MEDIUM 52 | |
| 16 | Unit no. Construction of toilet sewers and footpaths at 32, Roads & Paving — MUMBAI SUBURBAN(DISTRICT COLLECTOR MUMBAI SUBURBAN_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 635 days beyond expected completion
Read more (1 more)Show less- Implementing agency has a 61% delay rate across its projects
| MUMBAI SUBURBAN | ₹20.00 L | MEDIUM 51 | |
| 17 | Construction of drains, footpaths and levees at Bandrekar Wa Roads & Paving — MUMBAI SUBURBAN(DISTRICT COLLECTOR MUMBAI SUBURBAN_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 635 days beyond expected completion
Read more (1 more)Show less- Implementing agency has a 61% delay rate across its projects
| MUMBAI SUBURBAN | ₹20.00 L | MEDIUM 51 | |
| 18 | Construction of water channels, sewers and footpaths at Shiv Roads & Paving — MUMBAI SUBURBAN(DISTRICT COLLECTOR MUMBAI SUBURBAN_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 635 days beyond expected completion
Read more (1 more)Show less- Implementing agency has a 61% delay rate across its projects
| MUMBAI SUBURBAN | ₹20.00 L | MEDIUM 51 | |