For the construction work of Yoga Sadhana Hall on the first

Roads & Paving

Rajasthan / JAIPUR — JAIPUR(DISTRICT COLLECTOR JAIPUR_IDA) · Ramcharan Bohra (JAIPUR)

For the construction work of Yoga Sadhana Hall on the first floor of the community building of Sanjay Colony, Ward No. 32, Nehru Nagar, Police Academy Road, Civil Line Assembly Constituency.

Overall risk score
48/100
Blended from the five components below, each weighted as shown.
MEDIUM

Risk components

Cost60
Delay100
Duplication0
Agency55
Compliance0
Sanctioned
₹10.00 L
Delay
736d
Cost deviation
29%
Work status
Recommended

AI powered · gemini-flash-liteWhy was this flagged?

  • Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of rangeAI · Isolation Forest (scikit-learn)
  • 736 days beyond expected completionPublished dates
  • 6 payments still in progress, oldest 442 daysPayment records

Decision trail

Nobody has recorded a decision on this work yet.