| 1 | Tubewell installation at Ballpura, Sumel Gram Panchayat, Ad Water — JAIPUR(DISTRICT COLLECTOR JAIPUR_IDA) - ₹700,000 against a ₹298,950 median for Water works in JAIPUR (134% above, 53 peer works)
- 567 days beyond expected completion
Read more (1 more)Show less- 6 payments still in progress, oldest 442 days
| JAIPUR | ₹7.00 L | MEDIUM 61 | |
| 2 | Tubewell installation at Talai ki Dhani,, Sumel Gram Panchay Water — JAIPUR(DISTRICT COLLECTOR JAIPUR_IDA) - ₹700,000 against a ₹298,950 median for Water works in JAIPUR (134% above, 53 peer works)
- 567 days beyond expected completion
Read more (1 more)Show less- 6 payments still in progress, oldest 442 days
| JAIPUR | ₹7.00 L | MEDIUM 61 | |
| 3 | For installation of tube well in Shaheed Hemu Kalani Park, S Water — JAIPUR(DISTRICT COLLECTOR JAIPUR_IDA) - ₹700,000 against a ₹298,950 median for Water works in JAIPUR (134% above, 53 peer works)
- 584 days beyond expected completion
Read more (1 more)Show less- 6 payments still in progress, oldest 442 days
| JAIPUR | ₹7.00 L | MEDIUM 58 | |
| 4 | Renovation work of community building of Azad Basti in Kisha Community Buildings — JAIPUR(DISTRICT COLLECTOR JAIPUR_IDA) - ₹2,000,000 against a ₹700,000 median for Community Buildings works in JAIPUR (186% above, 102 peer works)
- 643 days beyond expected completion
Read more (1 more)Show less- 6 payments still in progress, oldest 442 days
| JAIPUR | ₹20.00 L | MEDIUM 58 | |
| 5 | For the construction work of "Centre of Excellence" building Community Buildings — JAIPUR(DISTRICT COLLECTOR JAIPUR_IDA) - ₹5,000,000 against a ₹700,000 median for Community Buildings works in JAIPUR (614% above, 102 peer works)
- 731 days beyond expected completion
Read more (1 more)Show less- 6 payments still in progress, oldest 442 days
| JAIPUR | ₹50.00 L | MEDIUM 58 | |
| 6 | For the construction of tin shed at the place of prayer in K Education — JAIPUR(DISTRICT COLLECTOR JAIPUR_IDA) - ₹2,000,000 against a ₹700,000 median for Education works in JAIPUR (186% above, 116 peer works)
- 734 days beyond expected completion
Read more (1 more)Show less- 6 payments still in progress, oldest 442 days
| JAIPUR | ₹20.00 L | MEDIUM 58 | |
| 7 | Construction of building in Faculty of Modern Knowledge Scie Education — JAIPUR(DISTRICT COLLECTOR JAIPUR_IDA) - ₹5,000,000 against a ₹700,000 median for Education works in JAIPUR (614% above, 116 peer works)
- 734 days beyond expected completion
Read more (1 more)Show less- 6 payments still in progress, oldest 442 days
| JAIPUR | ₹50.00 L | MEDIUM 58 | |
| 8 | E-library construction work at Shri Rajput Sabha Bhawan, Bha Roads & Paving — JAIPUR(DISTRICT COLLECTOR JAIPUR_IDA) - ₹2,000,000 against a ₹775,138 median for Roads & Paving works in JAIPUR (158% above, 89 peer works)
- 741 days beyond expected completion
Read more (1 more)Show less- 6 payments still in progress, oldest 442 days
| JAIPUR | ₹20.00 L | MEDIUM 58 | |
| 9 | Road construction work in Krishna Nagar Colony in Ward 20 un Roads & Paving — JAIPUR(DISTRICT COLLECTOR JAIPUR_IDA) - ₹2,000,000 against a ₹775,138 median for Roads & Paving works in JAIPUR (158% above, 89 peer works)
- 741 days beyond expected completion
Read more (1 more)Show less- 6 payments still in progress, oldest 442 days
| JAIPUR | ₹20.00 L | MEDIUM 58 | |
| 10 | Road construction work in the lanes of Ranjeev Puri in Ward Roads & Paving — JAIPUR(DISTRICT COLLECTOR JAIPUR_IDA) - ₹2,000,000 against a ₹775,138 median for Roads & Paving works in JAIPUR (158% above, 89 peer works)
- 741 days beyond expected completion
Read more (1 more)Show less- 6 payments still in progress, oldest 442 days
| JAIPUR | ₹20.00 L | MEDIUM 58 | |
| 11 | Road construction work at Ward 24 Santaji Marg, Lakshminaray Roads & Paving — JAIPUR(DISTRICT COLLECTOR JAIPUR_IDA) - ₹2,000,000 against a ₹775,138 median for Roads & Paving works in JAIPUR (158% above, 89 peer works)
- 741 days beyond expected completion
Read more (1 more)Show less- 6 payments still in progress, oldest 442 days
| JAIPUR | ₹20.00 L | MEDIUM 58 | |
| 12 | Road construction and patchwork work at Priests' Chowk of Wa Roads & Paving — JAIPUR(DISTRICT COLLECTOR JAIPUR_IDA) - ₹2,000,000 against a ₹775,138 median for Roads & Paving works in JAIPUR (158% above, 89 peer works)
- 741 days beyond expected completion
Read more (1 more)Show less- 6 payments still in progress, oldest 442 days
| JAIPUR | ₹20.00 L | MEDIUM 58 | |
| 13 | construction work in Ward 18 under Hawamahal Assembly Consti Roads & Paving — JAIPUR(DISTRICT COLLECTOR JAIPUR_IDA) - ₹2,000,000 against a ₹775,138 median for Roads & Paving works in JAIPUR (158% above, 89 peer works)
- 741 days beyond expected completion
Read more (1 more)Show less- 6 payments still in progress, oldest 442 days
| JAIPUR | ₹20.00 L | MEDIUM 58 | |
| 14 | Construction work of meeting hall in Shaheed Himmat Singh Sh Education — JAIPUR(DISTRICT COLLECTOR JAIPUR_IDA) - ₹2,000,000 against a ₹700,000 median for Education works in JAIPUR (186% above, 116 peer works)
- 741 days beyond expected completion
Read more (1 more)Show less- 6 payments still in progress, oldest 442 days
| JAIPUR | ₹20.00 L | MEDIUM 58 | |
| 15 | "For the development of Shaheed Hemu Kalani Park located in Sports — JAIPUR(DISTRICT COLLECTOR JAIPUR_IDA) - ₹1,500,000 against a ₹856,390 median for Sports works in JAIPUR (75% above, 12 peer works)
- 738 days beyond expected completion
Read more (1 more)Show less- 6 payments still in progress, oldest 442 days
| JAIPUR | ₹15.00 L | MEDIUM 52 | |
| 16 | Construction work of new sewer line by removing the old/dama Drainage & Sanitation — JAIPUR(DISTRICT COLLECTOR JAIPUR_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 741 days beyond expected completion
Read more (1 more)Show less- 6 payments still in progress, oldest 442 days
| JAIPUR | ₹20.00 L | MEDIUM 51 | |
| 17 | "
For the work of replacement of sewerage lines in Shivam Ap Drainage & Sanitation — JAIPUR(DISTRICT COLLECTOR JAIPUR_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 730 days beyond expected completion
Read more (1 more)Show less- 6 payments still in progress, oldest 442 days
| JAIPUR | ₹20.00 L | MEDIUM 51 | |
| 18 | Samudayik Kendra construction work in Sunder Nagar-P, Muhana Roads & Paving — JAIPUR(DISTRICT COLLECTOR JAIPUR_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 741 days beyond expected completion
Read more (1 more)Show less- 6 payments still in progress, oldest 442 days
| JAIPUR | ₹10.00 L | MEDIUM 48 | |
| 19 | Assembly Constituency Vidyadhar Nagar Ward No. In 19 for asp Roads & Paving — JAIPUR(DISTRICT COLLECTOR JAIPUR_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 741 days beyond expected completion
Read more (1 more)Show less- 6 payments still in progress, oldest 442 days
| JAIPUR | ₹10.00 L | MEDIUM 48 | |
| 20 | For the construction work of Yoga Sadhana Hall on the first Roads & Paving — JAIPUR(DISTRICT COLLECTOR JAIPUR_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 736 days beyond expected completion
Read more (1 more)Show less- 6 payments still in progress, oldest 442 days
| JAIPUR | ₹10.00 L | MEDIUM 48 | |
| 21 | For construction of class rooms in Government Upper Primary Roads & Paving — JAIPUR(DISTRICT COLLECTOR JAIPUR_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 736 days beyond expected completion
Read more (1 more)Show less- 6 payments still in progress, oldest 442 days
| JAIPUR | ₹10.00 L | MEDIUM 48 | |
| 22 | For installation of inter locking tiles on both sides of the Roads & Paving — JAIPUR(DISTRICT COLLECTOR JAIPUR_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 738 days beyond expected completion
Read more (1 more)Show less- 6 payments still in progress, oldest 442 days
| JAIPUR | ₹10.00 L | MEDIUM 48 | |
| 23 | For construction of road and square of block tiles in Ward 9 Roads & Paving — JAIPUR(DISTRICT COLLECTOR JAIPUR_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 730 days beyond expected completion
Read more (1 more)Show less- 6 payments still in progress, oldest 442 days
| JAIPUR | ₹10.00 L | MEDIUM 48 | |
| 24 | For installation of interlocking tiles in 250 meters in fron Roads & Paving — JAIPUR(DISTRICT COLLECTOR JAIPUR_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 711 days beyond expected completion
Read more (1 more)Show less- 6 payments still in progress, oldest 442 days
| JAIPUR | ₹10.00 L | MEDIUM 48 | |
| 25 | CC road construction work in Ward No. 98 in Assembly Constit Roads & Paving — JAIPUR(DISTRICT COLLECTOR JAIPUR_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 736 days beyond expected completion
Read more (1 more)Show less- 6 payments still in progress, oldest 442 days
| JAIPUR | ₹8.00 L | MEDIUM 47 | |